Monthly State Let Construction Report For El Paso District As Of Sep 15, 2016 Page 2 Of 3

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway VA
From AT VARIOUS LOCATIONS IN EL PASO CO
To .
CSJ 0924-06-449
Proj ID STP 2015(042)
Work Type CONSTRUCT CURB RAMPS
 
1.000 1991412.68 0.00 2103093.95 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-03-14
Work Began 01-05-15
Work Completed  
Time Computed 11-19-14
Contract Working Days 226
Addl Days Granted 95
Working Days Charged 321
Percent Time Used 100
Contractor(s)
GARCOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-449
BOWEN INDUSTRIAL CONTRACTORS, INC. (4.01%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (5.42%)
TRI STATE ELECTRIC, LTD. ( 16.69%)
HENRY TRUJILLO, INC. (1.25%)
Contract # 09143023
Totals 1991412.68 0.00 2103093.95 99.9

CountyEL PASO
Highway CS
From ALBERTON AVE
To 200 FT S OF LTV RD
CSJ 0924-06-457
Proj ID STP 2015(455)MM
Work Type WIDEN ROAD
 
1.250 6591274.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-457
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163204
Totals 6591274.78 0.00 0.00 0.0

CountyEL PASO
Highway VA
From EL PASO COUNTYWIDE
To .
CSJ 0924-06-491
Proj ID CM 1602(500)
Work Type REGIONAL BIKE IMPROVEMENTS (ON ST)
 
36.052 324898.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-491
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163221
Totals 324898.83 0.00 0.00 0.0

CountyEL PASO
Highway CS
From SOCORRO CITY LIMITS
To .
CSJ 0924-06-520
Proj ID STP 2016(796)TP
Work Type SOCORRO SAFE ROUTES TO SCHOOL
 
2.830 373864.65 0.00 19440.09 5.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-28-16
Work Began 08-24-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 4
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-520
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163018
Totals 373864.65 0.00 19440.09 5.1

CountyBREWSTER
Highway VA
From VARIOUS LOCATIONS IN ALPINE AREA
To .
CSJ 0924-35-022
Proj ID NH 1602(501)
Work Type ALPINE BEAUTIFICATION PROJECT
 
1.000 202104.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-35-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163015
Totals 202104.08 0.00 0.00 0.0

CountyEL PASO
Highway SS 601
From AT LP 375 / SPUR 601
To .
CSJ 1046-03-006
Proj ID CM 1402(076)
Work Type INTERSECTION IMPROVEMENTS
 
0.500 879924.05 0.00 1493923.34 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-19-14
Work Began 04-20-15
Work Completed  
Time Computed 12-05-14
Contract Working Days 120
Addl Days Granted 26
Working Days Charged 143
Percent Time Used 97
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1046-03-006
C & C ROAD CONSTRUCTION, INC.( 42.50%)
TRI STATE ELECTRIC, LTD. (1.60%)
HORIZONE CONSTRUCTION I, LTD (2.75%)
NATIONWIDE REBAR INC (0.81%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.90%)
Contract # 09143039
Totals 879924.05 0.00 1493923.34 99.9

CountyEL PASO
Highway FM 1110
From AT IH 10
To .
CSJ 1281-02-006
Proj ID BR 2013(630)
Work Type REPLACE BRIDGE
 
0.339 9449138.14 174555.64 9858520.73 99.9
Work Order 09-30-14
Work Began 10-23-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 278
Addl Days Granted 159
Working Days Charged 433
Percent Time Used 99
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1281-02-006
PAVEMENT MARKINGS INC. (1.28%)
TRI STATE ELECTRIC, LTD. (7.72%)
HARDY HOLE DRILLING(0.03%)
HAWK CONSTRUCTION(3.84%)
HARDY HOLE DRILLING(3.69%)
SATARAIN CONSTRUCTION, INC.(3.21%)
HENRY TRUJILLO, INC. (0.17%)
HORIZONE CONSTRUCTION I, LTD ( 20.01%)
NATIONWIDE REBAR INC (0.17%)
A BROTHERS MILLING, LLC(0.49%)
CRANE SERVICES, INC. (0.39%)
FALC ENTERPRISES, LLC(0.01%)
PENHALL COMPANY(0.03%)
SCOTT DERR PAINTING CO (0.16%)
SATARAIN CONSTRUCTION, INC.(5.07%)
DUSTROL, INC.(0.04%)
Contract # 07143207
Totals 9449138.14 174555.64 9858520.73 99.9

CountyHUDSPETH
Highway RM 1111
From 0.5 MI N OF RM 1111/BI-10 INTERSEC
To RM 1111/BI-10 INTERSECTION
CSJ 1282-02-018
Proj ID BR 1502(393)
Work Type REPLACE STRUCTURE
 
0.621 1291694.00 0.00 1283800.19 99.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-05-15
Work Began 11-03-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 155
Percent Time Used 96
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1282-02-018
C & C ROAD CONSTRUCTION, INC.( 14.41%)
NATIONWIDE REBAR INC (3.68%)
HARDY HOLE DRILLING(7.32%)
SOUTHWESTERN INDUSTRIAL CONTRACTORS(0.61%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.48%)
V.C. HUFF, L.L.C.(0.44%)
Contract # 07153041
Totals 1291694.00 0.00 1283800.19 99.3

CountyHUDSPETH
Highway RM 1111 ETC
From US 62/180
To 0.3 MI N OF IH 10
CSJ 1282-02-025
Proj ID STP 2016(395)
Work Type PREVENTATIVE MAINTENANCE
 
151.746 4749629.99 2829158.94 3770384.09 79.3
Work Order 04-18-16
Work Began 00-00-00
Work Completed  
Time Computed 04-18-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 25
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1282-02-025
FLASHER EQUIPMENT COMPANY(2.05%)
DOUBLE A CONTRACTING, L.P. (5.27%)
Contract # 12153218
Totals 4749629.99 2829158.94 3770384.09 79.3

CountyCULBERSON
Highway RM 652
From US 62
To RM 1108
CSJ 1314-01-013
Proj ID STP 1502(035)
Work Type OVERLAY MAIN LANES
 
22.188 6142019.50 595642.00 756496.61 12.3
Work Order 04-20-15
Work Began 00-00-00
Work Completed  
Time Computed 05-21-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1314-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153033
Totals 6142019.50 595642.00 756496.61 12.3

CountyEL PASO
Highway IH 10
From @ MESA
To .
CSJ 2121-01-087
Proj ID STP 2015(221)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.313 458248.26 0.00 4442.02 0.9
CountyEL PASO
Highway IH 10
From 0.48 MI E OF SUNLAND PARK DR
To 0.45 MI E OF EXECUTIVE CENTER
CSJ 2121-02-132
Proj ID NH 2015(335)
Work Type REHABILITATION
 
2.836 2487085.09 0.00 3111.11 0.1
CountyEL PASO
Highway IH 10
From MESA STREET
To EXECUTIVE CENTER
CSJ 2121-02-137
Proj ID CBI 2015(220)
Work Type COLLECTOR DISTRIBUTOR LANES
 
5.164 151231706.19 0.00 47030206.97 25.8
CountyEL PASO
Highway IH 10
From MESA STREET
To EXECUTIVE CENTER
CSJ 2121-02-154
Proj ID ROW 2121-2-154
Work Type ACQUISITION AND UTILITIES
 
7.854 4601364.66 0.00 1868716.89 40.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-19-14
Work Began 04-06-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 1,211
Addl Days Granted 51
Working Days Charged 388
Percent Time Used 30
Contractor(s)
TRADECO INFRAESTRUCTURA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-137
ZTEX CONSTRUCTION, INC.(9.00%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.09%)
HARDY HOLE DRILLING(0.69%)
TRI STATE ELECTRIC, LTD. (1.25%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.69%)
SOUTHWESTERN INDUSTRIAL CONTRACTORS(0.21%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.02%)
HENRY TRUJILLO, INC. (0.01%)
A BROTHERS (OLD PRIME) (0.13%)
SUNDT CONSTRUCTION, INC. (0.00%)
TRI STATE ELECTRIC, LTD. ( 12.29%)
HARDY HOLE DRILLING(0.46%)
HARDY HOLE DRILLING(3.12%)
D"AMBRA CONSTRUCTION CORPORATION (0.10%)
PMI PAVEMENT MARKING, INC. (0.36%)
DH UNDERGROUND, INC. (0.63%)
ANTIGO CONSTRUCTION, INC.(0.04%)
ADVANCED CONCRETE SAWING & SEALING, LLC(0.34%)
ALLIED PAVING CO.(0.64%)
REBAR REINFORCEMENT PLACERS(6.83%)
EARTH REINFORCEMENT SPECIALISTS(0.99%)
CHOCTAW ERECTORS, INC. (2.49%)
SCOTT DERR PAINTING CO, LLC(0.42%)
LEEDSMAN CONSTRUCTION, INC.(1.19%)
HENRY TRUJILLO, INC. (1.14%)
BORDER DRILLING LLC(0.06%)
CRANE SERVICES, INC. (0.01%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.84%)
CANO STRUCTURES, LLC (0.81%)
KEN"S PORTABLE WELDING (0.01%)
PENHALL COMPANY(0.25%)
HERNANDEZ CONCRETE PUMPING (0.13%)
A BROTHERS MILLING, LLC(0.05%)
Contract # 10143001
Totals 158778404.20 0.00 48906476.99 25.8

CountyEL PASO
Highway IH 10
From WESTWAY
To LP 375
CSJ 2121-01-088
Proj ID STP 1402(077)MM
Work Type REHAB AND OPERATIONAL IMPROVEMENTS
 
3.402 6031177.20 0.00 6103502.49 99.9
CountyEL PASO
Highway IH 10
From WESTWAY
To LP 375
CSJ 2121-01-093
Proj ID ROW 2121-1-93
Work Type UTILITY ADJUSTMENTS
 
3.402 56652.00 0.00 56652.00 99.9
Work Order 11-14-14
Work Began 01-12-15
Work Completed  
Time Computed 11-30-14
Contract Working Days 248
Addl Days Granted 0
Working Days Charged 248
Percent Time Used 100
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2121-01-088
SATARAIN CONSTRUCTION, INC.(7.54%)
TRAFFIC BARRICADE SERVICE, INC.(2.41%)
TRI STATE ELECTRIC, LTD. (8.90%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.26%)
HARDY HOLE DRILLING(1.20%)
PMI PAVEMENT MARKING, INC. (1.36%)
SANCHEZ CONSTRUCTION CO. (4.87%)
NATIONWIDE REBAR INC (0.10%)
FALC ENTERPRISES, LLC(1.51%)
CRANE SERVICES, INC. (0.11%)
SANCHEZ CONSTRUCTION & LANDSCAPING (4.87%)
BORDER DRILLING LLC(0.19%)
Contract # 09143216
Totals 6087829.20 0.00 6160154.49 99.9

CountyEL PASO
Highway IH 10
From WESTWAY
To LP 375
CSJ 2121-01-092
Proj ID C 2121-1-92
Work Type REHAB AND OPERATIONAL IMPROVEMENTS
 
3.400 12757146.91 1060055.87 11086471.41 86.9
Work Order 11-02-15
Work Began 11-30-15
Work Completed  
Time Computed 11-30-15
Contract Working Days 206
Addl Days Granted 50
Working Days Charged 180
Percent Time Used 70
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2121-01-092
BOWEN INDUSTRIAL CONTRACTORS, INC. (1.77%)
TRAFFIC BARRICADE SERVICE, INC.(0.88%)
SANCHEZ CONSTRUCTION & LANDSCAPING (5.85%)
HAWK CONSTRUCTION(1.56%)
FALC ENTERPRISES, LLC(0.94%)
SATARAIN CONSTRUCTION, INC.(7.67%)
PMI PAVEMENT MARKING, INC. (0.53%)
TRI STATE ELECTRIC, LTD. ( 12.99%)
EARTH REINFORCEMENTS LLC (0.75%)
HARDY HOLE DRILLING(1.05%)
HAWK CONSTRUCTION(0.11%)
GREATER EL PASO SANDBLASTING (0.11%)
D"AMBRA CONSTRUCTION CORPORATION (2.55%)
HDW CONSTRUCTION & DRILLING, LLC.(0.21%)
BELT CON CONSTRUCTION, INC.(0.14%)
BORDER DRILLING LLC(0.19%)
Contract # 08153207
Totals 12757146.91 1060055.87 11086471.41 86.9

CountyEL PASO
Highway IH 10
From COPIA ST (LP 478)
To CHELSEA ST
CSJ 2121-02-146
Proj ID NH 2017(025)
Work Type INSTALL HIGH MAST LIGHTING
 
1.486 1399520.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-146
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163212
Totals 1399520.76 0.00 0.00 0.0

CountyEL PASO
Highway IH 10
From COPIA ST (LP 478)
To CHELSEA ST
CSJ 2121-02-151
Proj ID STP 2014(127)TE
Work Type ENHANCEMENT PROJECT
 
1.309 7584729.54 1200.00 9035495.46 99.9
Work Order 02-25-14
Work Began 04-01-14
Work Completed  
Time Computed 03-13-14
Contract Working Days 161
Addl Days Granted 100
Working Days Charged 261
Percent Time Used 100
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-151
HAWK CONSTRUCTION( 11.81%)
HARDY HOLE DRILLING(3.96%)
QUARRY HILLS, LTD. (0.13%)
HOWE PRECAST (0.40%)
EARTH REINFORCEMENT SPECIALISTS(2.79%)
HENRY TRUJILLO, INC. (1.44%)
APACHE BARRICADE & SIGN(2.33%)
BEAVER TREE SERVICE, INC.(0.22%)
NATIONWIDE REBAR INC (3.96%)
TRI STATE ELECTRIC, LTD. (1.60%)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.( 31.84%)
KEN"S PORTABLE WELDING (0.06%)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.(0.09%)
GREATER EL PASO SANDBLASTING ( 22.61%)
PEREZ ROCKWALL ( 16.66%)
MARQUEZ WROUGHT IRON (4.38%)
EL PASO CONCRETE CUTTERS, INC(0.14%)
Contract # 12133026
Totals 7584729.54 1200.00 9035495.46 99.9

CountyEL PASO
Highway IH 10
From PORFIRIO DIAZ ST
To MISSOURI AVE
CSJ 2121-02-152
Proj ID CC 2121-2-152
Work Type BRIDGE ENHANCEMENT
 
8.000 4677712.44 -1260.32 5767346.03 99.9
CountyEL PASO
Highway IH 10
From COPIA ST (LP 478)
To CHELSEA ST
CSJ 2121-02-155
Proj ID CC 2121-2-155
Work Type ENHANCEMENT PROJECT
 
1.309 4151891.90 186460.16 5540809.26 99.9
Work Order 05-22-14
Work Began 05-22-14
Work Completed  
Time Computed 06-07-14
Contract Working Days 218
Addl Days Granted 300
Working Days Charged 485
Percent Time Used 93
Contractor(s)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-02-152
TRAFFIC BARRICADE SERVICE, INC.(0.20%)
GREATER EL PASO SANDBLASTING ( 10.88%)
HAWK CONSTRUCTION(1.04%)
TRI STATE ELECTRIC, LTD. (9.33%)
WESTSIDE WELDING INC.( 27.11%)
S. ROBERT"S IRON WORKS, INC. (0.29%)
THOMAS INDUSTRIAL COATINGS, INC. (0.96%)
EL PASO CONCRETE CUTTERS, INC(0.67%)
UNIQUE CUSTOM DRYWALL AND PAINTING DBA LUIS SIMENTAL (1.55%)
G&G ENTERPRISE (1.49%)
KASCO(4.98%)
HARDY HOLE DRILLING(7.48%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.64%)
RIVERBEND CRANE & RIGGING(3.39%)
CANYON GLASS CO. (0.53%)
HERNANDEZ CONCRETE PUMPING (0.06%)
ELIAS CONCRETE (0.07%)
GORMAN MOISTURE PROTECTION (0.07%)
PEREZ ROCKWALL (1.18%)
MANNY CARRIZAL PAINTING CO., INC.(0.09%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.12%)
Contract # 04143208
Totals 8829604.34 185199.84 11308155.29 99.9

CountyEL PASO
Highway IH 10
From VISCOUNT BLVD.
To FM 659 (ZARAGOZA ROAD)
CSJ 2121-03-151
Proj ID CBI 2014(630)
Work Type ADD 1 LANE EACH DIRECTION
 
4.608 18068661.12 165746.91 21662301.55 99.9
Work Order 09-09-14
Work Began 09-22-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 316
Addl Days Granted 134
Working Days Charged 450
Percent Time Used 100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2121-03-151
TRI STATE ELECTRIC, LTD. ( 46.56%)
HARDY HOLE DRILLING(2.88%)
BORDER DRILLING LLC(0.16%)
PAVEMENT MARKINGS INC. (1.93%)
DUSTROL, INC.(0.07%)
HAWK CONSTRUCTION(3.99%)
SATARAIN CONSTRUCTION, INC.(0.78%)
FALC ENTERPRISES, LLC(0.07%)
MARTINEZ BROS. CONTRACTORS, LLC(6.53%)
GOMEZ, XAVIER(0.05%)
ALDERETE & ASSOCIATES ROCK AND WROUGHT IRON SPECIALTIES, INC (1.14%)
HENRY TRUJILLO, INC. (0.17%)
LESNA CONSTRUCTION, INC. (0.01%)
S & S BRIDGE PAINTING, INC.(1.05%)
NATIONWIDE REBAR INC (0.04%)
C&M PRECAST(3.48%)
PENHALL COMPANY(0.47%)
Contract # 07143203
Totals 18068661.12 165746.91 21662301.55 99.9

CountyEL PASO
Highway IH 10
From IH 10 @ LP 375
To .
CSJ 2121-04-093
Proj ID C 2121-4-93
Work Type INTCHG IMPRV INCL CONSTR DIRECT CON
 
1.399 31027042.95 0.00 29322525.15 94.5
CountyEL PASO
Highway IH 10
From IH 10 @ LP 375
To .
CSJ 2121-04-103
Proj ID ROW 2121-4-103
Work Type UTILITY ONLY
 
1.399 462325.00 0.00 462477.74 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-14
Work Began 04-15-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 519
Addl Days Granted 0
Working Days Charged 369
Percent Time Used 71
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 2121-04-093
CHOCTAW ERECTORS, INC. ( 13.81%)
TRI STATE ELECTRIC, LTD. (8.96%)
A BROTHERS MILLING, LLC(0.18%)
HARDY HOLE DRILLING(4.67%)
NATIONWIDE REBAR INC (0.28%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.98%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.99%)
PENHALL COMPANY(0.15%)
ACCURATE CORING, INC.(0.01%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.44%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.62%)
BORDER DRILLING LLC(0.09%)
ALLIED PAVING CO.(0.71%)
X GOMEZ TRANSPORTATION (0.43%)
CONCRETE PLACEMENT, INC. (0.33%)
PMI PAVEMENT MARKING, INC. (0.44%)
ER HAWKINS, LLC(0.19%)
SCOTT DERR PAINTING CO, LLC(0.49%)
GORMAN MOISTURE PROTECTION (0.04%)
Contract # 08143054
Totals 31489367.95 0.00 29785002.89 94.5

CountyEL PASO
Highway IH 10
From FM 659 (ZARAGOZA)
To EASTLAKE
CSJ 2121-04-098
Proj ID C 2121-4-98
Work Type WIDEN ROADWAY
 
3.220 12915901.72 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-02-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 271
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-04-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163003
Totals 12915901.72 0.00 0.00 0.0

CountyEL PASO
Highway FM 2529
From US 54
To SL 375
CSJ 2326-01-023
Proj ID NH 2015(385)
Work Type OVERLAY
 
5.875 1526309.97 0.00 1791578.89 99.9
Work Order 02-10-15
Work Began 08-24-15
Work Completed  
Time Computed 02-26-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2326-01-023
DUSTROL, INC.(2.64%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (1.61%)
FALC ENTERPRISES, LLC(0.00%)
PMI PAVEMENT MARKING, INC. (3.59%)
Contract # 12143010
Totals 1526309.97 0.00 1791578.89 99.9