Monthly Local Let Maintenance Report For Houston District As Of Dec 10, 2014 Page 6 Of 6

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBRAZORIA
Highway SH0288
From VARIOUS ROADWAYS IN BRAZORIA COUNTY
To VARIOUS ROADWAYS IN BRAZORIA COUNTY
CSJ 6278-61-001
Proj ID SUP - 627861001
Work Type LITTER REMOVAL
 
0.001 173504.05 2107.08 32603.50 18.7
Work Order 09-01-14
Work Began 09-22-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 22
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6278-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141231
Totals 173504.05 2107.08 32603.50 18.7

CountyHARRIS
Highway SH0249
From VARIOUS HWYS IN N. HARRIS COUNTY
To VARIOUS HWYS IN N. HARRIS COUNTY
CSJ 6278-65-001
Proj ID SUP - 627865001
Work Type LITTER REMOVAL
 
0.001 276978.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-14
Work Began 12-08-14
Work Completed  
Time Computed 12-05-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6278-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141230
Totals 276978.12 0.00 0.00 0.0

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6278-97-001
Proj ID SUP - 627897001
Work Type LITTER REMOVAL
 
0.001 169109.44 18528.86 35141.74 20.7
Work Order 00-00-00
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6278-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141230
Totals 169109.44 18528.86 35141.74 20.7

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6279-32-001
Proj ID RMC - 627932001
Work Type FULL DEPTH CONCRETE REPAIR
 
0.001 193350.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12141202
Totals 193350.00 0.00 0.00 0.0

CountyWALLER
Highway US0290
From VARIOUS RAODWAYS IN WALLER COUNTY
To VARIOUS ROADWAYS IN WALLER COUNTY
CSJ 6279-44-001
Proj ID RMC - 627944001
Work Type PUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.001 174800.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6279-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12141203
Totals 174800.00 0.00 0.00 0.0

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6279-93-001
Proj ID SUP - 627993001
Work Type LITTER REMOVAL
 
0.001 224966.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6279-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12141230
Totals 224966.79 0.00 0.00 0.0

CountyHARRIS
Highway IH0010
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6280-24-001
Proj ID SUP - 628024001
Work Type LITTER REMOVAL
 
0.001 289383.17 23160.14 23160.14 8.0
Work Order 10-06-14
Work Began 10-06-14
Work Completed  
Time Computed 10-06-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141231
Totals 289383.17 23160.14 23160.14 8.0

CountyMONTGOMERY
Highway US0059
From MONTGOMERY COUNTY AREA ENGINEER AND
To MAINTENANCE OFFICE
CSJ 6280-76-001
Proj ID SUP - 628076001
Work Type JANITORIAL MAINTENANCE
 
0.001 37989.36 2166.62 2166.62 5.7
Work Order 11-10-14
Work Began 11-10-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 3
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6280-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141231
Totals 37989.36 2166.62 2166.62 5.7

CountyHARRIS
Highway IH0010
From IH 10 WB MAINLANES
To OVER MCCARTY
CSJ 6282-32-001
Proj ID EMC - 628232001
Work Type EMERGENCY BRIDGE REPAIR
 
0.001 208148.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141240
Totals 208148.80 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6