Monthly Local Let Maintenance Report For Lufkin District As Of Jul 14, 2017 Page 2 Of 6

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRINITY
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToIN TRINITY COUNTY
CSJ6290-02-001
Proj IDRMC - 629002001
Work TypeGUARD FENCE, ATTENUATOR & MTL RAIL REPR
 
0.010142795.0069630.0048.7
Work Order00-00-00
Work Began10-28-15
Work Completed
Time Computed10-28-15
Contract Working Days200
Addl Days Granted0
Working Days Charged18
Percent Time Used9
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151106
Totals142795.003000.0069630.0048.7

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6290-78-001
Proj IDSUP - 629078001
Work TypeLANDSCAPE, PICNIC & GROUNDS MAINTENANCE
 
0.01076022.2576131.2599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-07-15
Work Began12-08-15
Work Completed
Time Computed12-07-15
Contract Working Days365
Addl Days Granted31
Working Days Charged391
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151130
Totals76022.250.0076131.2599.9

CountyANGELINA
HighwayUS0069
FromVARIOUS LOCATIONS IN THE
ToANGELINA COUNTY MAINTENANCE SECTION
CSJ6291-44-001
Proj IDRMC - 629144001
Work TypeTREE TRIM & BRUSH REMOVAL/TREE REMOVAL
 
0.010188111.32103377.5054.9
Work Order07-29-16
Work Began10-04-16
Work Completed
Time Computed10-04-16
Contract Working Days45
Addl Days Granted155
Working Days Charged59
Percent Time Used29
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151101
Totals188111.320.00103377.5054.9

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToNACOGDOCHES COUNTY
CSJ6293-53-001
Proj IDSUP - 629353001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01091371.1570680.4177.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days190
Addl Days Granted30
Working Days Charged144
Percent Time Used65
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6293-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151133
Totals91371.150.0070680.4177.3

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY
ToMAINTENANCE OFFICE
CSJ6294-12-001
Proj IDSUP - 629412001
Work TypeJANITORIAL MAINTENANCE
 
0.01010858.4110858.4199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6294-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151136
Totals10858.410.0010858.4199.9

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6296-20-001
Proj IDRMC - 629620001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010102832.5025423.7524.7
Work Order01-29-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged8
Percent Time Used4
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151104
Totals102832.503360.0025423.7524.7

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToPOLK COUNTY
CSJ6297-00-001
Proj IDRMC - 629700001
Work TypeTREE & BRUSH TRIMMING/REMOVAL OF TREES
 
0.010267850.01228490.0085.3
Work Order05-09-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged138
Percent Time Used69
Contractor(s)
FLORES TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161104
Totals267850.012710.00228490.0085.3

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6297-73-001
Proj IDRMC - 629773001
Work TypeLARGE SIGN MAINTENANCE
 
0.001183683.85182418.6499.3
Work Order08-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days30
Addl Days Granted0
Working Days Charged30
Percent Time Used100
Contractor(s)
SOUTH RANGER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161111
Totals183683.850.00182418.6499.3

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToLUFKIN DISTRICT
CSJ6297-74-001
Proj IDRMC - 629774001
Work TypeINSTALL SPOT PAINT AND BEAD STRIPING
 
0.001296250.00485804.1099.9
Work Order05-12-16
Work Began05-24-16
Work Completed
Time Computed05-24-16
Contract Working Days365
Addl Days Granted365
Working Days Charged403
Percent Time Used55
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6297-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161107
Totals296250.0052093.20485804.1099.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN ANGELINA,
ToHOUSTON AND NACOGDOCHES COUNTIES
CSJ6299-76-001
Proj IDRMC - 629976001
Work TypeINSTALL RAISED REFL PAVEMENT MARKERS
 
0.001210952.0061819.3529.3
Work Order06-08-16
Work Began06-15-16
Work Completed
Time Computed06-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged382
Percent Time Used52
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161108
Totals210952.003896.4261819.3529.3

CountySHELBY
HighwayUS0059
FromVARIOUS LOCATIONS IN SHELBY,
ToSAN AUGUSTINE AND SABINE COUNTIES
CSJ6299-77-001
Proj IDRMC - 629977001
Work TypeINSTALL RAISED REFL PAVEMENT MARKERS
 
0.001210952.0068794.3032.6
Work Order06-08-16
Work Began06-15-16
Work Completed
Time Computed06-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged382
Percent Time Used52
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161109
Totals210952.001707.4268794.3032.6

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK,
ToSAN JACINTO AND TRINITY COUNTIES
CSJ6299-78-001
Proj IDRMC - 629978001
Work TypeINSTALL RAISED REFL PAVEMENT MARKERS
 
0.001210952.0035371.2616.7
Work Order06-08-16
Work Began06-15-16
Work Completed
Time Computed06-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged382
Percent Time Used52
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161110
Totals210952.000.0035371.2616.7

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY MAINTENANCE SECTION
CSJ6300-07-001
Proj IDRMC - 630007001
Work TypeTREE REMOVAL AND TREE AND BRUSH TRIMMING
 
0.010258400.00127802.0049.4
Work Order00-00-00
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days200
Addl Days Granted0
Working Days Charged81
Percent Time Used40
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6300-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161105
Totals258400.0030513.00127802.0049.4

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS THROUGHOUT
ToTRINITY COUNTY
CSJ6300-98-001
Proj IDRMC - 630098001
Work TypeTREE REMOVAL AND TREE TRIM
 
0.010271080.00198349.3873.1
Work Order08-24-16
Work Began09-19-16
Work Completed
Time Computed09-19-16
Contract Working Days175
Addl Days Granted0
Working Days Charged132
Percent Time Used75
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161115
Totals271080.0021060.00198349.3873.1

CountyTRINITY
HighwayFM2781
FromVARIOUS LOCATIONS IN TRINITY & ANGELINA
ToMAINTENANCE SECTIONS
CSJ6301-20-001
Proj IDRMC - 630120001
Work TypeDRAINAGE REPAIR
 
0.010205367.9494784.4747.5
Work Order03-13-17
Work Began03-20-17
Work Completed
Time Computed03-20-17
Contract Working Days60
Addl Days Granted0
Working Days Charged65
Percent Time Used108
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171101
Totals205367.94907.5094784.4747.5

CountySHELBY
HighwayFM0414
From0.89 MILES NORTHEAST OF SH 87 ON THE
ToSOUTH SIDE OF FM 414
CSJ6301-55-001
Proj IDRMC - 630155001
Work TypeCULVERT INSTALLATION
 
0.010109175.00120789.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began07-26-16
Work Completed01-31-17
Time Computed07-18-16
Contract Working Days25
Addl Days Granted0
Working Days Charged25
Percent Time Used100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161101
Totals109175.000.00120789.00100.0

CountyNACOGDOCHES
HighwaySH0007
FromVARIOUS LOCATIONS WITHIN_THE
ToNACOGDOCHES COUNTY MAINTENANCE SECTION
CSJ6301-57-001
Proj IDRMC - 630157001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010190750.0045358.0023.7
Work Order11-30-16
Work Began12-02-16
Work Completed
Time Computed12-02-16
Contract Working Days200
Addl Days Granted0
Working Days Charged9
Percent Time Used4
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161106
Totals190750.0016880.0045358.0023.7

CountySHELBY
HighwaySH0007
From1.16 MILES WEST OF FM 711
To2.90 MILES WEST OF FM 711
CSJ6302-08-001
Proj IDEMC - 630208001
Work TypeEXCAVATION, TEMP SPCL SHORING, CULVERT
 
0.0102640798.752683877.2599.9
Work Order07-11-16
Work Began07-19-16
Work Completed
Time Computed07-12-16
Contract Working Days72
Addl Days Granted24
Working Days Charged93
Percent Time Used96
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6302-08-001
AR DANIEL CONSTRUCTION SERVICES, INC. (2.70)
DREWERY & WHEATON, LLC (3.61)
FREDONIA CONSTRUCTION SERVICES (0.37)
PANOLA SIGN & BARRICADE, INC. (0.49)
STRIPING TECHNOLOGY, L.P. (2.00)
OSCAR ORDUNO, INC. (8.62)
Contract #06161152
Totals2640798.750.002683877.2599.9

CountySHELBY
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6302-27-001
Proj IDSUP - 630227001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010101849.3967876.5066.6
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161135
Totals101849.394050.1567876.5066.6

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6302-28-001
Proj IDSUP - 630228001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010103351.3273808.3071.4
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged248
Percent Time Used67
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161114
Totals103351.326020.5373808.3071.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6