Monthly Local Let Maintenance Report For Lufkin District As Of Sep 21, 2017 Page 2 Of 6

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6290-78-001
Proj IDSUP - 629078001
Work TypeLANDSCAPE, PICNIC & GROUNDS MAINTENANCE
 
0.01076022.2576131.2599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-07-15
Work Began12-08-15
Work Completed
Time Computed12-07-15
Contract Working Days365
Addl Days Granted31
Working Days Charged391
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151130
Totals76022.250.0076131.2599.9

CountyANGELINA
HighwayUS0069
FromVARIOUS LOCATIONS IN THE
ToANGELINA COUNTY MAINTENANCE SECTION
CSJ6291-44-001
Proj IDRMC - 629144001
Work TypeTREE TRIM & BRUSH REMOVAL/TREE REMOVAL
 
0.010188111.32170267.5054.9
Work Order07-29-16
Work Began10-04-16
Work Completed
Time Computed10-04-16
Contract Working Days45
Addl Days Granted155
Working Days Charged59
Percent Time Used29
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151101
Totals188111.3266890.00170267.5054.9

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToNACOGDOCHES COUNTY
CSJ6293-53-001
Proj IDSUP - 629353001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01091371.1570680.4177.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days190
Addl Days Granted30
Working Days Charged144
Percent Time Used65
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6293-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151133
Totals91371.150.0070680.4177.3

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY
ToMAINTENANCE OFFICE
CSJ6294-12-001
Proj IDSUP - 629412001
Work TypeJANITORIAL MAINTENANCE
 
0.01010858.4110858.4199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6294-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151136
Totals10858.410.0010858.4199.9

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6296-20-001
Proj IDRMC - 629620001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010102832.5029746.2528.9
Work Order01-29-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged10
Percent Time Used5
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151104
Totals102832.501047.5029746.2528.9

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToPOLK COUNTY
CSJ6297-00-001
Proj IDRMC - 629700001
Work TypeTREE & BRUSH TRIMMING/REMOVAL OF TREES
 
0.010267850.01228490.00100.0
Work Order05-09-16
Work Began06-01-16
Work Completed09-19-17
Time Computed06-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged160
Percent Time Used80
Contractor(s)
FLORES TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161104
Totals267850.010.00228490.00100.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6297-73-001
Proj IDRMC - 629773001
Work TypeLARGE SIGN MAINTENANCE
 
0.001183683.85182418.6499.3
Work Order08-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days30
Addl Days Granted0
Working Days Charged30
Percent Time Used100
Contractor(s)
SOUTH RANGER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161111
Totals183683.850.00182418.6499.3

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToLUFKIN DISTRICT
CSJ6297-74-001
Proj IDRMC - 629774001
Work TypeINSTALL SPOT PAINT AND BEAD STRIPING
 
0.001296250.00530622.6099.9
Work Order05-12-16
Work Began05-24-16
Work Completed
Time Computed05-24-16
Contract Working Days365
Addl Days Granted365
Working Days Charged465
Percent Time Used63
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6297-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161107
Totals296250.008135.45530622.6099.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN ANGELINA,
ToHOUSTON AND NACOGDOCHES COUNTIES
CSJ6299-76-001
Proj IDRMC - 629976001
Work TypeINSTALL RAISED REFL PAVEMENT MARKERS
 
0.001210952.0061819.3529.3
Work Order06-08-16
Work Began06-15-16
Work Completed
Time Computed06-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged444
Percent Time Used60
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161108
Totals210952.000.0061819.3529.3

CountySHELBY
HighwayUS0059
FromVARIOUS LOCATIONS IN SHELBY,
ToSAN AUGUSTINE AND SABINE COUNTIES
CSJ6299-77-001
Proj IDRMC - 629977001
Work TypeINSTALL RAISED REFL PAVEMENT MARKERS
 
0.001210952.0068794.3032.6
Work Order06-08-16
Work Began06-15-16
Work Completed
Time Computed06-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged444
Percent Time Used60
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161109
Totals210952.000.0068794.3032.6

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK,
ToSAN JACINTO AND TRINITY COUNTIES
CSJ6299-78-001
Proj IDRMC - 629978001
Work TypeINSTALL RAISED REFL PAVEMENT MARKERS
 
0.001210952.0050053.4823.7
Work Order06-08-16
Work Began06-15-16
Work Completed
Time Computed06-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged444
Percent Time Used60
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6299-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161110
Totals210952.0010017.6650053.4823.7

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY MAINTENANCE SECTION
CSJ6300-07-001
Proj IDRMC - 630007001
Work TypeTREE REMOVAL AND TREE AND BRUSH TRIMMING
 
0.010258400.00134321.0051.9
Work Order00-00-00
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days200
Addl Days Granted0
Working Days Charged101
Percent Time Used50
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6300-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161105
Totals258400.003491.00134321.0051.9

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS THROUGHOUT
ToTRINITY COUNTY
CSJ6300-98-001
Proj IDRMC - 630098001
Work TypeTREE REMOVAL AND TREE TRIM
 
0.010271080.00215404.3879.4
Work Order08-24-16
Work Began09-19-16
Work Completed
Time Computed09-19-16
Contract Working Days175
Addl Days Granted0
Working Days Charged151
Percent Time Used86
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161115
Totals271080.0017055.00215404.3879.4

CountyTRINITY
HighwayFM2781
FromVARIOUS LOCATIONS IN TRINITY & ANGELINA
ToMAINTENANCE SECTIONS
CSJ6301-20-001
Proj IDRMC - 630120001
Work TypeDRAINAGE REPAIR
 
0.010205367.94150727.4080.8
Work Order03-13-17
Work Began03-20-17
Work Completed
Time Computed03-20-17
Contract Working Days60
Addl Days Granted0
Working Days Charged86
Percent Time Used143
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171101
Totals205367.942030.00150727.4080.8

CountySHELBY
HighwayFM0414
From0.89 MILES NORTHEAST OF SH 87 ON THE
ToSOUTH SIDE OF FM 414
CSJ6301-55-001
Proj IDRMC - 630155001
Work TypeCULVERT INSTALLATION
 
0.010109175.00120789.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began07-26-16
Work Completed01-31-17
Time Computed07-18-16
Contract Working Days25
Addl Days Granted0
Working Days Charged25
Percent Time Used100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161101
Totals109175.000.00120789.00100.0

CountyNACOGDOCHES
HighwaySH0007
FromVARIOUS LOCATIONS WITHIN_THE
ToNACOGDOCHES COUNTY MAINTENANCE SECTION
CSJ6301-57-001
Proj IDRMC - 630157001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010190750.0052273.0027.4
Work Order11-30-16
Work Began12-02-16
Work Completed
Time Computed12-02-16
Contract Working Days200
Addl Days Granted0
Working Days Charged10
Percent Time Used5
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161106
Totals190750.006915.0052273.0027.4

CountySHELBY
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6302-27-001
Proj IDSUP - 630227001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010101849.3983360.9681.8
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161135
Totals101849.397451.9183360.9681.8

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6302-28-001
Proj IDSUP - 630228001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010103351.3277255.7374.7
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged310
Percent Time Used84
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161114
Totals103351.32779.6177255.7374.7

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS WITHIN
ToHOUSTON COUNTY
CSJ6302-29-001
Proj IDSUP - 630229001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01058420.6345934.6978.6
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161111
Totals58420.63712.3645934.6978.6

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATION IN
ToTRINITY COUNTY
CSJ6302-30-001
Proj IDSUP - 630230001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01043866.9035974.3682.0
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6302-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161118
Totals43866.900.0035974.3682.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6