Monthly State Let Construction Report For Paris District As Of Jun 10, 2015 Page 1 Of 3

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHUNT
Highway SH 66 ETC
From COLLIN COUNTY LINE
To US 69
CSJ 0009-06-050
Proj ID STP 2015(325)
Work Type SEAL COAT
 
217.821 7694347.58 246319.60 854415.18 11.1
Work Order 01-27-15
Work Began 00-00-00
Work Completed  
Time Computed 05-01-15
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-06-050
STRIPE-A-ZONE, INC.( 14.45%)
Contract # 11143004
Totals 7694347.58 246319.60 854415.18 11.1

CountyHOPKINS
Highway IH 30 ETC
From SH 19
To TEXAS AVE IN SULPHUR SPRINGS
CSJ 0009-09-099
Proj ID STP 2015(079)HESG
Work Type HAZARD ELIMINATION & SAFETY
 
130.476 1210344.26 100860.80 152610.80 12.6
Work Order 02-18-15
Work Began 03-29-15
Work Completed  
Time Computed 03-06-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 38
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-099
STRIPING SYSTEMS, INC. (0.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.68%)
BRYDL CONTRACTING, INC.(2.54%)
COWBELL TRAFFIC SERVICES, INC. ( 21.73%)
NE-TEX CONSTRUCTION, LTD.(7.35%)
TEXOMA CONCRETE CUTTING, LLC (2.94%)
J & L PAVING (1.22%)
Contract # 09143029
Totals 1210344.26 100860.80 152610.80 12.6

CountyHUNT
Highway IH 30
From VARIOUS BRIDGE LOCATIONS IN HUNT CO
To .
CSJ 0009-13-161
Proj ID BR 1502(260)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.304 370171.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-161
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153020
Totals 370171.75 0.00 0.00 0.0

CountyFRANKLIN
Highway US 67
From 0.41 MI E OF SPUR 423
To TITUS C/L
CSJ 0010-05-022
Proj ID STP 2014(552)HRR
Work Type HAZARD ELIMINATION & SAFETY
 
5.284 2849816.37 2895.67 1836031.35 64.7
Work Order 04-25-14
Work Began 05-11-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 137
Percent Time Used 107
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-05-022
PANOLA SIGN & BARRICADE, INC.(0.50%)
MOORE CONSTRUCTION, INC. (1.19%)
CATOCON, INC.(2.93%)
J & M CONTRACTING, COMPANY ( 17.36%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.90%)
DUSTIN ALLEN, INC. (2.27%)
STRIPING TECHNOLOGY, L.P.(1.17%)
TEX OP CONSTRUCTION, LP(0.56%)
Contract # 03143212
Totals 2849816.37 2895.67 1836031.35 64.7

CountyLAMAR
Highway US 82
From FANNIN COUNTY LINE
To FM 38 EAST
CSJ 0045-08-036
Proj ID NH 2014(736)
Work Type WIDEN NON - FREEWAY
 
15.205 8860584.85 48565.40 4208914.68 47.5
Work Order 07-22-14
Work Began 08-08-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 157
Percent Time Used 69
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-08-036
MOORE CONSTRUCTION, INC. (1.84%)
SAMMY G. SMALLWOOD (1.03%)
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
HIGHWAY 19 CONSTRUCTION, LLC (0.71%)
BAHENA CONSTRUCTION CO.,INC. (5.99%)
DUSTROL, INC.(0.97%)
RK HALL, LLC ( 37.29%)
STRIPING TECHNOLOGY, L.P.(2.05%)
CATACON, INC.(2.39%)
RED SIXTEEN CONSTRUCTION, INC(0.30%)
Contract # 06143204
Totals 8860584.85 48565.40 4208914.68 47.5

CountyGRAYSON
Highway US 82
From 2180' W OF FM 1417 W (FRTG ONLY)
To FM 1417 W (FRONTAGE ONLY)
CSJ 0045-18-033
Proj ID NH 1402(083)
Work Type OVERLAY
 
3.428 1889024.62 105649.84 1819836.27 96.3
Work Order 10-02-14
Work Began 10-26-14
Work Completed  
Time Computed 10-18-14
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 88
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-18-033
ALTUS TRAFFIC MANAGEMENT LLC (0.72%)
DUSTROL, INC.(3.22%)
DUSTIN ALLEN, INC. (6.77%)
STRIPING TECHNOLOGY, L.P.(2.93%)
O. TREVINO CONSTRUCTION, LLC (5.70%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.06%)
Contract # 08143215
Totals 1889024.62 105649.84 1819836.27 96.3

CountyGRAYSON
Highway US 82
From FM 1897
To FANNIN COUNTY LINE
CSJ 0045-19-047
Proj ID C 45-19-47
Work Type WIDEN NON - FREEWAY
 
12.152 26059261.46 181950.98 25246928.60 96.8
Work Order 10-12-12
Work Began 11-15-12
Work Completed  
Time Computed 04-10-13
Contract Working Days 473
Addl Days Granted 0
Working Days Charged 446
Percent Time Used 94
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-047
BAHENA CONSTRUCTION CO.,INC. (3.42%)
FORTSON CONTRACTING, INC.(0.06%)
L & N BRIDGE, LLC(2.48%)
GARY A. CRAIN, INC.(0.01%)
LYON BARRICADE AND CONSTRUCTION CO.(0.18%)
MOORE CONSTRUCTION, INC. (0.65%)
MURRAY CONSTRUCTION(0.63%)
RK HALL, LLC ( 42.19%)
STRIPING TECHNOLOGY, L.P.(0.72%)
WEST TEXAS RUMBLE STRIP(0.06%)
WYLIE DRILLING & DRAINAGE, INC.(0.38%)
TEX OP CONSTRUCTION, LP(0.69%)
SOUTHEAST GRINDING & GROOVING, LLC (0.01%)
TEXAS SHAFTS, INC. (0.20%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.25%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.01%)
Contract # 08123201
Totals 26059261.46 181950.98 25246928.60 96.8

CountyRED RIVER
Highway US 82
From @ KICKAPOO CREEK
To .
CSJ 0046-01-061
Proj ID BR 1502(210)
Work Type BRIDGE REPLACEMENT
 
0.515 2651371.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153246
Totals 2651371.11 0.00 0.00 0.0

CountyGRAYSON
Highway SH 5
From COLLIN COUNTY LINE
To US 75
CSJ 0047-03-075
Proj ID STP 1402(084)
Work Type MISCELLANEOUS CONSTRUCTION
 
9.575 3711917.79 53962.32 720689.93 19.4
Work Order 11-12-14
Work Began 12-02-14
Work Completed  
Time Computed 02-10-15
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 55
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-075
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
MOORE CONSTRUCTION, INC. (0.26%)
WITHERS CONSTRUCTION, LLC(2.37%)
BAHENA CONSTRUCTION CO.,INC. (9.12%)
LONE STAR BARRIER SERVICES, LLC(0.77%)
TEXANA LAND & ASPHALT, INC.( 10.26%)
TEXAS ALTERNATIVE GRASSER, INC.(0.61%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(0.33%)
STRIPING TECHNOLOGY, L.P.(1.88%)
Contract # 09143041
Totals 3711917.79 53962.32 720689.93 19.4

CountyGRAYSON
Highway US 75
From FM 902
To SHEPHERD DRIVE
CSJ 0047-03-076
Proj ID C 47-3-76
Work Type REHABILITATION OF EXISTING ROADWAY
 
1.495 8342650.77 146502.00 7718031.18 92.9
Work Order 11-04-13
Work Began 01-27-14
Work Completed  
Time Computed 01-03-14
Contract Working Days 142
Addl Days Granted 27
Working Days Charged 205
Percent Time Used 121
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-076
BROCK ENVIRONMENTAL, LLC (0.10%)
DUSTROL, INC.(0.10%)
FORTSON CONTRACTING, INC.(0.14%)
ALTUS TRAFFIC MANAGEMENT LLC (0.18%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.24%)
SAMMY G. SMALLWOOD (0.42%)
W.O.E. CONSTRUCTION(0.44%)
STRIPING TECHNOLOGY, L.P.(1.00%)
ANTIGO CONSTRUCTION, INC.(0.38%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(1.29%)
VENUS CONSTRUCTION (4.15%)
MCL CONTRACTING, LLC (1.18%)
MABAK DIRECTIONAL DRILLING (0.08%)
ASPLUNDH TREE EXPERT CO(0.39%)
Contract # 08133224
Totals 8342650.77 146502.00 7718031.18 92.9

CountyGRAYSON
Highway US 75
From 1.65 MILES NORTH OF FM 1417
To FM 1417
CSJ 0047-03-077
Proj ID NH 2013(907)
Work Type MISCELLANEOUS CONSTRUCTION
 
1.650 739670.03 0.00 766794.03 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-13
Work Began 01-03-14
Work Completed 09-02-14
Time Computed 12-30-13
Contract Working Days 43
Addl Days Granted 5
Working Days Charged 48
Percent Time Used 100
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-077
CROSSROADS, L.P. (1.07%)
BRENDA PRICE TRUCKING(0.71%)
BROCK ENVIRONMENTAL, LLC (0.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.80%)
RK HALL, LLC ( 26.50%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.27%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (7.65%)
DUSTROL, INC.(3.21%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.23%)
GJ SEEDING, LLC(0.63%)
Contract # 08133028
Totals 739670.03 0.00 766794.03 100.0

CountyGRAYSON
Highway US 75
From @ LOY LAKE ROAD (SHERMAN)
To .
CSJ 0047-18-068
Proj ID NH 2013(908)
Work Type WIDEN NON - FREEWAY
 
0.434 5248890.96 230035.03 4740559.86 90.4
Work Order 01-06-14
Work Began 01-27-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 268
Addl Days Granted 24
Working Days Charged 302
Percent Time Used 103
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-068
TOTAL HIGHWAY MAINTENANCE, LLC (1.24%)
EROSION CONTROL MANAGEMENT SERVICES(0.09%)
S & S BRIDGE PAINTING, INC.(0.67%)
WYLIE DRILLING & DRAINAGE, INC.(1.37%)
CROSSROADS, L.P. (0.48%)
A BROTHERS MILLING, LLC(0.48%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (5.62%)
MCL CONTRACTING, LLC (0.55%)
W.O.E. CONSTRUCTION(0.54%)
LONE STAR BARRIER SERVICES, LLC(0.40%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.22%)
PEACHTREE CONSTRUCTION, LTD. (2.49%)
PLACIDO CONSTRUCTION COMPANY (0.57%)
T & R EXCAVATION, INC. (0.96%)
BRADCO, LLC(1.96%)
NORTH TEXAS DRILLING (0.01%)
S & S BORING (0.14%)
BATTEN DRILLING, INC.(0.06%)
Contract # 09133221
Totals 5248890.96 230035.03 4740559.86 90.4

CountyHOPKINS
Highway SH 19
From SH 11
To RAINS COUNTY LINE
CSJ 0108-09-043
Proj ID STP 2013(906)
Work Type SEAL COAT
 
16.672 1364788.07 0.00 1361508.10 99.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-13
Work Began 11-01-13
Work Completed  
Time Computed 11-04-13
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 98
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-09-043
PANOLA SIGN & BARRICADE, INC.(1.09%)
STRIPING TECHNOLOGY, L.P.(3.16%)
BAHENA CONSTRUCTION CO.,INC. (9.34%)
SAMMY G. SMALLWOOD (1.78%)
MOORE CONSTRUCTION, INC. (1.43%)
CATACON, INC.(1.88%)
Contract # 08133044
Totals 1364788.07 0.00 1361508.10 99.7

CountyDELTA
Highway SH 24
From FM 904
To FM 64
CSJ 0136-03-044
Proj ID TCSP 2010(387)
Work Type GR, STRS BS, & SURF
 
10.955 39277746.71 725471.85 10940427.19 27.8
Work Order 02-18-14
Work Began 08-20-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 598
Addl Days Granted 2
Working Days Charged 137
Percent Time Used 22
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0136-03-044
MOORE CONSTRUCTION, INC. (0.34%)
LYON BARRICADE AND CONSTRUCTION CO.(0.20%)
DUSTROL, INC.(0.04%)
HIGHWAY 19 CONSTRUCTION, LLC (6.50%)
FLAT LINE, INC.(0.80%)
NORTH TEXAS HYDRA-HAMMER, INC. (0.05%)
RK HALL, LLC ( 29.02%)
SAMMY G. SMALLWOOD (0.83%)
TEXAS ALTERNATIVE GRASSER, INC.(0.15%)
TEX OP CONSTRUCTION, LP(0.19%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 16.25%)
RED SIXTEEN CONSTRUCTION, INC(0.34%)
MCL CONTRACTING, LLC (0.08%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.19%)
Contract # 12133002
Totals 39277746.71 725471.85 10940427.19 27.8

CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-007
Proj ID BR 2012(716)
Work Type BRIDGE REPLACEMENT
 
0.570 11302230.33 0.00 10655580.91 94.2
CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-009
Proj ID BR 2012(792)
Work Type BRIDGE REPLACEMENT
 
0.360 1517866.78 0.00 1303102.21 85.8
CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-010
Proj ID CC 189-1-10
Work Type BRIDGE REPLACEMENT
 
0.360 1759959.64 0.00 1569049.83 89.1
Work Order 10-24-12
Work Began 02-05-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 495
Addl Days Granted 0
Working Days Charged 408
Percent Time Used 82
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0189-01-007
ATS DRILLING, INC. ( 14.68%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.91%)
SCOTT DERR PAINTING CO, LLC(0.20%)
TEX OP CONSTRUCTION, LP(0.22%)
RK HALL, LLC ( 12.53%)
SOUTHEAST GRINDING & GROOVING, LLC (0.09%)
MCL CONTRACTING, LLC (0.96%)
LYON BARRICADE AND CONSTRUCTION CO.(0.11%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.08%)
DUSTIN ALLEN, INC. (0.14%)
MCL CONTRACTING, LLC (2.18%)
STRIPING TECHNOLOGY, L.P.(0.39%)
Contract # 08123208
Totals 14580056.75 0.00 13527732.95 92.7

CountyRED RIVER
Highway SH 37
From 0.2 MI N OF US 82
To 0.2 MI S OF FM 195
CSJ 0189-02-050
Proj ID STP 2014(739)
Work Type OVERLAY
 
16.136 1186753.45 29467.90 1460000.97 99.9
Work Order 07-18-14
Work Began 10-22-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 186
Contractor(s)
VIKING CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0189-02-050
TRP CONSTRUCTION GROUP, LLC(5.97%)
COWBELL TRAFFIC SERVICES, INC. (1.46%)
PANOLA SIGN & BARRICADE, INC.(0.52%)
BRYDL CONTRACTING, INC.(0.37%)
Contract # 06143036
Totals 1186753.45 29467.90 1460000.97 99.9

CountyRAINS
Highway US 69
From 586FT NORTH OF FM 3299 INTERSECTION
To COUNTY ROAD 4530
CSJ 0203-03-042
Proj ID STP 1502(131)
Work Type OVERLAY
 
6.223 1742911.94 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0203-03-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153239
Totals 1742911.94 0.00 0.00 0.0

CountyRAINS
Highway US 69
From SH 19
To 586 NORTH OF FM 3299 INTERSECTION
CSJ 0203-03-044
Proj ID STP 1402(093)
Work Type MISCELLANEOUS CONSTRUCTION
 
3.240 4635055.96 2400.00 63468.52 1.3
Work Order 11-12-14
Work Began 02-26-15
Work Completed  
Time Computed 02-10-15
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 5
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0203-03-044
ALTUS TRAFFIC MANAGEMENT LLC (0.27%)
BAHENA CONSTRUCTION CO.,INC. ( 13.11%)
MOORE CONSTRUCTION, INC. (0.71%)
RK HALL, LLC ( 34.23%)
SAMMY G. SMALLWOOD (0.30%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(0.25%)
TEX OP CONSTRUCTION, LP(0.35%)
WITHERS CONSTRUCTION, LLC(0.37%)
STRIPING TECHNOLOGY, L.P.(0.77%)
Contract # 09143209
Totals 4635055.96 2400.00 63468.52 1.3

CountyDELTA
Highway FM 64
From FM 1532
To FM 3388
CSJ 0399-03-034
Proj ID STP 2013(547)
Work Type REHABILITATION OF EXISTING ROAD
 
4.939 1399777.15 0.00 1408019.11 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-06-13
Work Began 06-19-13
Work Completed 08-13-14
Time Computed 08-05-13
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 97
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0399-03-034
BAHENA CONSTRUCTION CO.,INC. (3.22%)
LYON BARRICADE AND CONSTRUCTION CO.(0.90%)
CATACON, INC.(1.28%)
SAMMY G. SMALLWOOD (3.10%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.05%)
MOORE CONSTRUCTION, INC. (3.14%)
Contract # 04133008
Totals 1399777.15 0.00 1408019.11 100.0

CountyHOPKINS
Highway SH 19
From DELTA COUNTY LINE
To LOOP 301
CSJ 0400-02-048
Proj ID STP 1502(137)
Work Type OVERLAY
 
12.204 1267814.14 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0400-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153032
Totals 1267814.14 0.00 0.00 0.0

page 1 | page 2 | page 3