Monthly State Let Construction Report For Paris District As Of Oct 14, 2014 Page 1 Of 3

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOPKINS
Highway IH 30 ETC
From SH 19
To TEXAS AVE IN SULPHUR SPRINGS
CSJ 0009-09-099
Proj ID STP 2015(079)HESG
Work Type HAZARD ELIMINATION & SAFETY
 
130.476 1210344.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-099
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143029
Totals 1210344.26 0.00 0.00 0.0

CountyHOPKINS
Highway IH 30 ETC
From SH 19
To SL 301
CSJ 0010-02-088
Proj ID IM 0302(101)
Work Type SEAL COAT
 
215.872 7079441.47 0.00 6841534.19 96.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-20-13
Work Began 06-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 117
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-02-088
FLAT LINE, INC.( 13.15%)
RED SIXTEEN CONSTRUCTION, INC. (0.82%)
Contract # 10133204
Totals 7079441.47 0.00 6841534.19 96.7

CountyFRANKLIN
Highway US 67
From 0.41 MI E OF SPUR 423
To TITUS C/L
CSJ 0010-05-022
Proj ID STP 2014(552)HRR
Work Type HAZARD ELIMINATION & SAFETY
 
5.284 2849816.37 227878.05 1385833.45 48.6
Work Order 04-25-14
Work Began 05-11-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 55
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-05-022
PANOLA SIGN & BARRICADE, INC.(0.50%)
MOORE CONSTRUCTION, INC. (1.19%)
CATOCON, INC.(2.93%)
J & M CONTRACTING, COMPANY ( 17.36%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.90%)
DUSTIN ALLEN, INC. (2.27%)
STRIPING TECHNOLOGY, L.P.(1.17%)
Contract # 03143212
Totals 2849816.37 227878.05 1385833.45 48.6

CountyLAMAR
Highway US 82
From FANNIN COUNTY LINE
To FM 38 EAST
CSJ 0045-08-036
Proj ID NH 2014(736)
Work Type WIDEN NON - FREEWAY
 
15.205 8860584.85 794449.70 1233445.42 13.9
Work Order 07-22-14
Work Began 08-08-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 14
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-08-036
MOORE CONSTRUCTION, INC. (1.84%)
SAMMY G. SMALLWOOD (1.03%)
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
HIGHWAY 19 CONSTRUCTION, LLC (0.71%)
BAHENA CONSTRUCTION CO.,INC. (5.99%)
DUSTROL, INC.(0.97%)
RK HALL, LLC ( 35.66%)
STRIPING TECHNOLOGY, L.P.(2.05%)
CATACON, INC.(2.39%)
RED SIXTEEN CONSTRUCTION, INC(0.30%)
Contract # 06143204
Totals 8860584.85 794449.70 1233445.42 13.9

CountyGRAYSON
Highway US 82
From FM 901
To FM 1417 W
CSJ 0045-18-028
Proj ID NH 2014(441)
Work Type OVERLAY
 
11.830 1958802.67 0.00 1925517.74 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-14
Work Began 04-02-14
Work Completed 08-28-14
Time Computed 04-28-14
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 93
Contractor(s)
VIKING CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-18-028
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 17.85%)
DUSTROL, INC.(1.82%)
COWBELL TRAFFIC SERVICES, INC. (0.99%)
ALTUS TRAFFIC MANAGEMENT LLC (0.32%)
TRP CONSTRUCTION GROUP, LLC(5.59%)
Contract # 02143211
Totals 1958802.67 0.00 1925517.74 100.0

CountyGRAYSON
Highway US 82
From 2180' W OF FM 1417 W (FRTG ONLY)
To FM 1417 W (FRONTAGE ONLY)
CSJ 0045-18-033
Proj ID NH 1402(083)
Work Type OVERLAY
 
3.428 1889024.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-14
Work Began 00-00-00
Work Completed  
Time Computed 10-18-14
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-18-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143215
Totals 1889024.62 0.00 0.00 0.0

CountyGRAYSON
Highway US 82
From FM 1897
To FANNIN COUNTY LINE
CSJ 0045-19-047
Proj ID C 45-19-47
Work Type WIDEN NON - FREEWAY
 
12.152 26059261.46 656548.69 23254837.57 89.2
Work Order 10-12-12
Work Began 11-15-12
Work Completed  
Time Computed 04-10-13
Contract Working Days 473
Addl Days Granted 0
Working Days Charged 369
Percent Time Used 78
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-047
BAHENA CONSTRUCTION CO.,INC. (3.42%)
FORTSON CONTRACTING, INC.(0.06%)
L & N BRIDGE, LLC(2.48%)
GARY A. CRAIN, INC.(0.01%)
LYON BARRICADE AND CONSTRUCTION CO.(0.18%)
MOORE CONSTRUCTION, INC. (0.65%)
MURRAY CONSTRUCTION(0.63%)
RK HALL, LLC ( 42.19%)
STRIPING TECHNOLOGY, L.P.(0.72%)
WEST TEXAS RUMBLE STRIP(0.06%)
WYLIE DRILLING & DRAINAGE, INC.(0.38%)
TEX OP CONSTRUCTION, LP(0.69%)
SOUTHEAST GRINDING & GROOVING, LLC (0.01%)
TEXAS SHAFTS, INC. (0.20%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.25%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.01%)
Contract # 08123201
Totals 26059261.46 656548.69 23254837.57 89.2

CountyGRAYSON
Highway SH 5
From COLLIN COUNTY LINE
To US 75
CSJ 0047-03-075
Proj ID STP 1402(084)
Work Type MISCELLANEOUS CONSTRUCTION
 
9.575 3711917.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143041
Totals 3711917.79 0.00 0.00 0.0

CountyGRAYSON
Highway US 75
From FM 902
To SHEPHERD DRIVE
CSJ 0047-03-076
Proj ID C 47-3-76
Work Type REHABILITATION OF EXISTING ROADWAY
 
1.495 8342650.77 1238869.00 4708924.32 56.4
Work Order 11-04-13
Work Began 01-27-14
Work Completed  
Time Computed 01-03-14
Contract Working Days 142
Addl Days Granted 6
Working Days Charged 122
Percent Time Used 82
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-076
BROCK ENVIRONMENTAL, LLC (0.10%)
DUSTROL, INC.(0.10%)
FORTSON CONTRACTING, INC.(0.14%)
ALTUS TRAFFIC MANAGEMENT LLC (0.18%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.24%)
SAMMY G. SMALLWOOD (0.42%)
W.O.E. CONSTRUCTION(0.44%)
STRIPING TECHNOLOGY, L.P.(0.76%)
ANTIGO CONSTRUCTION, INC.(0.38%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(1.29%)
VENUS CONSTRUCTION (4.15%)
MCL CONTRACTING, LLC (1.18%)
MABAK DIRECTIONAL DRILLING (0.08%)
ASPLUNDH TREE EXPERT CO(0.39%)
Contract # 08133224
Totals 8342650.77 1238869.00 4708924.32 56.4

CountyGRAYSON
Highway US 75
From 1.65 MILES NORTH OF FM 1417
To FM 1417
CSJ 0047-03-077
Proj ID NH 2013(907)
Work Type MISCELLANEOUS CONSTRUCTION
 
1.650 739670.03 2175.00 766794.03 99.9
Work Order 10-30-13
Work Began 01-03-14
Work Completed  
Time Computed 12-30-13
Contract Working Days 43
Addl Days Granted 5
Working Days Charged 48
Percent Time Used 100
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-077
CROSSROADS, L.P. (1.07%)
BRENDA PRICE TRUCKING(0.71%)
BROCK ENVIRONMENTAL, LLC (0.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.80%)
RK HALL, LLC ( 26.50%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.27%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (7.65%)
DUSTROL, INC.(3.21%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.23%)
GJ SEEDING, LLC(0.63%)
Contract # 08133028
Totals 739670.03 2175.00 766794.03 99.9

CountyGRAYSON
Highway US 75
From @ LOY LAKE ROAD (SHERMAN)
To .
CSJ 0047-18-068
Proj ID NH 2013(908)
Work Type WIDEN NON - FREEWAY
 
0.434 5248890.96 190832.81 2735802.06 52.1
Work Order 01-06-14
Work Began 01-27-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 268
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 54
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-068
TOTAL HIGHWAY MAINTENANCE, LLC (1.24%)
EROSION CONTROL MANAGEMENT SERVICES(0.09%)
S & S BRIDGE PAINTING, INC.(0.67%)
WYLIE DRILLING & DRAINAGE, INC.(1.37%)
CROSSROADS, L.P. (0.48%)
A BROTHERS MILLING, LLC(0.48%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (5.62%)
MCL CONTRACTING, LLC (0.55%)
W.O.E. CONSTRUCTION(0.19%)
LONE STAR BARRIER SERVICES, LLC(0.40%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.22%)
PEACHTREE CONSTRUCTION, LTD. (2.49%)
PLACIDO CONSTRUCTION COMPANY (0.57%)
Contract # 09133221
Totals 5248890.96 190832.81 2735802.06 52.1

CountyGRAYSON
Highway SH 289
From 0.300 MILES SOUTH OF SP 316
To 0.183 MILES NORTH OF SP 316
CSJ 0091-01-046
Proj ID STP 2012(573)
Work Type WIDEN NON - FREEWAY
 
7.464 4252949.45 0.00 4078848.67 96.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 07-31-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 201
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 107
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0091-01-046
CATOCON, INC.(0.96%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.12%)
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.61%)
J. M. CONSTRUCTION (6.12%)
LONE STAR BARRIER SERVICES, LLC(0.19%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.11%)
RK HALL, LLC (2.79%)
TEX OP CONSTRUCTION, LP(0.25%)
HIGHWAY 19 CONSTRUCTION, LLC (0.00%)
STRIPING TECHNOLOGY, L.P.(1.20%)
Contract # 05123220
Totals 4252949.45 0.00 4078848.67 96.2

CountyHOPKINS
Highway SH 19
From SH 11
To RAINS COUNTY LINE
CSJ 0108-09-043
Proj ID STP 2013(906)
Work Type SEAL COAT
 
16.672 1364788.07 0.00 1355429.16 99.3
Work Order 10-22-13
Work Began 11-01-13
Work Completed  
Time Computed 11-04-13
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 98
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-09-043
PANOLA SIGN & BARRICADE, INC.(1.09%)
STRIPING TECHNOLOGY, L.P.(3.16%)
BAHENA CONSTRUCTION CO.,INC. (9.34%)
SAMMY G. SMALLWOOD (1.78%)
MOORE CONSTRUCTION, INC. (1.43%)
CATACON, INC.(1.88%)
Contract # 08133044
Totals 1364788.07 0.00 1355429.16 99.3

CountyDELTA
Highway SH 24
From FM 904
To FM 64
CSJ 0136-03-044
Proj ID TCSP 2010(387)
Work Type GR, STRS BS, & SURF
 
10.955 39277746.71 2029192.38 4433616.34 11.2
Work Order 02-18-14
Work Began 08-20-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 598
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 5
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0136-03-044
MOORE CONSTRUCTION, INC. (0.34%)
LYON BARRICADE AND CONSTRUCTION CO.(0.20%)
DUSTROL, INC.(0.04%)
HIGHWAY 19 CONSTRUCTION, LLC (6.28%)
FLAT LINE, INC.(0.80%)
NORTH TEXAS HYDRA-HAMMER, INC. (0.05%)
RK HALL, LLC ( 29.02%)
SAMMY G. SMALLWOOD (0.83%)
TEXAS ALTERNATIVE GRASSER, INC.(0.15%)
TEX OP CONSTRUCTION, LP(0.19%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 16.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.19%)
RED SIXTEEN CONSTRUCTION, INC(0.03%)
MCL CONTRACTING, LLC (0.08%)
Contract # 12133002
Totals 39277746.71 2029192.38 4433616.34 11.2

CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-007
Proj ID BR 2012(716)
Work Type BRIDGE REPLACEMENT
 
0.570 11302230.33 132096.95 9714922.70 85.9
CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-009
Proj ID BR 2012(792)
Work Type BRIDGE REPLACEMENT
 
0.360 1517866.78 441590.16 771676.80 50.8
CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-010
Proj ID CC 189-1-10
Work Type BRIDGE REPLACEMENT
 
0.360 1759959.64 404694.56 1280541.02 72.7
Work Order 10-24-12
Work Began 02-05-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 495
Addl Days Granted 0
Working Days Charged 318
Percent Time Used 64
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0189-01-007
ATS DRILLING, INC. ( 14.68%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.91%)
SCOTT DERR PAINTING CO, LLC(0.20%)
TEX OP CONSTRUCTION, LP(0.22%)
RK HALL, LLC ( 12.53%)
SOUTHEAST GRINDING & GROOVING, LLC (0.09%)
MCL CONTRACTING, LLC (0.96%)
LYON BARRICADE AND CONSTRUCTION CO.(0.11%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.08%)
DUSTIN ALLEN, INC. (0.13%)
MCL CONTRACTING, LLC (2.18%)
STRIPING TECHNOLOGY, L.P.(0.39%)
Contract # 08123208
Totals 14580056.75 978381.67 11767140.52 80.7

CountyRED RIVER
Highway SH 37
From 0.2 MI N OF US 82
To 0.2 MI S OF FM 195
CSJ 0189-02-050
Proj ID STP 2014(739)
Work Type OVERLAY
 
16.136 1186753.45 0.00 0.00 0.0
Work Order 07-18-14
Work Began 00-00-00
Work Completed  
Time Computed 08-03-14
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 50
Contractor(s)
VIKING CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0189-02-050
TRP CONSTRUCTION GROUP, LLC(5.97%)
COWBELL TRAFFIC SERVICES, INC. (1.46%)
PANOLA SIGN & BARRICADE, INC.(0.52%)
Contract # 06143036
Totals 1186753.45 0.00 0.00 0.0

CountyGRAYSON
Highway FM 131
From CANYON GROVE ROAD
To FM 691
CSJ 0202-08-055
Proj ID STP 2013(679)
Work Type OVERLAY
 
2.008 906055.26 0.00 793513.66 89.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 10-09-13
Work Completed  
Time Computed 07-24-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 87
Percent Time Used 145
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0202-08-055
NE-TEX CONSTRUCTION, LTD.( 31.59%)
MARCOM"S MOWING SERVICE, LLC (6.56%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.47%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.86%)
STRIPING TECHNOLOGY, L.P.(2.99%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (3.90%)
TEX OP CONSTRUCTION, LP(2.31%)
HALL BROTHERS, INC.(4.13%)
RK HALL, LLC (3.54%)
Contract # 05133017
Totals 906055.26 0.00 793513.66 89.3

CountyRAINS
Highway US 69
From SH 19
To 586 NORTH OF FM 3299 INTERSECTION
CSJ 0203-03-044
Proj ID STP 1402(093)
Work Type MISCELLANEOUS CONSTRUCTION
 
3.240 4635055.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0203-03-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143209
Totals 4635055.96 0.00 0.00 0.0

CountyRAINS
Highway US 69
From 0.1 MILES E OF FM 515
To WOOD COUNTY LINE
CSJ 0203-04-038
Proj ID STP 2014(631)
Work Type SEAL COAT
 
33.209 1355512.84 6080.00 1285255.26 95.1
Work Order 05-09-14
Work Began 06-10-14
Work Completed  
Time Computed 05-25-14
Contract Working Days 16
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 143
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0203-04-038
FLAT LINE, INC.( 10.54%)
RED SIXTEEN CONSTRUCTION, INC. (0.60%)
Contract # 04143242
Totals 1355512.84 6080.00 1285255.26 95.1

CountyDELTA
Highway FM 64
From FM 1532
To FM 3388
CSJ 0399-03-034
Proj ID STP 2013(547)
Work Type REHABILITATION OF EXISTING ROAD
 
4.939 1399777.15 2160.00 1408019.11 100.0
Work Order 06-06-13
Work Began 06-19-13
Work Completed 08-13-14
Time Computed 08-05-13
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 97
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0399-03-034
BAHENA CONSTRUCTION CO.,INC. (3.22%)
LYON BARRICADE AND CONSTRUCTION CO.(0.90%)
CATACON, INC.(1.28%)
SAMMY G. SMALLWOOD (3.10%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.05%)
MOORE CONSTRUCTION, INC. (3.14%)
Contract # 04133008
Totals 1399777.15 2160.00 1408019.11 100.0

page 1 | page 2 | page 3