Monthly State Let Construction Report For Paris District As Of Sep 21, 2017 Page 2 Of 3

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHUNT
HighwaySH 34 ETC
From0.19 MI. SOUTH OF IH30
ToBU 69-D
CSJ0173-07-055
Proj IDNH 2017(926)
Work TypeOVERLAY
 
6.4201683587.851377890.1981.8
Work Order05-18-17
Work Began06-15-17
Work Completed
Time Computed06-19-17
Contract Working Days102
Addl Days Granted0
Working Days Charged40
Percent Time Used39
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0173-07-055
ALTUS TRAFFIC MANAGEMENT LLC (0.82)
SOUTHWEST ENVIRONMENT SERVICES LLC (5.09)
TOTAL HIGHWAY MAINTENANCE, LLC (3.04)
Contract #04173014
Totals1683587.85180333.481377890.1981.8

CountyFRANKLIN
HighwaySH 37
FromFM 21
ToWOOD C/L
CSJ0190-01-021
Proj IDNH 1502(556)
Work TypeRECONST & ADD 10' SHLDRS
 
13.25820387243.9810451012.6351.2
Work Order03-08-16
Work Began03-23-16
Work Completed
Time Computed06-06-16
Contract Working Days457
Addl Days Granted18
Working Days Charged299
Percent Time Used62
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0190-01-021
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18)
BAHENA CONSTRUCTION CO.,INC. (1.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.99)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.33)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.74)
STRIPING TECHNOLOGY, L.P. (1.18)
TX TINMAN ENTERPRISES, LLC. (1.85)
WOLFE CONSTRUCTION GROUP, INC. (0.57)
KLP COMMERCIAL, LLC (0.00)
MESA ROD BUSTERS, INC. (0.04)
DFW REBAR, INC. (0.02)
ISAACS CONSTRUCTION SERVICES, LLC. (1.65)
Contract #01163001
Totals20387243.98371019.0210451012.6351.2

CountyFANNIN ETC
HighwayUS 69
FromFM 151
ToHUNT COUNTY LINE
CSJ0202-03-041
Proj IDSTP 2017(739)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
39.0843186550.00978442.9730.7
Work Order03-15-17
Work Began04-10-17
Work Completed
Time Computed04-14-17
Contract Working Days180
Addl Days Granted0
Working Days Charged90
Percent Time Used50
Contractor(s)
GHB EQUIPMENT COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0202-03-041
AREA WIDE PROTECTIVE, INC. (0.84)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.02)
EAGLE BARRICADE,LLC. (1.12)
STRIPING TECHNOLOGY, L.P. (0.41)
SHALOM SERVICES CORPORATION (4.39)
ODUM SERVICES, L.P. (10.47)
Contract #02173020
Totals3186550.00250586.07978442.9730.7

CountyFANNIN
HighwaySH 78
FromSH 11
To0.68 MI S OF SH 56
CSJ0279-03-035
Proj IDSTP 2017(188)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
23.8702675061.25828358.6130.9
Work Order12-06-16
Work Began01-09-17
Work Completed
Time Computed02-01-17
Contract Working Days159
Addl Days Granted0
Working Days Charged90
Percent Time Used56
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0279-03-035
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.76)
WITHERS CONSTRUCTION, LLC (1.32)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION, LTD. (0.38)
MORRIS COUNTY CONTRACTORS, L.L.C. (13.21)
Contract #10163212
Totals2675061.2593088.51828358.6130.9

CountyRED RIVER
HighwayFM 44
FromFM 412
ToFM 911
CSJ0427-01-037
Proj IDSTP 2016(363)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.3634617291.244063542.1488.3
Work Order03-15-16
Work Began04-25-16
Work Completed
Time Computed05-16-16
Contract Working Days222
Addl Days Granted4
Working Days Charged241
Percent Time Used106
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0427-01-037
HIGHWAY 19 CONSTRUCTION, LLC (1.62)
LYON BARRICADE AND CONSTRUCTION CO. (0.52)
WITHERS CONSTRUCTION, LLC (2.23)
MOORE CONSTRUCTION CO. (2.98)
SAMMY SMALLWOOD COMPANY (2.37)
BAHENA CONSTRUCTION CO.,INC. (11.37)
TEX OP CONSTRUCTION, LP (0.15)
STRIPING TECHNOLOGY, L.P. (1.84)
STRIPING SYSTEMS, INC. (0.02)
MOORE CONSTRUCTION, INC. (2.98)
SOUTHERN CROSS CONTRACTORS, LLC (0.19)
Contract #02163241
Totals4617291.24362949.124063542.1488.3

CountyLAMAR
HighwayFM 137
FromFM 38
ToUS 82
CSJ0435-01-068
Proj IDSTP 2016(099)
Work TypeREHABILITATION OF EXISTING ROAD
 
8.9983768340.103470723.7892.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-13-15
Work Began12-09-15
Work Completed
Time Computed01-12-16
Contract Working Days171
Addl Days Granted0
Working Days Charged187
Percent Time Used109
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-068
N-LINE TRAFFIC MAINTENANCE, L.P. (0.72)
STRIPING TECHNOLOGY, L.P. (3.34)
CATOCON, INC. (1.79)
MOORE CONSTRUCTION, INC. (1.99)
SAMMY SMALLWOOD COMPANY (4.58)
BAHENA CONSTRUCTION CO.,INC. (1.46)
MURRAY CONSTRUCTION (1.48)
ACU CONSTRUCTION LLC (0.65)
ANCHOR CONTRACTING, LLC (0.43)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.49)
Contract #09153025
Totals3768340.100.003470723.7892.5

CountyGRAYSON
HighwayFM 902
FromUS 377
ToSH 289
CSJ0510-01-026
Proj IDSTP 2015(309)
Work TypeREHABILITATION OF EXISTING ROAD
 
14.4277337375.526541699.8189.7
Work Order01-02-15
Work Began09-28-15
Work Completed
Time Computed04-02-15
Contract Working Days304
Addl Days Granted0
Working Days Charged342
Percent Time Used112
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-01-026
TEXOP CONSTRUCTION (0.05)
CATOCON, INC. (1.83)
FARR FOUNDATION, INC. (4.74)
LYON BARRICADE AND CONSTRUCTION CO. (0.46)
MURRAY CONSTRUCTION (1.26)
SAMMY G. SMALLWOOD (1.75)
STRIPING TECHNOLOGY, L.P. (1.54)
TEXANA LAND & ASPHALT, INC. (2.35)
BAHENA CONSTRUCTION CO.,INC. (14.62)
MOORE CONSTRUCTION, INC. (1.15)
Contract #11143220
Totals7337375.5211195.866541699.8189.7

CountyDELTA ETC
HighwaySH 19 ETC
From@ BRUSHY CREEK
To.
CSJ0525-01-020
Proj IDBR 1502(141)
Work TypeBRIDGE REPLACEMENT
 
0.6784018602.903882291.1696.6
Work Order06-30-15
Work Began09-22-15
Work Completed
Time Computed08-30-15
Contract Working Days348
Addl Days Granted0
Working Days Charged342
Percent Time Used98
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0525-01-020
PANOLA SIGN & BARRICADE, INC. (0.71)
MOORE CONSTRUCTION, INC. (1.43)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (4.08)
DUSTIN ALLEN, INC. (3.15)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.02)
STRIPING TECHNOLOGY, L.P. (1.08)
PENHALL COMPANY (0.23)
TEX OP CONSTRUCTION, LP (0.62)
WITHERS CONSTRUCTION, LLC (0.79)
MCL CONTRACTING, LLC (0.30)
STRIPING SYSTEMS, INC. (0.00)
Contract #05153217
Totals4018602.9018375.503882291.1696.6

CountyFANNIN
HighwaySH 121
FromUS 82
ToSH 56
CSJ0549-01-029
Proj IDSTP 2012(575)
Work TypeUPGRADE TO NON-FREEWAY STANDARDS
 
1.8636855007.156454588.3399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-18-12
Work Began03-11-13
Work Completed
Time Computed04-22-13
Contract Working Days284
Addl Days Granted36
Working Days Charged725
Percent Time Used226
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-029
BAHENA CONSTRUCTION CO.,INC. (12.83)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.70)
NE-TEX CONSTRUCTION, LTD. (37.43)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.64)
STRIPING TECHNOLOGY, L.P. (1.16)
TEX OP CONSTRUCTION, LP (0.16)
TOTAL HIGHWAY MAINTENANCE, LLC (0.69)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.13)
SCOTT DERR PAINTING CO, LLC (0.04)
STRIPING SYSTEMS, INC. (0.00)
Contract #08123015
Totals6855007.150.006454588.3399.9

CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE (EB)
ToTITUS COUNTY LINE
CSJ0610-02-052
Proj IDNH 2016(100)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.7229114259.968736426.4695.8
CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE (WB)
ToTITUS COUNTY LINE
CSJ0610-02-053
Proj IDNH 2016(100)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.7227316744.767077529.1796.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-15
Work Began03-02-16
Work Completed
Time Computed12-21-15
Contract Working Days223
Addl Days Granted0
Working Days Charged173
Percent Time Used77
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0610-02-052
A BROTHERS MILLING, LLC (2.54)
CDM HOLDINGS, LLC (7.36)
STRAIGHT LINE SAWING & SEALING (0.20)
TRP CONSTRUCTION GROUP, LLC (1.04)
ALTUS TRAFFIC MANAGEMENT LLC (0.15)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.10)
MARTIN MARIETTA MATERIALS (POWDERLY) (0.00)
TEX OP CONSTRUCTION, LP (0.03)
JM YANEZ CONSTRUCTION (0.16)
Contract #09153003
Totals16431004.720.0015813955.6396.2

CountyFRANKLIN
HighwayFM 21
FromFM 2723
ToCR 4140
CSJ0633-01-021
Proj IDSTP 1702(748)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.4981216614.350.000.0
CountyFRANKLIN
HighwayFM 3357
FromFM 115
ToSH 37
CSJ3354-01-015
Proj IDC 3354-1-15
Work TypeSEAL COAT
 
5.324323324.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0633-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173026
Totals1539938.350.000.000.0

CountyLAMAR
HighwayFM 196
FromUS 271
ToFM 1501
CSJ0680-01-015
Proj IDSTP 2017(086)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.8062490743.372141139.7285.9
Work Order11-15-16
Work Began01-03-17
Work Completed
Time Computed12-15-16
Contract Working Days144
Addl Days Granted0
Working Days Charged136
Percent Time Used94
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-01-015
CATACON, INC. (1.92)
MOORE CONSTRUCTION, INC. (2.36)
SCOTT PAVING, INC. (17.51)
TOTAL HIGHWAY MAINTENANCE, LLC (1.83)
SOUTHERN CROSS CONTRACTORS, LLC (2.24)
DUSTIN ALLEN, INC. (0.48)
Contract #09163221
Totals2490743.37262490.002141139.7285.9

CountyHOPKINS
HighwayFM 900
FromAT W GREENWOOD CREEK
To.
CSJ0680-05-008
Proj IDBR 0090(264)
Work TypeBRIDGE REPLACEMENT
 
0.2201570944.581572897.5899.9
Work Order04-20-15
Work Began06-24-15
Work Completed
Time Computed06-20-15
Contract Working Days270
Addl Days Granted0
Working Days Charged277
Percent Time Used102
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-05-008
N LINE TRAFFIC CONTROL (1.15)
SAMMY G. SMALLWOOD (6.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.21)
MESA ROD BUSTERS, INC. (0.32)
MOORE CONSTRUCTION, INC. (1.19)
STRIPING TECHNOLOGY, L.P. (0.80)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.05)
PENHALL COMPANY (0.20)
Contract #03153019
Totals1570944.584500.001572897.5899.9

CountyRAINS
HighwayFM 275
FromFM 514
ToFM 514
CSJ0725-02-019
Proj IDSTP 1702(751)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
1.405614717.760.000.0
CountyRAINS
HighwayFM 275
FromFM 514
ToFM 514
CSJ0725-02-020
Proj IDSTP 1702(752)
Work TypeSEAL COAT
 
1.40570822.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0725-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173036
Totals685540.510.000.000.0

CountyGRAYSON
HighwayFM 120
FromCENTER AVE
ToOKLAHOMA STATE LINE
CSJ0728-02-029
Proj IDSTP 1502(558)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.4862460214.082281956.7293.5
Work Order10-22-15
Work Began02-08-16
Work Completed
Time Computed12-21-15
Contract Working Days116
Addl Days Granted14
Working Days Charged155
Percent Time Used119
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0728-02-029
ALTUS TRAFFIC MANAGEMENT LLC (0.51)
SAMMY GIST ENTERPRISES, INC. (1.96)
BAHENA CONSTRUCTION CO.,INC. (20.18)
WIMMS ENVIRONMENTAL, INC. (0.73)
DUSTIN ALLEN, INC. (8.13)
TRP CONSTRUCTION GROUP, LLC (2.20)
MOORE CONSTRUCTION, INC. (1.78)
WITHERS CONSTRUCTION, LLC (4.14)
TEXANA LAND & ASPHALT, INC. (4.39)
Contract #08153225
Totals2460214.0821868.002281956.7293.5

CountyGRAYSON
HighwayFM 121
FromSH 289
To1200 FT WEST OF FM 3356
CSJ0729-01-037
Proj IDSTP 1502(559)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.9584609064.064126915.6489.5
Work Order01-29-16
Work Began03-16-16
Work Completed
Time Computed04-28-16
Contract Working Days272
Addl Days Granted0
Working Days Charged274
Percent Time Used100
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0729-01-037
TOTAL HIGHWAY MAINTENANCE, LLC (0.49)
STRIPING TECHNOLOGY, L.P. (2.18)
CATACON, INC. (1.41)
MOORE CONSTRUCTION, INC. (1.88)
LONE STAR BARRIER SERVICES, LLC (4.24)
BAHENA CONSTRUCTION CO.,INC. (15.72)
DUSTIN ALLEN, INC. (3.33)
MARCOM"S MOWING SERVICE, LLC (0.88)
STRIPING SYSTEMS, INC. (0.00)
Contract #10153228
Totals4609064.06194907.604126915.6489.5

CountyGRAYSON
HighwayFM 121
FromAT WEST FORK OF PILOT GROVE CREEK
To.
CSJ0729-02-026
Proj IDBR 1502(261)
Work TypeREPLACE BRIDGE
 
0.1931590415.601550784.4997.9
Work Order07-30-15
Work Began10-20-15
Work Completed
Time Computed08-31-15
Contract Working Days234
Addl Days Granted0
Working Days Charged243
Percent Time Used103
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0729-02-026
ALTUS TRAFFIC MANAGEMENT LLC (1.30)
STRIPE-A-ZONE, INC. (1.56)
ODUM SERVICES, L.P. (2.63)
PENHALL COMPANY (0.22)
FOUNDATION DRILLERS, INC. (3.38)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.36)
W. W. FOUNDATION DRILLING, LTD. (4.13)
MOORE CONSTRUCTION, INC. (1.83)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.35)
Contract #06153031
Totals1590415.603462.001550784.4997.9

CountyHOPKINS
HighwayFM 1870
FromSH 11
ToCR 2309
CSJ0735-05-017
Proj IDSTP 2016(101)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.8151161897.121135191.0797.7
CountyHOPKINS
HighwayFM 1870
FromSH 11
ToCR 2309
CSJ0735-05-020
Proj IDSTP 2016(102)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
3.819542959.77519647.3395.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-29-16
Work Began03-28-16
Work Completed
Time Computed03-29-16
Contract Working Days120
Addl Days Granted0
Working Days Charged120
Percent Time Used100
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0735-05-017
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
MOORE CONSTRUCTION, INC. (3.73)
STRIPING TECHNOLOGY, L.P. (2.49)
CATACON, INC. (1.45)
SCOTT PAVING, INC. (24.79)
SAMMY G. SMALLWOOD (1.27)
STRIPING SYSTEMS, INC. (0.05)
Contract #09153218
Totals1704856.890.001654838.4097.0

CountyHUNT
HighwayFM 272
FromUS 69
ToFM 816
CSJ0764-02-011
Proj IDC 764-2-11
Work TypeREHABILITATION OF EXISTING ROAD
 
6.0883455817.183181707.5192.0
Work Order09-20-16
Work Began10-07-16
Work Completed
Time Computed10-20-16
Contract Working Days202
Addl Days Granted0
Working Days Charged162
Percent Time Used80
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0764-02-011
N-LINE TRAFFIC MAINTENANCE, L.P. (0.50)
STRIPING TECHNOLOGY, L.P. (1.47)
CATOCON, INC. (2.46)
MOORE CONSTRUCTION, INC. (3.34)
SAMMY SMALLWOOD COMPANY (4.09)
BAHENA CONSTRUCTION CO.,INC. (8.01)
MURRAY CONSTRUCTION (1.38)
DUSTROL, INC. (0.33)
Contract #07163021
Totals3455817.18493021.913181707.5192.0

CountyLAMAR
HighwayFM 906
FromCR 45030
ToCR 47400
CSJ0769-02-028
Proj IDSTP 2016(189)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.6554368067.412239154.1051.2
CountyLAMAR
HighwayFM 906
FromFM 197
ToUS 271
CSJ0769-02-030
Proj IDSTP 2016(190)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
4.4541549596.88868916.5156.0
Work Order06-23-16
Work Began09-21-16
Work Completed
Time Computed07-25-16
Contract Working Days345
Addl Days Granted4
Working Days Charged194
Percent Time Used55
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0769-02-028
BAHENA CONSTRUCTION CO.,INC. (8.62)
DUSTIN ALLEN, INC. (6.76)
MOORE CONSTRUCTION, INC. (1.89)
RK HALL, LLC (13.87)
STRIPING TECHNOLOGY, L.P. (2.46)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.82)
WITHERS CONSTRUCTION, LLC (2.12)
LYON BARRICADE AND CONSTRUCTION CO. (0.56)
TEXOP CONSTRUCTION (1.52)
SAMMY GIST ENTERPRISES, INC. (0.31)
Contract #01163215
Totals5917664.29165656.113108070.6152.5

page 1 | page 2 | page 3