Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDELTA
Highway SH 24
From FM 904
To FM 64
CSJ 0136-03-044
Proj ID TCSP 2010(387)
Work Type GR, STRS BS, & SURF
 
10.955 39277746.71 480489.50 16994233.86 43.2
Work Order 02-18-14
Work Began 08-20-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 598
Addl Days Granted 2
Working Days Charged 267
Percent Time Used 44
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0136-03-044
MOORE CONSTRUCTION, INC. (0.34%)
LYON BARRICADE AND CONSTRUCTION CO.(0.20%)
DUSTROL, INC.(0.04%)
HIGHWAY 19 CONSTRUCTION, LLC (6.50%)
FLAT LINE, INC.(0.80%)
NORTH TEXAS HYDRA-HAMMER, INC. (0.05%)
RK HALL, LLC ( 29.02%)
SAMMY G. SMALLWOOD (0.83%)
TEXAS ALTERNATIVE GRASSER, INC.(0.15%)
TEX OP CONSTRUCTION, LP(0.19%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 16.25%)
RED SIXTEEN CONSTRUCTION, INC(0.34%)
MCL CONTRACTING, LLC (0.08%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.19%)
Contract # 12133002
Totals 39277746.71 480489.50 16994233.86 43.2

CountyHUNT
Highway SH 34
From INTERSECTION OF SH 276/SH 34
To .
CSJ 0173-06-044
Proj ID STP 1502(639)
Work Type LANDSCAPE AND SCENIC ENHANCEMENT
 
0.100 39179.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 14
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0173-06-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153215
Totals 39179.00 0.00 0.00 0.0

CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-007
Proj ID BR 2012(716)
Work Type BRIDGE REPLACEMENT
 
0.570 11302230.33 0.00 10917039.71 96.5
CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-009
Proj ID BR 2012(792)
Work Type BRIDGE REPLACEMENT
 
0.360 1517866.78 0.00 1498001.84 98.6
CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-010
Proj ID CC 189-1-10
Work Type BRIDGE REPLACEMENT
 
0.360 1759959.64 0.00 1756100.40 99.7
Work Order 10-24-12
Work Began 02-05-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 495
Addl Days Granted 0
Working Days Charged 480
Percent Time Used 96
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0189-01-007
ATS DRILLING, INC. ( 14.68%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.91%)
SCOTT DERR PAINTING CO, LLC(0.20%)
TEX OP CONSTRUCTION, LP(0.22%)
RK HALL, LLC ( 12.53%)
SOUTHEAST GRINDING & GROOVING, LLC (0.09%)
MCL CONTRACTING, LLC (0.96%)
LYON BARRICADE AND CONSTRUCTION CO.(0.11%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.08%)
DUSTIN ALLEN, INC. (0.14%)
MCL CONTRACTING, LLC (2.18%)
STRIPING TECHNOLOGY, L.P.(0.39%)
DUSTROL, INC.(0.03%)
Contract # 08123208
Totals 14580056.75 0.00 14171141.95 97.1

CountyRED RIVER
Highway SH 37
From 0.2 MI N OF US 82
To 0.2 MI S OF FM 195
CSJ 0189-02-050
Proj ID STP 2014(739)
Work Type OVERLAY
 
16.136 1186753.45 0.00 1462000.97 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-18-14
Work Began 10-22-14
Work Completed 09-24-15
Time Computed 08-03-14
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 186
Contractor(s)
VIKING CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0189-02-050
TRP CONSTRUCTION GROUP, LLC(5.97%)
COWBELL TRAFFIC SERVICES, INC. (1.46%)
PANOLA SIGN & BARRICADE, INC.(0.52%)
BRYDL CONTRACTING, INC.(0.37%)
Contract # 06143036
Totals 1186753.45 0.00 1462000.97 100.0

CountyFRANKLIN
Highway SH 37
From FM 21
To WOOD C/L
CSJ 0190-01-021
Proj ID NH 1502(556)
Work Type RECONST & ADD 10' SHLDRS
 
13.258 20387243.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0190-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163001
Totals 20387243.98 0.00 0.00 0.0

CountyRAINS
Highway US 69
From 586FT NORTH OF FM 3299 INTERSECTION
To COUNTY ROAD 4530
CSJ 0203-03-042
Proj ID STP 1502(131)
Work Type OVERLAY
 
6.223 1742911.94 0.00 1820289.96 99.9
Work Order 06-16-15
Work Began 08-24-15
Work Completed  
Time Computed 07-17-15
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0203-03-042
TOTAL HIGHWAY MAINTENANCE, LLC (0.31%)
DIAMOND SURFACE, INC.(0.58%)
MOORE CONSTRUCTION, INC. (1.03%)
STRIPING TECHNOLOGY, L.P.(2.68%)
Contract # 05153239
Totals 1742911.94 0.00 1820289.96 99.9

CountyRAINS
Highway US 69
From SH 19
To 586 NORTH OF FM 3299 INTERSECTION
CSJ 0203-03-044
Proj ID STP 1402(093)
Work Type MISCELLANEOUS CONSTRUCTION
 
3.240 4635055.96 87084.68 1806798.73 38.9
Work Order 11-12-14
Work Began 02-26-15
Work Completed  
Time Computed 02-10-15
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 78
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0203-03-044
ALTUS TRAFFIC MANAGEMENT LLC (0.27%)
BAHENA CONSTRUCTION CO.,INC. ( 13.11%)
MOORE CONSTRUCTION, INC. (0.71%)
RK HALL, LLC ( 34.23%)
SAMMY G. SMALLWOOD (0.30%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(0.25%)
TEX OP CONSTRUCTION, LP(0.35%)
WITHERS CONSTRUCTION, LLC(0.37%)
STRIPING TECHNOLOGY, L.P.(0.77%)
Contract # 09143209
Totals 4635055.96 87084.68 1806798.73 38.9

CountyDELTA
Highway FM 64
From FM 1532
To FM 3388
CSJ 0399-03-034
Proj ID STP 2013(547)
Work Type REHABILITATION OF EXISTING ROAD
 
4.939 1399777.15 0.00 1408019.11 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-06-13
Work Began 06-19-13
Work Completed 08-13-14
Time Computed 08-05-13
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 97
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0399-03-034
BAHENA CONSTRUCTION CO.,INC. (3.22%)
LYON BARRICADE AND CONSTRUCTION CO.(0.90%)
CATACON, INC.(1.28%)
SAMMY G. SMALLWOOD (3.10%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.05%)
MOORE CONSTRUCTION, INC. (3.14%)
Contract # 04133008
Totals 1399777.15 0.00 1408019.11 100.0

CountyHOPKINS
Highway SH 19
From DELTA COUNTY LINE
To LOOP 301
CSJ 0400-02-048
Proj ID STP 1502(137)
Work Type OVERLAY
 
12.204 1267814.14 0.00 205021.17 16.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-15-15
Work Began 08-24-15
Work Completed  
Time Computed 07-16-15
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 87
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0400-02-048
FLEX SUPPLY, LLC (0.60%)
JOHN MILLSAP (5.23%)
STRIPING TECHNOLOGY, L.P.(6.43%)
WEST TEXAS RUMBLE STRIP(0.81%)
Contract # 05153032
Totals 1267814.14 0.00 205021.17 16.1

CountyHOPKINS
Highway SH 154
From 0.315 MILES NORTH OF FM 1567 EAST
To 0.195 MILES SOUTH OF CR 1104
CSJ 0401-01-022
Proj ID STP 2013(464)
Work Type UPGRADE TO NON - FREEWAY STANDARDS
 
4.973 6591501.99 426566.64 7722657.70 99.9
Work Order 05-13-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 444
Percent Time Used 97
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0401-01-022
PANOLA SIGN & BARRICADE, INC.(0.54%)
BAHENA CONSTRUCTION CO.,INC. (9.56%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.24%)
FORTSON CONTRACTING, INC.(4.14%)
STRIPING TECHNOLOGY, L.P.(1.24%)
MOORE CONSTRUCTION, INC. (0.57%)
TEXANA LAND & ASPHALT, INC.(0.57%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. ( 27.89%)
Contract # 03133219
Totals 6591501.99 426566.64 7722657.70 99.9

CountyGRAYSON
Highway US 69
From 0.490 MI. NORTH OF SH 11
To 0.638 MI. SOUTH OF SH 56
CSJ 0410-02-030
Proj ID STP 2013(069)
Work Type REHABILITATION OF EXISTING ROAD
 
6.282 5218898.13 0.00 5556556.90 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-01-12
Work Began 11-09-12
Work Completed 09-02-14
Time Computed 04-30-13
Contract Working Days 131
Addl Days Granted 27
Working Days Charged 194
Percent Time Used 122
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0410-02-030
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.29%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.12%)
BAHENA CONSTRUCTION CO.,INC. (4.46%)
MOORE CONSTRUCTION, INC. (0.62%)
DUSTROL, INC.(0.09%)
SAMMY G. SMALLWOOD (1.19%)
COWBELL TRAFFIC SERVICES, INC. (0.17%)
MARTIN MARIETTA MATERIALS, INC.( 30.80%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (0.68%)
Contract # 09123214
Totals 5218898.13 0.00 5556556.90 100.0

CountyRED RIVER
Highway FM 44
From FM 412
To FM 911
CSJ 0427-01-037
Proj ID STP 2016(363)
Work Type REHABILITATION OF EXISTING ROAD
 
10.363 4617291.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 222
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0427-01-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163241
Totals 4617291.24 0.00 0.00 0.0

CountyLAMAR
Highway FM 137
From @ DENTON CREEK
To .
CSJ 0435-01-053
Proj ID BR 2013(680)
Work Type BRIDGE REPLACEMENT
 
0.216 960387.80 0.00 954523.46 100.0
CountyLAMAR
Highway CS
From CR E050-1
To AT DENTON CREEK
CSJ 0901-29-055
Proj ID BR 1102(219)
Work Type BRIDGE REPLACEMENT
 
0.138 428290.88 0.00 405519.98 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-26-13
Work Began 09-24-13
Work Completed 07-10-15
Time Computed 09-24-13
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 196
Percent Time Used 103
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-053
DUSTIN ALLEN, INC. (5.64%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.90%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.05%)
MCL CONTRACTING, LLC (0.51%)
SCOTT PAVING, INC. (0.76%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.62%)
FRITCHER CONSTRUCTION SERVICES (4.14%)
Contract # 05133226
Totals 1388678.68 0.00 1360043.44 100.0

CountyLAMAR
Highway FM 38
From LCR 34150
To FM 2820
CSJ 0435-01-063
Proj ID STP 2014(334)
Work Type REHABILITATION OF EXISTING ROAD
 
2.829 1267350.13 0.00 1425674.12 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-14
Work Began 05-06-14
Work Completed 07-27-15
Time Computed 05-19-14
Contract Working Days 96
Addl Days Granted 5
Working Days Charged 100
Percent Time Used 99
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-063
MOORE CONSTRUCTION, INC. (1.81%)
PANOLA SIGN & BARRICADE, INC.(0.43%)
CATACON, INC.(3.00%)
BAHENA CONSTRUCTION CO.,INC. ( 11.63%)
SAMMY G. SMALLWOOD (1.17%)
STRIPING TECHNOLOGY, L.P.(1.67%)
Contract # 01143015
Totals 1267350.13 0.00 1425674.12 100.0

CountyLAMAR
Highway FM 137
From FM 38
To US 82
CSJ 0435-01-068
Proj ID STP 2016(099)
Work Type REHABILITATION OF EXISTING ROAD
 
8.998 3768340.10 373472.54 583385.78 15.4
Work Order 11-13-15
Work Began 12-09-15
Work Completed  
Time Computed 01-12-16
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 9
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-068
N-LINE TRAFFIC MAINTENANCE, L.P. (0.72%)
STRIPING TECHNOLOGY, L.P.(3.34%)
CATOCON, INC.(1.79%)
MOORE CONSTRUCTION, INC. (1.99%)
SAMMY SMALLWOOD COMPANY(4.58%)
BAHENA CONSTRUCTION CO.,INC. (1.46%)
MURRAY CONSTRUCTION(1.48%)
ACU CONSTRUCTION LLC (0.65%)
Contract # 09153025
Totals 3768340.10 373472.54 583385.78 15.4

CountyGRAYSON
Highway FM 902
From US 377
To SH 289
CSJ 0510-01-026
Proj ID STP 2015(309)
Work Type REHABILITATION OF EXISTING ROAD
 
14.427 7337375.52 491244.22 1929438.09 26.2
Work Order 01-02-15
Work Began 09-28-15
Work Completed  
Time Computed 04-02-15
Contract Working Days 304
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 50
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-01-026
TEXOP CONSTRUCTION (0.05%)
CATOCON, INC.(1.83%)
FARR FOUNDATION, INC.(4.74%)
LYON BARRICADE AND CONSTRUCTION CO.(0.46%)
A.E. MOORE CONSTRUCTION, INC. DBA(1.15%)
MURRAY CONSTRUCTION(1.26%)
SAMMY G. SMALLWOOD (1.75%)
STRIPING TECHNOLOGY, L.P.(1.54%)
TEXANA LAND & ASPHALT, INC.(2.35%)
BAHENA CONSTRUCTION CO.,INC. ( 14.62%)
Contract # 11143220
Totals 7337375.52 491244.22 1929438.09 26.2

CountyGRAYSON
Highway FM 902
From SH 5
To SH 11
CSJ 0510-02-028
Proj ID STP 2013(839)
Work Type REHABILITATION OF EXISTING ROAD
 
7.973 4317753.44 4957.90 4171949.87 96.6
Work Order 09-06-13
Work Began 01-03-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 291
Percent Time Used 81
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-02-028
CROSSROADS, L.P. (1.02%)
MOORE CONSTRUCTION, INC. (1.38%)
CATOCON, INC.(1.05%)
DUSTIN ALLEN, INC. (0.25%)
BAHENA CONSTRUCTION CO.,INC. (4.13%)
PEACHTREE CONSTRUCTION, LTD. (7.61%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.95%)
Contract # 07133220
Totals 4317753.44 4957.90 4171949.87 96.6

CountyDELTA
Highway SH 19 ETC
From @ BRUSHY CREEK
To .
CSJ 0525-01-020
Proj ID BR 1502(141)
Work Type BRIDGE REPLACEMENT
 
0.678 4018602.90 58756.50 251185.50 6.2
Work Order 06-30-15
Work Began 09-22-15
Work Completed  
Time Computed 08-30-15
Contract Working Days 348
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 13
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0525-01-020
PANOLA SIGN & BARRICADE, INC.(0.71%)
MOORE CONSTRUCTION, INC. (1.43%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (4.08%)
DUSTIN ALLEN, INC. (3.15%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.02%)
STRIPING TECHNOLOGY, L.P.(1.08%)
PENHALL COMPANY(0.23%)
TEX OP CONSTRUCTION, LP(0.62%)
WITHERS CONSTRUCTION, LLC(0.79%)
Contract # 05153217
Totals 4018602.90 58756.50 251185.50 6.2

CountyHOPKINS
Highway FM 71
From FM 3236
To SH 19
CSJ 0546-06-017
Proj ID STP 2015(235)
Work Type REHABILITATION OF EXISTING ROAD
 
4.049 1903182.02 6596.10 1776577.49 93.3
Work Order 12-05-14
Work Began 12-11-14
Work Completed  
Time Computed 02-03-15
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 60
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-06-017
PANOLA SIGN & BARRICADE, INC.(0.53%)
STRIPING TECHNOLOGY, L.P.(1.87%)
WITHERS CONSTRUCTION, LLC(1.15%)
MOORE CONSTRUCTION, INC. (1.65%)
SAMMY G. SMALLWOOD (1.32%)
BAHENA CONSTRUCTION CO.,INC. ( 10.61%)
ANCHOR CONTRACTING, LLC(0.25%)
Contract # 10143211
Totals 1903182.02 6596.10 1776577.49 93.3

CountyFRANKLIN
Highway FM 71
From SH 37
To TITUS C/L
CSJ 0546-07-013
Proj ID STP 2015(422)
Work Type REHABILITATION OF EXISTING ROAD
 
7.546 3055233.71 1200.00 2834210.39 92.7
Work Order 01-16-15
Work Began 01-30-15
Work Completed  
Time Computed 03-17-15
Contract Working Days 198
Addl Days Granted 0
Working Days Charged 158
Percent Time Used 79
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-07-013
FLEX SUPPLY, LLC (0.43%)
MOORE CONSTRUCTION, INC. (4.11%)
CATACON, INC.(2.07%)
BAHENA CONSTRUCTION CO.,INC. ( 10.96%)
STRIPING TECHNOLOGY, L.P.(2.78%)
SAMMY G. SMALLWOOD (0.78%)
ANCHOR CONTRACTING, LLC(0.35%)
Contract # 12143214
Totals 3055233.71 1200.00 2834210.39 92.7