Monthly State Let Construction Report For Paris District As Of Aug 10, 2015 Page 2 Of 4

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRAINS
Highway US 69
From 586FT NORTH OF FM 3299 INTERSECTION
To COUNTY ROAD 4530
CSJ 0203-03-042
Proj ID STP 1502(131)
Work Type OVERLAY
 
6.223 1742911.94 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-16-15
Work Began 00-00-00
Work Completed  
Time Computed 07-17-15
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0203-03-042
TOTAL HIGHWAY MAINTENANCE, LLC (0.31%)
Contract # 05153239
Totals 1742911.94 0.00 0.00 0.0

CountyRAINS
Highway US 69
From SH 19
To 586 NORTH OF FM 3299 INTERSECTION
CSJ 0203-03-044
Proj ID STP 1402(093)
Work Type MISCELLANEOUS CONSTRUCTION
 
3.240 4635055.96 273267.15 576275.78 12.4
Work Order 11-12-14
Work Began 02-26-15
Work Completed  
Time Computed 02-10-15
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 28
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0203-03-044
ALTUS TRAFFIC MANAGEMENT LLC (0.27%)
BAHENA CONSTRUCTION CO.,INC. ( 13.11%)
MOORE CONSTRUCTION, INC. (0.71%)
RK HALL, LLC ( 34.23%)
SAMMY G. SMALLWOOD (0.30%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(0.25%)
TEX OP CONSTRUCTION, LP(0.35%)
WITHERS CONSTRUCTION, LLC(0.37%)
STRIPING TECHNOLOGY, L.P.(0.77%)
Contract # 09143209
Totals 4635055.96 273267.15 576275.78 12.4

CountyDELTA
Highway FM 64
From FM 1532
To FM 3388
CSJ 0399-03-034
Proj ID STP 2013(547)
Work Type REHABILITATION OF EXISTING ROAD
 
4.939 1399777.15 0.00 1408019.11 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-06-13
Work Began 06-19-13
Work Completed 08-13-14
Time Computed 08-05-13
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 97
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0399-03-034
BAHENA CONSTRUCTION CO.,INC. (3.22%)
LYON BARRICADE AND CONSTRUCTION CO.(0.90%)
CATACON, INC.(1.28%)
SAMMY G. SMALLWOOD (3.10%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.05%)
MOORE CONSTRUCTION, INC. (3.14%)
Contract # 04133008
Totals 1399777.15 0.00 1408019.11 100.0

CountyHOPKINS
Highway SH 19
From DELTA COUNTY LINE
To LOOP 301
CSJ 0400-02-048
Proj ID STP 1502(137)
Work Type OVERLAY
 
12.204 1267814.14 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-15-15
Work Began 00-00-00
Work Completed  
Time Computed 07-16-15
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0400-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153032
Totals 1267814.14 0.00 0.00 0.0

CountyHOPKINS
Highway SH 154
From 0.315 MILES NORTH OF FM 1567 EAST
To 0.195 MILES SOUTH OF CR 1104
CSJ 0401-01-022
Proj ID STP 2013(464)
Work Type UPGRADE TO NON - FREEWAY STANDARDS
 
4.973 6591501.99 3994.57 6086956.98 92.3
Work Order 05-13-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 353
Percent Time Used 77
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0401-01-022
PANOLA SIGN & BARRICADE, INC.(0.54%)
BAHENA CONSTRUCTION CO.,INC. (9.56%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.24%)
FORTSON CONTRACTING, INC.(4.14%)
STRIPING TECHNOLOGY, L.P.(1.24%)
MOORE CONSTRUCTION, INC. (0.57%)
TEXANA LAND & ASPHALT, INC.(0.57%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. ( 13.00%)
Contract # 03133219
Totals 6591501.99 3994.57 6086956.98 92.3

CountyGRAYSON
Highway US 69
From 0.490 MI. NORTH OF SH 11
To 0.638 MI. SOUTH OF SH 56
CSJ 0410-02-030
Proj ID STP 2013(069)
Work Type REHABILITATION OF EXISTING ROAD
 
6.282 5218898.13 0.00 5556556.90 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-01-12
Work Began 11-09-12
Work Completed 09-02-14
Time Computed 04-30-13
Contract Working Days 131
Addl Days Granted 27
Working Days Charged 194
Percent Time Used 122
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0410-02-030
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.29%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.12%)
BAHENA CONSTRUCTION CO.,INC. (4.46%)
MOORE CONSTRUCTION, INC. (0.62%)
DUSTROL, INC.(0.09%)
SAMMY G. SMALLWOOD (1.19%)
COWBELL TRAFFIC SERVICES, INC. (0.17%)
MARTIN MARIETTA MATERIALS, INC.( 30.80%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (0.68%)
Contract # 09123214
Totals 5218898.13 0.00 5556556.90 100.0

CountyLAMAR
Highway FM 137
From @ DENTON CREEK
To .
CSJ 0435-01-053
Proj ID BR 2013(680)
Work Type BRIDGE REPLACEMENT
 
0.216 960387.80 3000.00 954523.46 100.0
CountyLAMAR
Highway CS
From CR E050-1
To AT DENTON CREEK
CSJ 0901-29-055
Proj ID BR 1102(219)
Work Type BRIDGE REPLACEMENT
 
0.138 428290.88 0.00 405519.98 100.0
Work Order 06-26-13
Work Began 09-24-13
Work Completed 07-10-15
Time Computed 09-24-13
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 196
Percent Time Used 103
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-053
DUSTIN ALLEN, INC. (5.64%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.90%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.05%)
MCL CONTRACTING, LLC (0.51%)
SCOTT PAVING, INC. (0.76%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.62%)
FRITCHER CONSTRUCTION SERVICES (4.14%)
Contract # 05133226
Totals 1388678.68 3000.00 1360043.44 100.0

CountyLAMAR
Highway FM 38
From LCR 34150
To FM 2820
CSJ 0435-01-063
Proj ID STP 2014(334)
Work Type REHABILITATION OF EXISTING ROAD
 
2.829 1267350.13 2015.27 1425674.12 100.0
Work Order 03-18-14
Work Began 05-06-14
Work Completed 07-27-15
Time Computed 05-19-14
Contract Working Days 96
Addl Days Granted 5
Working Days Charged 100
Percent Time Used 99
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-063
MOORE CONSTRUCTION, INC. (1.81%)
PANOLA SIGN & BARRICADE, INC.(0.43%)
CATACON, INC.(3.00%)
BAHENA CONSTRUCTION CO.,INC. ( 11.63%)
SAMMY G. SMALLWOOD (1.17%)
STRIPING TECHNOLOGY, L.P.(1.67%)
Contract # 01143015
Totals 1267350.13 2015.27 1425674.12 100.0

CountyGRAYSON
Highway FM 902
From US 377
To SH 289
CSJ 0510-01-026
Proj ID STP 2015(309)
Work Type REHABILITATION OF EXISTING ROAD
 
14.427 7337375.52 0.00 72856.25 0.9
Work Order 01-02-15
Work Began 00-00-00
Work Completed  
Time Computed 04-02-15
Contract Working Days 304
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 17
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-01-026
TEXOP CONSTRUCTION (0.05%)
CATOCON, INC.(1.83%)
FARR FOUNDATION, INC.(4.74%)
LYON BARRICADE AND CONSTRUCTION CO.(0.46%)
A.E. MOORE CONSTRUCTION, INC. DBA(1.15%)
MURRAY CONSTRUCTION(1.26%)
SAMMY G. SMALLWOOD (1.75%)
STRIPING TECHNOLOGY, L.P.(1.54%)
TEXANA LAND & ASPHALT, INC.(2.35%)
BAHENA CONSTRUCTION CO.,INC. ( 14.62%)
Contract # 11143220
Totals 7337375.52 0.00 72856.25 0.9

CountyGRAYSON
Highway FM 902
From SH 5
To SH 11
CSJ 0510-02-028
Proj ID STP 2013(839)
Work Type REHABILITATION OF EXISTING ROAD
 
7.973 4317753.44 63684.33 4140857.85 95.9
Work Order 09-06-13
Work Began 01-03-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 270
Percent Time Used 75
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-02-028
CROSSROADS, L.P. (1.02%)
MOORE CONSTRUCTION, INC. (1.38%)
CATOCON, INC.(1.05%)
DUSTIN ALLEN, INC. (0.25%)
BAHENA CONSTRUCTION CO.,INC. (4.13%)
PEACHTREE CONSTRUCTION, LTD. (7.61%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.48%)
Contract # 07133220
Totals 4317753.44 63684.33 4140857.85 95.9

CountyDELTA
Highway SH 19 ETC
From @ BRUSHY CREEK
To .
CSJ 0525-01-020
Proj ID BR 1502(141)
Work Type BRIDGE REPLACEMENT
 
0.678 4018602.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-15
Work Began 00-00-00
Work Completed  
Time Computed 08-30-15
Contract Working Days 348
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0525-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153217
Totals 4018602.90 0.00 0.00 0.0

CountyHOPKINS
Highway FM 71
From FM 3236
To SH 19
CSJ 0546-06-017
Proj ID STP 2015(235)
Work Type REHABILITATION OF EXISTING ROAD
 
4.049 1903182.02 134564.50 1752089.64 92.0
Work Order 12-05-14
Work Began 12-11-14
Work Completed  
Time Computed 02-03-15
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 56
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-06-017
PANOLA SIGN & BARRICADE, INC.(0.53%)
STRIPING TECHNOLOGY, L.P.(1.87%)
WITHERS CONSTRUCTION, LLC(1.15%)
MOORE CONSTRUCTION, INC. (1.65%)
SAMMY G. SMALLWOOD (1.32%)
BAHENA CONSTRUCTION CO.,INC. ( 10.61%)
ANCHOR CONTRACTING, LLC(0.25%)
Contract # 10143211
Totals 1903182.02 134564.50 1752089.64 92.0

CountyFRANKLIN
Highway FM 71
From SH 37
To TITUS C/L
CSJ 0546-07-013
Proj ID STP 2015(422)
Work Type REHABILITATION OF EXISTING ROAD
 
7.546 3055233.71 542127.58 2516307.89 82.3
Work Order 01-16-15
Work Began 01-30-15
Work Completed  
Time Computed 03-17-15
Contract Working Days 198
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 47
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-07-013
FLEX SUPPLY, LLC (0.43%)
MOORE CONSTRUCTION, INC. (4.11%)
CATACON, INC.(2.07%)
BAHENA CONSTRUCTION CO.,INC. ( 10.96%)
STRIPING TECHNOLOGY, L.P.(2.78%)
SAMMY G. SMALLWOOD (0.78%)
ANCHOR CONTRACTING, LLC(0.35%)
Contract # 12143214
Totals 3055233.71 542127.58 2516307.89 82.3

CountyFANNIN
Highway SH 121
From US 82
To SH 56
CSJ 0549-01-029
Proj ID STP 2012(575)
Work Type UPGRADE TO NON - FREEWAY STANDARDS
 
1.863 6855007.15 44397.71 3302550.98 49.5
Work Order 10-18-12
Work Began 03-11-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 284
Addl Days Granted 36
Working Days Charged 406
Percent Time Used 126
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-029
BAHENA CONSTRUCTION CO.,INC. ( 12.33%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.70%)
NE-TEX CONSTRUCTION, LTD.( 32.14%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.64%)
STRIPING TECHNOLOGY, L.P.(1.13%)
TEX OP CONSTRUCTION, LP(0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.69%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.13%)
Contract # 08123015
Totals 6855007.15 44397.71 3302550.98 49.5

CountyFANNIN
Highway SH 121
From 0.209 MILES NORTH OF BS 121D
To SH 56
CSJ 0549-01-034
Proj ID STP 2013(548)
Work Type HEAVY OVERLAY
 
5.696 3739245.50 0.00 4237745.35 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 01-14-14
Work Completed  
Time Computed 07-24-13
Contract Working Days 95
Addl Days Granted 34
Working Days Charged 191
Percent Time Used 148
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-034
TOTAL HIGHWAY MAINTENANCE, LLC (0.27%)
STRIPING TECHNOLOGY, L.P.(2.02%)
NE-TEX CONSTRUCTION, LTD.(1.74%)
TEX OP CONSTRUCTION, LP(0.12%)
MOORE CONSTRUCTION, INC. (0.52%)
Contract # 04133213
Totals 3739245.50 0.00 4237745.35 99.9

CountyHUNT
Highway SH 276
From 5.92 MILES EAST OF FM 751
To 0.17 MILES EAST OF FM 513
CSJ 0641-01-033
Proj ID C 641-1-33
Work Type BRIDGE REPLACEMENT
 
2.803 47845878.71 2044500.27 40555468.73 84.7
Work Order 08-28-12
Work Began 09-25-12
Work Completed  
Time Computed 02-25-13
Contract Working Days 671
Addl Days Granted 106
Working Days Charged 628
Percent Time Used 80
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0641-01-033
SOUTHWEST ENVIRONMENT SERVICES LLC (0.03%)
SCOTT DERR PAINTING CO (0.58%)
SAMMY G. SMALLWOOD (0.21%)
NORTH TEXAS REBAR, LLC (7.04%)
BAHENA CONSTRUCTION CO.,INC. (0.15%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
PEACHTREE CONSTRUCTION, LTD. (0.48%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.07%)
BOWMAN ENGINEERING & CONSULTING, INC.(5.78%)
Contract # 07123202
Totals 47845878.71 2044500.27 40555468.73 84.7

CountyHOPKINS
Highway FM 1567
From AT RUNNING CREEK
To .
CSJ 0641-05-016
Proj ID BR 2013(781)
Work Type BRIDGE REPLACEMENT
 
0.276 2644004.60 3048.00 2648544.56 99.9
Work Order 08-19-13
Work Began 11-04-13
Work Completed  
Time Computed 11-18-13
Contract Working Days 236
Addl Days Granted 21
Working Days Charged 251
Percent Time Used 97
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0641-05-016
ODUM SERVICES, L.P.(4.37%)
PANOLA SIGN & BARRICADE, INC.(0.85%)
HOUSTON SAWING & DRILLING(0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.53%)
STRIPING TECHNOLOGY, L.P.(2.53%)
DUSTIN ALLEN, INC. (1.34%)
Contract # 06133217
Totals 2644004.60 3048.00 2648544.56 99.9

CountyHUNT
Highway FM 36
From IH 30
To SH 276
CSJ 0642-03-022
Proj ID STP 1502(557)HES
Work Type HAZARD ELIMINATION & SAFETY
 
8.630 2623426.37 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0642-03-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153031
Totals 2623426.37 0.00 0.00 0.0

CountyGRAYSON
Highway FM 691
From FM 131 NORTH
To SH 91
CSJ 0666-01-024
Proj ID STP 2013(782)
Work Type WIDEN NON - FREEWAY
 
1.334 3093915.10 111397.41 2112969.04 69.7
Work Order 01-17-14
Work Began 06-16-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 210
Addl Days Granted 10
Working Days Charged 267
Percent Time Used 121
Contractor(s)
TEXANA LAND & ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0666-01-024
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
EROSION CONTROL MANAGEMENT SERVICES(0.20%)
CATACON, INC.(1.02%)
HIGHWAY 19 CONSTRUCTION, LLC ( 19.52%)
MCMAHON CONTRACTING, L.P.( 29.06%)
MOORE CONSTRUCTION, INC. (0.31%)
SCOTT DERR PAINTING CO, LLC(0.08%)
SAMMY G. SMALLWOOD (1.18%)
TEX OP CONSTRUCTION, LP(0.42%)
STRIPING TECHNOLOGY, L.P.(1.66%)
BREDA COMPANY, INC.(0.98%)
Contract # 10133026
Totals 3093915.10 111397.41 2112969.04 69.7

CountyHOPKINS
Highway FM 900
From AT W GREENWOOD CREEK
To .
CSJ 0680-05-008
Proj ID BR 0090(264)
Work Type BRIDGE REPLACEMENT
 
0.220 1570944.58 21045.00 22180.00 1.4
Work Order 04-20-15
Work Began 06-24-15
Work Completed  
Time Computed 06-20-15
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 10
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-05-008
N LINE TRAFFIC CONTROL (1.15%)
SAMMY G. SMALLWOOD (6.27%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.21%)
MESA ROD BUSTERS, INC. (0.32%)
MOORE CONSTRUCTION, INC. (1.19%)
STRIPING TECHNOLOGY, L.P.(0.80%)
Contract # 03153019
Totals 1570944.58 21045.00 22180.00 1.4

page 1 | page 2 | page 3 | page 4