Monthly State Let Construction Report For Paris District As Of Feb 11, 2016 Page 3 Of 4

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFANNIN
Highway SH 121
From US 82
To SH 56
CSJ 0549-01-029
Proj ID STP 2012(575)
Work Type UPGRADE TO NON - FREEWAY STANDARDS
 
1.863 6855007.15 87665.87 4516701.26 69.0
Work Order 10-18-12
Work Began 03-11-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 284
Addl Days Granted 36
Working Days Charged 514
Percent Time Used 160
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-029
BAHENA CONSTRUCTION CO.,INC. ( 12.74%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.70%)
NE-TEX CONSTRUCTION, LTD.( 37.43%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.64%)
STRIPING TECHNOLOGY, L.P.(1.13%)
TEX OP CONSTRUCTION, LP(0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.69%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.13%)
Contract # 08123015
Totals 6855007.15 87665.87 4516701.26 69.0

CountyFANNIN
Highway SH 121
From 0.209 MILES NORTH OF BS 121D
To SH 56
CSJ 0549-01-034
Proj ID STP 2013(548)
Work Type HEAVY OVERLAY
 
5.696 3739245.50 0.00 4237745.35 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 01-14-14
Work Completed  
Time Computed 07-24-13
Contract Working Days 95
Addl Days Granted 34
Working Days Charged 191
Percent Time Used 148
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-034
TOTAL HIGHWAY MAINTENANCE, LLC (0.27%)
STRIPING TECHNOLOGY, L.P.(2.02%)
NE-TEX CONSTRUCTION, LTD.(1.74%)
TEX OP CONSTRUCTION, LP(0.12%)
MOORE CONSTRUCTION, INC. (0.52%)
Contract # 04133213
Totals 3739245.50 0.00 4237745.35 99.9

CountyFRANKLIN
Highway IH 30
From HOPKINS COUNTY LINE (EB)
To TITUS COUNTY LINE
CSJ 0610-02-052
Proj ID NH 2016(100)
Work Type REHABILITATION OF EXISTING ROAD
 
10.722 9114259.96 0.00 0.00 0.0
CountyFRANKLIN
Highway IH 30
From HOPKINS COUNTY LINE (WB)
To TITUS COUNTY LINE
CSJ 0610-02-053
Proj ID NH 2016(100)
Work Type REHABILITATION OF EXISTING ROAD
 
10.722 7316744.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0610-02-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153003
Totals 16431004.72 0.00 0.00 0.0

CountyHUNT
Highway SH 276
From 5.92 MILES EAST OF FM 751
To 0.17 MILES EAST OF FM 513
CSJ 0641-01-033
Proj ID C 641-1-33
Work Type BRIDGE REPLACEMENT
 
2.803 47845878.71 206706.77 43922688.50 91.8
Work Order 08-28-12
Work Began 09-25-12
Work Completed  
Time Computed 02-25-13
Contract Working Days 671
Addl Days Granted 225
Working Days Charged 758
Percent Time Used 84
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0641-01-033
SOUTHWEST ENVIRONMENT SERVICES LLC (0.03%)
SCOTT DERR PAINTING CO (0.58%)
SAMMY G. SMALLWOOD (0.21%)
NORTH TEXAS REBAR, LLC (7.04%)
BAHENA CONSTRUCTION CO.,INC. (0.15%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
PEACHTREE CONSTRUCTION, LTD. (0.48%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.07%)
BOWMAN ENGINEERING & CONSULTING, INC.(5.78%)
ROADWAY CONSTRUCTION, LLC(0.82%)
Contract # 07123202
Totals 47845878.71 206706.77 43922688.50 91.8

CountyHOPKINS
Highway FM 1567
From AT RUNNING CREEK
To .
CSJ 0641-05-016
Proj ID BR 2013(781)
Work Type BRIDGE REPLACEMENT
 
0.276 2644004.60 18714.60 2767463.33 99.9
Work Order 08-19-13
Work Began 11-04-13
Work Completed  
Time Computed 11-18-13
Contract Working Days 236
Addl Days Granted 21
Working Days Charged 251
Percent Time Used 97
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0641-05-016
ODUM SERVICES, L.P.(4.37%)
PANOLA SIGN & BARRICADE, INC.(0.85%)
HOUSTON SAWING & DRILLING(0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.53%)
STRIPING TECHNOLOGY, L.P.(2.53%)
DUSTIN ALLEN, INC. (1.34%)
Contract # 06133217
Totals 2644004.60 18714.60 2767463.33 99.9

CountyHUNT
Highway FM 36
From IH 30
To SH 276
CSJ 0642-03-022
Proj ID STP 1502(557)HES
Work Type HAZARD ELIMINATION & SAFETY
 
8.630 2623426.37 140231.75 613745.60 23.3
Work Order 11-02-15
Work Began 11-09-15
Work Completed  
Time Computed 01-01-16
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 18
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0642-03-022
LYON BARRICADE AND CONSTRUCTION CO.(0.26%)
TRP CONSTRUCTION GROUP, LLC(1.78%)
WITHERS CONSTRUCTION, LLC(3.09%)
MOORE CONSTRUCTION, INC. (2.19%)
SAMMY SMALLWOOD COMPANY(0.91%)
BAHENA CONSTRUCTION CO.,INC. ( 26.96%)
GIST ENTERPRISES, INC. (5.98%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (5.53%)
Contract # 08153031
Totals 2623426.37 140231.75 613745.60 23.3

CountyGRAYSON
Highway FM 691
From FM 131 NORTH
To SH 91
CSJ 0666-01-024
Proj ID STP 2013(782)
Work Type WIDEN NON - FREEWAY
 
1.334 3093915.10 0.00 2903488.77 97.7
Work Order 01-17-14
Work Began 06-16-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 210
Addl Days Granted 10
Working Days Charged 345
Percent Time Used 156
Contractor(s)
TEXANA LAND & ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0666-01-024
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
EROSION CONTROL MANAGEMENT SERVICES(0.20%)
CATACON, INC.(1.02%)
HIGHWAY 19 CONSTRUCTION, LLC ( 19.52%)
MCMAHON CONTRACTING, L.P.( 29.06%)
MOORE CONSTRUCTION, INC. (0.31%)
SCOTT DERR PAINTING CO, LLC(0.08%)
SAMMY G. SMALLWOOD (1.18%)
TEX OP CONSTRUCTION, LP(0.42%)
STRIPING TECHNOLOGY, L.P.(1.66%)
BREDA COMPANY, INC.(0.98%)
Contract # 10133026
Totals 3093915.10 0.00 2903488.77 97.7

CountyHOPKINS
Highway FM 900
From AT W GREENWOOD CREEK
To .
CSJ 0680-05-008
Proj ID BR 0090(264)
Work Type BRIDGE REPLACEMENT
 
0.220 1570944.58 83455.00 111310.00 7.0
Work Order 04-20-15
Work Began 06-24-15
Work Completed  
Time Computed 06-20-15
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 33
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-05-008
N LINE TRAFFIC CONTROL (1.15%)
SAMMY G. SMALLWOOD (6.27%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.21%)
MESA ROD BUSTERS, INC. (0.32%)
MOORE CONSTRUCTION, INC. (1.19%)
STRIPING TECHNOLOGY, L.P.(0.80%)
Contract # 03153019
Totals 1570944.58 83455.00 111310.00 7.0

CountyLAMAR
Highway FM 79
From @ E. FORK SLOUGH CREEK
To .
CSJ 0688-02-055
Proj ID BR 2015(310)
Work Type BRIDGE REPLACEMENT
 
0.059 321632.67 14884.40 272437.33 93.2
CountyDELTA
Highway CR
From CR 215-2
To AT LAKE CREEK TRIBUTARY
CSJ 0901-31-126
Proj ID BR 2013(498)
Work Type BRIDGE REPLACEMENT
 
0.086 210016.78 1643.50 209160.66 99.5
Work Order 01-02-15
Work Began 02-20-15
Work Completed  
Time Computed 03-03-15
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 144
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0688-02-055
LYON BARRICADE AND CONSTRUCTION CO.(2.83%)
ODUM SERVICES, L.P.(2.38%)
HARTBEAT CONSTRUCTION(0.00%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.33%)
STRIPING TECHNOLOGY, L.P.(2.03%)
TEXANA LAND & ASPHALT, INC.(6.51%)
Contract # 11143016
Totals 531649.45 16527.90 481597.99 95.7

CountyLAMAR
Highway FM 1497 ETC
From AT CANEY CREEK
To .
CSJ 0688-03-023
Proj ID BR 2014(202)
Work Type BRIDGE REPLACEMENT
 
0.585 2196575.03 19132.50 1810825.89 82.4
Work Order 12-10-13
Work Began 03-18-14
Work Completed  
Time Computed 03-10-14
Contract Working Days 381
Addl Days Granted 0
Working Days Charged 349
Percent Time Used 91
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0688-03-023
SOUTHWEST ENVIRONMENT SERVICES LLC (1.42%)
SAMMY G. SMALLWOOD (3.45%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.06%)
TEX OP CONSTRUCTION, LP(0.73%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.54%)
ACTION SERVICES(0.33%)
SOTO"S STEEL (0.31%)
PENHALL COMPANY(0.18%)
FRITCHER CONSTRUCTION SERVICES (1.60%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (0.85%)
SCOTT PAVING, INC. (1.04%)
MCL CONTRACTING, LLC (0.36%)
Contract # 11133009
Totals 2196575.03 19132.50 1810825.89 82.4

CountyHUNT
Highway FM 1570
From FM 2101
To SH 34
CSJ 0692-01-017
Proj ID STP 2016(743)
Work Type OVERLAY
 
5.999 2207943.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0692-01-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163218
Totals 2207943.10 0.00 0.00 0.0

CountyGRAYSON
Highway SH 91
From AT U.P. RAILROAD IN NORTH DENISON
To RR DOT # 410 961N
CSJ 0705-01-023
Proj ID STP 2010(911)RGS
Work Type MISCELLANEOUS CONSTRUCTION
 
0.584 6566674.51 0.00 6556672.41 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-02-10
Work Began 01-24-11
Work Completed 02-25-15
Time Computed 08-18-10
Contract Working Days 354
Addl Days Granted 102
Working Days Charged 630
Percent Time Used 138
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0705-01-023
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.28%)
J.V. CONCRETE CONSTRUCTION ( 10.15%)
DUSTROL, INC. (ROANOKE)(1.35%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.64%)
WEBBER BARRIER SERVICES, INC.(3.40%)
T-BAR FENCE, INC.(0.18%)
S & S BRIDGE PAINTING, INC.(0.36%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.56%)
NORTH TEXAS REBAR, LLC (0.04%)
PRIMATE CONSTRUCTION, INC. (0.14%)
Contract # 06103204
Totals 6566674.51 0.00 6556672.41 100.0

CountyGRAYSON
Highway SH 91
From AT SHAWNEE CREEK
To .
CSJ 0705-01-027
Proj ID ER 2016(253)
Work Type EMERGENCY RELIEF PROJECT
 
0.282 1734743.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0705-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153045
Totals 1734743.20 0.00 0.00 0.0

CountyGRAYSON
Highway FM 120
From CENTER AVE
To OKLAHOMA STATE LINE
CSJ 0728-02-029
Proj ID STP 1502(558)HES
Work Type HAZARD ELIMINATION & SAFETY
 
6.486 2460214.08 19116.00 19116.00 0.7
Work Order 10-22-15
Work Began 00-00-00
Work Completed  
Time Computed 12-21-15
Contract Working Days 116
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 6
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0728-02-029
ALTUS TRAFFIC MANAGEMENT LLC (0.51%)
Contract # 08153225
Totals 2460214.08 19116.00 19116.00 0.7

CountyGRAYSON
Highway FM 121
From SH 289
To 1200 FT WEST OF FM 3356
CSJ 0729-01-037
Proj ID STP 1502(559)HES
Work Type HAZARD ELIMINATION & SAFETY
 
6.958 4609064.06 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 272
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0729-01-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153228
Totals 4609064.06 0.00 0.00 0.0

CountyGRAYSON
Highway FM 121
From AT WEST FORK OF PILOT GROVE CREEK
To .
CSJ 0729-02-026
Proj ID BR 1502(261)
Work Type REPLACE BRIDGE
 
0.193 1590415.60 64972.60 176683.60 11.1
Work Order 07-30-15
Work Began 10-20-15
Work Completed  
Time Computed 08-31-15
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 21
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0729-02-026
ALTUS TRAFFIC MANAGEMENT LLC (1.30%)
STRIPE-A-ZONE, INC.(1.56%)
A.E. MOORE CONSTRUCTION, INC. DBA(1.83%)
ODUM SERVICES, L.P.(2.63%)
PENHALL COMPANY(0.22%)
FOUNDATION DRILLERS, INC.(3.38%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.36%)
Contract # 06153031
Totals 1590415.60 64972.60 176683.60 11.1

CountyLAMAR
Highway FM 195
From 5.215 MI N OF US 82
To 2.0 MI S OF FM 906
CSJ 0730-02-013
Proj ID STP 2013(783)
Work Type REHABILITATION OF EXISTING ROAD
 
4.962 1632328.37 0.00 1500955.74 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-13
Work Began 08-15-13
Work Completed 07-24-14
Time Computed 08-16-13
Contract Working Days 79
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 77
Contractor(s)
TEXANA LAND & ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0730-02-013
STRIPING TECHNOLOGY, L.P.(2.60%)
R. K. HALL CONSTRUCTION, LTD.( 46.27%)
LYON BARRICADE AND CONSTRUCTION CO.(0.57%)
DUSTROL, INC.(2.61%)
MOORE CONSTRUCTION, INC. (0.76%)
RK HALL, LLC ( 46.27%)
Contract # 06133018
Totals 1632328.37 0.00 1500955.74 100.0

CountyHOPKINS
Highway FM 1870
From SH 11
To CR 2309
CSJ 0735-05-017
Proj ID STP 2016(101)
Work Type REHABILITATION OF EXISTING ROAD
 
3.815 1161897.12 0.00 0.00 0.0
CountyHOPKINS
Highway FM 1870
From SH 11
To CR 2309
CSJ 0735-05-020
Proj ID STP 2016(102)HES
Work Type HAZARD ELIMINATION & SAFETY
 
3.819 542959.77 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0735-05-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153218
Totals 1704856.89 0.00 0.00 0.0

CountyDELTA
Highway FM 1533
From FM 1530
To FM 128
CSJ 0749-04-011
Proj ID STP 2015(537)
Work Type REHABILITATION OF EXISTING ROAD
 
3.686 1574292.03 0.00 1517589.38 96.4
Work Order 02-20-15
Work Began 03-10-15
Work Completed  
Time Computed 03-08-15
Contract Working Days 99
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 102
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0749-04-011
BAHENA CONSTRUCTION CO.,INC. ( 11.46%)
SAMMY G. SMALLWOOD (0.86%)
CATACON, INC.(1.14%)
STRIPING TECHNOLOGY, L.P.(1.94%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MOORE CONSTRUCTION, INC. (2.98%)
Contract # 01153010
Totals 1574292.03 0.00 1517589.38 96.4

CountyHOPKINS
Highway FM 69
From 1.553 MI S OF FM 1537
To 3.830 MI N OF FM 1537
CSJ 0766-01-027
Proj ID STP 2014(203)
Work Type REHABILITATION OF EXISTING ROAD
 
5.383 1863527.19 0.00 1884502.86 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 04-09-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 186
Addl Days Granted 19
Working Days Charged 230
Percent Time Used 112
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0766-01-027
SAMMY G. SMALLWOOD (1.49%)
DUSTIN ALLEN, INC. (0.72%)
CATACON, INC.(5.26%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.17%)
MOORE CONSTRUCTION, INC. (3.75%)
SCOTT PAVING, INC. ( 15.94%)
BAHENA CONSTRUCTION CO.,INC. ( 11.29%)
LYON BARRICADE AND CONSTRUCTION CO.(0.95%)
TEXANA LAND & ASPHALT, INC.(0.64%)
Contract # 11133210
Totals 1863527.19 0.00 1884502.86 99.9