Monthly Local Let Maintenance Report For Paris District As Of Jul 11, 2014 Page 2 Of 5

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHUNT
Highway IH0030
From VARIOUS ROADWAYS IN HUNT COUNTY
To ALSO IN RAINS COUNTY ON OCCASION
CSJ 6247-77-001
Proj ID RMC - 624777001
Work Type ONE WAY TRAFFIC CONTROL (FLAGGING)
 
0.001 64148.00 9301.46 112488.10 99.9
Work Order 11-29-12
Work Began 01-02-13
Work Completed  
Time Computed 01-09-13
Contract Working Days 261
Addl Days Granted 261
Working Days Charged 376
Percent Time Used 72
Contractor(s)
MORTON ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6247-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11120105
Totals 64148.00 9301.46 112488.10 99.9

CountyGRAYSON
Highway US0075
From VARIOUS ROADWAYS IN
To GRAYSON COUNTY
CSJ 6249-15-001
Proj ID RMC - 624915001
Work Type SWEEPING
 
0.001 122170.00 290.00 110620.00 90.5
Work Order 05-02-13
Work Began 05-13-13
Work Completed  
Time Computed 05-20-13
Contract Working Days 254
Addl Days Granted 2
Working Days Charged 256
Percent Time Used 100
Contractor(s)
R RESPONSE DELIVERY SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6249-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11120104
Totals 122170.00 290.00 110620.00 90.5

CountyGRAYSON
Highway US0082
From VARIOUS ROADWAYS IN GRAYSON AND
To ON OCCASION IN FANNIN COUNTY
CSJ 6250-16-001
Proj ID RMC - 625016001
Work Type ONE WAY TRAFFIC CONTROL (FLAGGING)
 
0.001 69192.50 9708.24 83776.15 99.9
Work Order 01-07-13
Work Began 01-07-13
Work Completed  
Time Computed 01-14-13
Contract Working Days 254
Addl Days Granted 160
Working Days Charged 374
Percent Time Used 90
Contractor(s)
CHITWOOD, INC
SUBCONTRACTOR(S) FOR CCSJ: 6250-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12120101
Totals 69192.50 9708.24 83776.15 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATONS IN HOPKINS
To AND FRANKLIN COUNTIES
CSJ 6251-65-001
Proj ID RMC - 625165001
Work Type CLEANING / SWEEPING HIGHWAYS
 
0.001 68700.00 0.00 45600.00 66.3
Work Order 02-21-13
Work Began 03-08-13
Work Completed  
Time Computed 03-15-13
Contract Working Days 508
Addl Days Granted 0
Working Days Charged 329
Percent Time Used 64
Contractor(s)
R RESPONSE DELIVERY SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6251-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01130105
Totals 68700.00 0.00 45600.00 66.3

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN
To HOPKINS COUNTY
CSJ 6252-31-001
Proj ID SUP - 625231001
Work Type LANDSCAPE MAINTENANCE
 
0.001 13081.00 1058.00 1058.00 8.0
Work Order 05-19-14
Work Began 00-00-00
Work Completed  
Time Computed 06-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6252-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140131
Totals 13081.00 1058.00 1058.00 8.0

CountyGRAYSON
Highway FM0697
From VARIOUS ROADWAYS IN GRAYSON
To AND FANNIN COUNTIES
CSJ 6255-66-001
Proj ID RMC - 625566001
Work Type SAFETY TREE TRIMMING
 
0.001 23343.81 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS CUTTERS
SUBCONTRACTOR(S) FOR CCSJ: 6255-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03130104
Totals 23343.81 0.00 0.00 0.0

CountyLAMAR
Highway US0271
From VARIOUS LOCATIONS IN
To PARIS DISTRICT
CSJ 6258-93-001
Proj ID RMC - 625893001
Work Type ON CALL LARGE SIGN MAINTENANCE
 
0.001 196595.27 11016.25 75504.68 38.4
Work Order 09-03-13
Work Began 10-25-13
Work Completed  
Time Computed 09-13-13
Contract Working Days 425
Addl Days Granted 0
Working Days Charged 291
Percent Time Used 68
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07130101
Totals 196595.27 11016.25 75504.68 38.4

CountyFRANKLIN
Highway IH0030
From VARIOUS ROADWAYS IN
To FRANKLIN COUNTY
CSJ 6259-01-001
Proj ID SUP - 625901001
Work Type PICNIC AREA MAINTENANCE
 
0.010 13010.00 1255.00 12305.00 94.5
Work Order 06-24-13
Work Began 07-01-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6259-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130131
Totals 13010.00 1255.00 12305.00 94.5

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS IN
To PARIS DISTRICT
CSJ 6259-33-001
Proj ID RMC - 625933001
Work Type ILLUMINATION MAINTENANCE
 
0.001 123125.00 0.00 30347.50 24.6
Work Order 01-10-14
Work Began 00-00-00
Work Completed  
Time Computed 01-20-14
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 114
Percent Time Used 43
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11130103
Totals 123125.00 0.00 30347.50 24.6

CountyFRANKLIN
Highway IH0030
From FRANKLIN COUNTY MAINTENANCE COMPLEX
To AT MT. VERNON
CSJ 6260-22-001
Proj ID SUP - 626022001
Work Type JANITORIAL MAINTENANCE
 
0.010 15841.70 1110.93 13742.43 86.7
Work Order 07-30-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 334
Percent Time Used 91
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07130131
Totals 15841.70 1110.93 13742.43 86.7

CountyFANNIN
Highway FM1396
From VARIOUS LOCATIONS
To IN PARIS DISTRICT
CSJ 6260-68-001
Proj ID BPM - 626068001
Work Type BPM - BENT REPAIR AND INSTALL TIE BEAMS
 
0.001 177280.00 0.00 81500.00 45.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-14
Work Began 00-00-00
Work Completed  
Time Computed 06-16-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 18
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6260-68-001
DALLAS LITE AND BARRICADE INC. (1.75%)
Contract # 03140103
Totals 177280.00 0.00 81500.00 45.9

CountyHOPKINS
Highway IH0030
From VARIOUS ROADWAYS IN HOPKINS
To AND FRANKLIN COUNTIES
CSJ 6260-84-001
Proj ID RMC - 626084001
Work Type ON - CALL MBGF REPAIR
 
0.010 162258.00 18525.00 91934.00 56.6
Work Order 09-06-13
Work Began 09-12-13
Work Completed  
Time Computed 09-19-13
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 24
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130107
Totals 162258.00 18525.00 91934.00 56.6

CountyRED RIVER
Highway US0082
From VARIOUS LOCATIONS
To IN RED RIVER COUNTY
CSJ 6261-05-001
Proj ID RMC - 626105001
Work Type ON CALL TREE REMOVAL
 
0.001 248450.00 0.00 179336.00 72.1
Work Order 10-03-13
Work Began 10-07-13
Work Completed  
Time Computed 10-14-13
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 128
Percent Time Used 73
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130104
Totals 248450.00 0.00 179336.00 72.1

CountyRAINS
Highway US0069
From RAINS COUNTY
To MAINTENANCE OFFICE COMPLEX
CSJ 6261-08-001
Proj ID SUP - 626108001
Work Type GROUNDS MAINTENANCE
 
0.001 10620.00 930.00 6800.00 64.0
Work Order 08-01-13
Work Began 08-06-13
Work Completed  
Time Computed 08-06-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 329
Percent Time Used 90
Contractor(s)
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6261-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07130132
Totals 10620.00 930.00 6800.00 64.0

CountyRED RIVER
Highway US0082
From RED RIVER COUNTY
To MAINTENANCE OFFICE COMPLEX
CSJ 6261-09-001
Proj ID SUP - 626109001
Work Type GROUNDS MAINTENANCE
 
0.010 6550.00 645.00 2845.00 43.4
Work Order 08-12-13
Work Began 08-17-13
Work Completed  
Time Computed 08-17-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 318
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6261-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130131
Totals 6550.00 645.00 2845.00 43.4

CountyRAINS
Highway US0069
From RAINS COUNTY MAINTENANCE COMPLEX
To IN EMORY
CSJ 6261-10-001
Proj ID SUP - 626110001
Work Type JANITORIAL MAINTENANCE
 
0.001 14258.50 958.79 11650.47 81.7
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130132
Totals 14258.50 958.79 11650.47 81.7

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS
To IN GRAYSON CO.
CSJ 6261-19-001
Proj ID SUP - 626119001
Work Type LITTER PICK UP
 
0.001 56843.09 3721.95 47076.29 82.8
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 82
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6261-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130133
Totals 56843.09 3721.95 47076.29 82.8

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN
To HOPKINS/FRANKLIN COUNTIES
CSJ 6261-20-001
Proj ID SUP - 626120001
Work Type LITTER PICKUP
 
0.001 121008.22 2863.40 87043.89 71.9
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 82
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6261-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130134
Totals 121008.22 2863.40 87043.89 71.9

CountyHUNT
Highway IH0030
From VARIOUS LOCATIONS IN
To HUNT COUNTY
CSJ 6261-21-001
Proj ID SUP - 626121001
Work Type LITTER PICKUP
 
0.001 79306.86 3275.32 53847.14 67.8
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 82
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130135
Totals 79306.86 3275.32 53847.14 67.8

CountyLAMAR
Highway US0082
From VARIOUSS LOCATIONS IN
To LAMAR, DELTA, AND RED RIVER CO.
CSJ 6261-22-001
Proj ID SUP - 626122001
Work Type LITTER PICKUP
 
0.001 123754.72 7103.37 92790.77 74.9
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 82
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6261-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130136
Totals 123754.72 7103.37 92790.77 74.9