Monthly Local Let Maintenance Report For Paris District As Of Oct 14, 2014 Page 3 Of 5

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGRAYSON
Highway US0082
From VARIOUS LOCATIONS IN
To GRAYSON COUNTY
CSJ 6262-72-001
Proj ID RMC - 626272001
Work Type DEBRIS REMOVAL
 
0.001 59748.00 1968.00 54567.00 91.3
Work Order 10-03-13
Work Began 10-14-13
Work Completed  
Time Computed 10-14-13
Contract Working Days 305
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 89
Contractor(s)
CHITWOOD, INC
SUBCONTRACTOR(S) FOR CCSJ: 6262-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09130102
Totals 59748.00 1968.00 54567.00 91.3

CountyGRAYSON
Highway SH0091
From VARIOUS LOCATIONS IN GRAYSON, FANNIN,
To HUNT, AND DELTA COUNTIES
CSJ 6262-73-001
Proj ID BPM - 626273001
Work Type BRIDGE ABUTMENT / EROSION REPAIR
 
0.001 316650.00 0.00 286420.25 92.5
Work Order 02-21-14
Work Began 03-03-14
Work Completed  
Time Computed 03-10-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 124
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6262-73-001
ALTUS TRAFFIC MANAGEMENT LLC (2.08%)
Contract # 01140102
Totals 316650.00 0.00 286420.25 92.5

CountyDELTA
Highway SH0024
From DELTA COUNTY MAINTENANCE COMPLEX
To IN COOPER
CSJ 6263-17-001
Proj ID SUP - 626317001
Work Type JANITORIAL MAINTENANCE
 
0.001 11802.00 0.00 10965.71 92.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09130131
Totals 11802.00 0.00 10965.71 92.9

CountyFANNIN
Highway US0082
From VARIOUS ROADWAYS IN
To FANNIN COUNTY
CSJ 6265-05-001
Proj ID RMC - 626505001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 225886.00 0.00 211790.95 93.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 30
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130102
Totals 225886.00 0.00 211790.95 93.7

CountyRED RIVER
Highway US0082
From VARIOUS ROADWAYS IN
To RED RIVER COUNTY
CSJ 6265-06-001
Proj ID RMC - 626506001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 152493.00 0.00 97792.64 64.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 47
Contractor(s)
RICKEY BAIRD
SUBCONTRACTOR(S) FOR CCSJ: 6265-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130103
Totals 152493.00 0.00 97792.64 64.1

CountyDELTA
Highway SH0024
From VARIOUS ROADWAYS IN
To DELTA COUNTY
CSJ 6265-07-001
Proj ID RMC - 626507001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 104426.00 0.00 88638.00 84.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 32
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130104
Totals 104426.00 0.00 88638.00 84.8

CountyRAINS
Highway US0069
From VARIOUS ROADWAYS IN
To RAINS AND HUNT COUNTIES
CSJ 6265-08-001
Proj ID RMC - 626508001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 153253.00 0.00 78343.00 51.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 13
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130105
Totals 153253.00 0.00 78343.00 51.1

CountyHUNT
Highway SH0011
From VARIOUS ROADWAYS IN
To HUNT COUNTY
CSJ 6265-09-001
Proj ID RMC - 626509001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 142250.00 0.00 76457.84 53.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 55
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130106
Totals 142250.00 0.00 76457.84 53.7

CountyFRANKLIN
Highway SH0037
From VARIOUS ROADWAYS IN
To FRANKLIN COUNTY
CSJ 6265-10-001
Proj ID RMC - 626510001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 98384.00 0.00 55642.00 56.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 28
Contractor(s)
EASTGATE SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6265-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130107
Totals 98384.00 0.00 55642.00 56.5

CountyLAMAR
Highway US0082
From VARIOUS ROADWAYS IN
To LAMAR COUNTY
CSJ 6265-11-001
Proj ID RMC - 626511001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 203825.76 0.00 144386.63 70.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 41
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130108
Totals 203825.76 0.00 144386.63 70.8

CountyGRAYSON
Highway US0075
From VARIOUS ROADWAYS IN
To GRAYSON COUNTY
CSJ 6265-12-001
Proj ID RMC - 626512001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 126227.64 0.00 93538.20 74.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 52
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130109
Totals 126227.64 0.00 93538.20 74.1

CountyGRAYSON
Highway US0069
From VARIOUS ROADWAYS IN
To GRAYSON COUNTY
CSJ 6265-13-001
Proj ID RMC - 626513001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 206792.00 0.00 174972.00 84.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 25
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6265-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130110
Totals 206792.00 0.00 174972.00 84.6

CountyHOPKINS
Highway IH0030
From VARIOUS ROADWAYS IN
To HOPKINS COUNTY
CSJ 6265-14-001
Proj ID RMC - 626514001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 222766.00 0.00 171733.00 77.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 59
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130111
Totals 222766.00 0.00 171733.00 77.0

CountyHOPKINS
Highway SH0019
From VARIOUS ROADWAYS IN
To HOPKINS COUNTY
CSJ 6265-15-001
Proj ID RMC - 626515001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 137739.00 0.00 73806.00 53.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 59
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130112
Totals 137739.00 0.00 73806.00 53.5

CountyDELTA
Highway SH0024
From DELTA COUNTY
To PICNIC MAINTENANCE
CSJ 6265-52-001
Proj ID SUP - 626552001
Work Type PICNIC AREA MAINTENANCE
 
0.010 14775.00 500.00 9965.00 67.4
Work Order 10-21-13
Work Began 11-01-13
Work Completed  
Time Computed 11-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 334
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6265-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10130131
Totals 14775.00 500.00 9965.00 67.4

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS IN LAMAR, DELTA,
To AND RED RIVER COUNTIES
CSJ 6266-10-001
Proj ID RMC - 626610001
Work Type ON CALL ROADWAY DRAINAGE IMPROVEMENT
 
0.001 187850.00 9993.85 79634.10 42.3
Work Order 04-02-14
Work Began 05-01-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 28
Contractor(s)
ANCHOR CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6266-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140103
Totals 187850.00 9993.85 79634.10 42.3

CountyRED RIVER
Highway US0082
From VARIOUS ROADWAYS
To IN RED RIVER COUNTY
CSJ 6266-14-001
Proj ID SUP - 626614001
Work Type PICNIC AREA MAINTENANCE
 
0.001 21795.00 1610.00 17675.00 81.0
Work Order 11-05-13
Work Began 11-17-13
Work Completed  
Time Computed 11-17-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 318
Percent Time Used 86
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6266-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11130131
Totals 21795.00 1610.00 17675.00 81.0

CountyLAMAR
Highway FM1502
From VARIOUS LOCATIONS IN LAMAR, DELTA,
To AND RED RIVER COUNTIES
CSJ 6266-33-001
Proj ID RMC - 626633001
Work Type CROSS DRAINAGE STRUCTURE REPLACEMENT
 
0.001 294995.00 9000.00 286620.75 99.9
Work Order 04-18-14
Work Began 05-05-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 137
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6266-33-001
PANOLA SIGN & BARRICADE, INC.(2.37%)
Contract # 03140104
Totals 294995.00 9000.00 286620.75 99.9

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS IN LAMAR, DELTA,
To AND RED RIVER COUNTIES
CSJ 6266-40-001
Proj ID RMC - 626640001
Work Type ON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001 147784.00 2615.00 106121.00 71.8
Work Order 02-10-14
Work Began 00-00-00
Work Completed  
Time Computed 02-19-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 32
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140103
Totals 147784.00 2615.00 106121.00 71.8

CountyFANNIN
Highway US0082
From VARIOUS ROADWAYS IN
To FANNIN COUNTY
CSJ 6266-49-001
Proj ID SUP - 626649001
Work Type LITTER PICK UP
 
0.010 22982.36 0.00 20559.36 89.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-25-13
Work Began 12-01-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 275
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 25
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6266-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11130132
Totals 22982.36 0.00 20559.36 89.4

page 1 | page 2 | page 3 | page 4 | page 5