Monthly Local Let Maintenance Report For Paris District As Of Jul 11, 2014 Page 3 Of 5

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRAINS
Highway US0069
From VARIOUS LOCATIONS
To IN RAINS COUNTY
CSJ 6261-23-001
Proj ID SUP - 626123001
Work Type LITTER PICKUP
 
0.001 45668.87 0.00 32535.31 71.2
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 82
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6261-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130137
Totals 45668.87 0.00 32535.31 71.2

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS IN
To GRAYSON COUNTY
CSJ 6262-48-001
Proj ID RMC - 626248001
Work Type LANDSCAPE MAINTENANCE
 
0.100 107569.60 7294.01 20960.02 19.4
Work Order 02-25-14
Work Began 00-00-00
Work Completed  
Time Computed 03-10-14
Contract Working Days 508
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 15
Contractor(s)
TANDEM MOWING SERVICE, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6262-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130113
Totals 107569.60 7294.01 20960.02 19.4

CountyHOPKINS
Highway IH0030
From VARIOUS ROADWAYS IN
To HOPKINS AND FRANKLIN COUNTIES
CSJ 6262-56-001
Proj ID RMC - 626256001
Work Type POTHOLE REPAIR
 
0.001 204416.00 15261.24 117323.92 57.3
Work Order 11-06-13
Work Began 11-13-13
Work Completed  
Time Computed 11-20-13
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 85
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10130102
Totals 204416.00 15261.24 117323.92 57.3

CountyHUNT
Highway US0069
From VARIOUS LOCATIONS IN
To HUNT AND RAINS COUNTIES
CSJ 6262-57-001
Proj ID RMC - 626257001
Work Type POTHOLE REPAIR
 
0.001 207248.00 54714.14 148166.03 71.4
Work Order 11-06-13
Work Began 11-13-13
Work Completed  
Time Computed 11-20-13
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 82
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10130101
Totals 207248.00 54714.14 148166.03 71.4

CountyGRAYSON
Highway US0082
From VARIOUS LOCATIONS IN
To GRAYSON COUNTY
CSJ 6262-72-001
Proj ID RMC - 626272001
Work Type DEBRIS REMOVAL
 
0.001 59748.00 4777.00 39764.00 66.5
Work Order 10-03-13
Work Began 10-14-13
Work Completed  
Time Computed 10-14-13
Contract Working Days 305
Addl Days Granted 0
Working Days Charged 196
Percent Time Used 64
Contractor(s)
CHITWOOD, INC
SUBCONTRACTOR(S) FOR CCSJ: 6262-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09130102
Totals 59748.00 4777.00 39764.00 66.5

CountyGRAYSON
Highway SH0091
From VARIOUS LOCATIONS IN GRAYSON, FANNIN,
To HUNT, AND DELTA COUNTIES
CSJ 6262-73-001
Proj ID BPM - 626273001
Work Type BRIDGE ABUTMENT / EROSION REPAIR
 
0.001 316650.00 8510.00 286420.25 92.5
Work Order 02-21-14
Work Began 03-03-14
Work Completed  
Time Computed 03-10-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 124
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6262-73-001
ALTUS TRAFFIC MANAGEMENT LLC (2.08%)
Contract # 01140102
Totals 316650.00 8510.00 286420.25 92.5

CountyDELTA
Highway SH0024
From DELTA COUNTY MAINTENANCE COMPLEX
To IN COOPER
CSJ 6263-17-001
Proj ID SUP - 626317001
Work Type JANITORIAL MAINTENANCE
 
0.001 11802.00 836.29 8630.23 73.1
Work Order 09-30-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09130131
Totals 11802.00 836.29 8630.23 73.1

CountyFANNIN
Highway US0082
From VARIOUS ROADWAYS IN
To FANNIN COUNTY
CSJ 6265-05-001
Proj ID RMC - 626505001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 225886.00 0.00 97284.00 43.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 15
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130102
Totals 225886.00 0.00 97284.00 43.0

CountyRED RIVER
Highway US0082
From VARIOUS ROADWAYS IN
To RED RIVER COUNTY
CSJ 6265-06-001
Proj ID RMC - 626506001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 152493.00 0.00 43183.78 28.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 19
Contractor(s)
RICKEY BAIRD
SUBCONTRACTOR(S) FOR CCSJ: 6265-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130103
Totals 152493.00 0.00 43183.78 28.3

CountyDELTA
Highway SH0024
From VARIOUS ROADWAYS IN
To DELTA COUNTY
CSJ 6265-07-001
Proj ID RMC - 626507001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 104426.00 0.00 54692.00 52.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 17
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130104
Totals 104426.00 0.00 54692.00 52.3

CountyRAINS
Highway US0069
From VARIOUS ROADWAYS IN
To RAINS AND HUNT COUNTIES
CSJ 6265-08-001
Proj ID RMC - 626508001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 153253.00 0.00 78343.00 51.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 13
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130105
Totals 153253.00 0.00 78343.00 51.1

CountyHUNT
Highway SH0011
From VARIOUS ROADWAYS IN
To HUNT COUNTY
CSJ 6265-09-001
Proj ID RMC - 626509001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 142250.00 0.00 9741.00 6.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 22
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130106
Totals 142250.00 0.00 9741.00 6.8

CountyFRANKLIN
Highway SH0037
From VARIOUS ROADWAYS IN
To FRANKLIN COUNTY
CSJ 6265-10-001
Proj ID RMC - 626510001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 98384.00 0.00 55642.00 56.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 28
Contractor(s)
EASTGATE SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6265-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130107
Totals 98384.00 0.00 55642.00 56.5

CountyLAMAR
Highway US0082
From VARIOUS ROADWAYS IN
To LAMAR COUNTY
CSJ 6265-11-001
Proj ID RMC - 626511001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 203825.76 0.00 88948.59 43.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 21
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130108
Totals 203825.76 0.00 88948.59 43.6

CountyGRAYSON
Highway US0075
From VARIOUS ROADWAYS IN
To GRAYSON COUNTY
CSJ 6265-12-001
Proj ID RMC - 626512001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 126227.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130109
Totals 126227.64 0.00 0.00 0.0

CountyGRAYSON
Highway US0069
From VARIOUS ROADWAYS IN
To GRAYSON COUNTY
CSJ 6265-13-001
Proj ID RMC - 626513001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 206792.00 0.00 120204.00 58.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 17
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6265-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130110
Totals 206792.00 0.00 120204.00 58.1

CountyHOPKINS
Highway IH0030
From VARIOUS ROADWAYS IN
To HOPKINS COUNTY
CSJ 6265-14-001
Proj ID RMC - 626514001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 222766.00 0.00 29998.00 13.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 16
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130111
Totals 222766.00 0.00 29998.00 13.4

CountyHOPKINS
Highway SH0019
From VARIOUS ROADWAYS IN
To HOPKINS COUNTY
CSJ 6265-15-001
Proj ID RMC - 626515001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 137739.00 0.00 4594.00 3.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-14
Work Began 06-02-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 27
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130112
Totals 137739.00 0.00 4594.00 3.3

CountyDELTA
Highway SH0024
From DELTA COUNTY
To PICNIC MAINTENANCE
CSJ 6265-52-001
Proj ID SUP - 626552001
Work Type PICNIC AREA MAINTENANCE
 
0.010 14775.00 1030.00 6705.00 45.3
Work Order 10-21-13
Work Began 11-01-13
Work Completed  
Time Computed 11-01-13
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6265-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10130131
Totals 14775.00 1030.00 6705.00 45.3

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS IN LAMAR, DELTA,
To AND RED RIVER COUNTIES
CSJ 6266-10-001
Proj ID RMC - 626610001
Work Type ON CALL ROADWAY DRAINAGE IMPROVEMENT
 
0.001 187850.00 18493.75 25701.75 13.6
Work Order 04-02-14
Work Began 05-01-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 9
Contractor(s)
ANCHOR CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6266-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140103
Totals 187850.00 18493.75 25701.75 13.6