Monthly Local Let Maintenance Report For Paris District As Of Apr 10, 2015 Page 3 Of 6

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDELTA
Highway SH0019
From FOR THE DELTA COUNTY
To MAINTENANCE OFFICE COMPLEX
CSJ 6270-34-001
Proj ID SUP - 627034001
Work Type GROUNDS MAINTENANCE
 
0.001 5425.00 0.00 2550.00 47.0
Work Order 03-12-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6270-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140132
Totals 5425.00 0.00 2550.00 47.0

CountyLAMAR
Highway US0271
From DISTRICT HEADQUARTERS
To AT 1365 N MAIN, PARIS, TEXAS
CSJ 6270-36-001
Proj ID SUP - 627036001
Work Type JANITORIAL MAINTENANCE
 
0.001 31700.00 1700.00 31700.00 99.9
Work Order 03-26-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 363
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6270-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140133
Totals 31700.00 1700.00 31700.00 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN HOPKINS, FRANKLIN
To HUNT AND RAINS COUNTY
CSJ 6270-48-001
Proj ID RMC - 627048001
Work Type ON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001 226485.00 0.00 109358.00 48.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-14
Work Began 00-00-00
Work Completed  
Time Computed 12-12-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 16
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140101
Totals 226485.00 0.00 109358.00 48.2

CountyFRANKLIN
Highway IH0030
From FRANKLIN CO MAINTENANCE
To COMPLEX
CSJ 6271-64-001
Proj ID SUP - 627164001
Work Type GROUNDS MAINTENANCE
 
0.001 6525.00 217.50 5655.00 86.6
Work Order 04-07-14
Work Began 05-01-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 334
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6271-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140132
Totals 6525.00 217.50 5655.00 86.6

CountyHOPKINS
Highway SH0011
From HOPKINS CO MAINTENANCE
To OFFICE COMPLEX
CSJ 6271-65-001
Proj ID SUP - 627165001
Work Type GROUNDS MAINTENANCE
 
0.001 6342.00 362.00 5430.00 85.6
Work Order 04-07-14
Work Began 05-06-14
Work Completed  
Time Computed 05-06-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 330
Percent Time Used 90
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6271-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140131
Totals 6342.00 362.00 5430.00 85.6

CountyHUNT
Highway IH0030
From HUNT COUNTY AREA OFFICE AND
To MAINTENANCE COMPLEX
CSJ 6271-66-001
Proj ID SUP - 627166001
Work Type GROUNDS MAINTENANCE
 
0.001 0.00 435.00 10005.00 0.0
Work Order 05-08-14
Work Began 05-08-14
Work Completed  
Time Computed 05-08-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 327
Percent Time Used 89
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6271-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140133
Totals 0.00 435.00 10005.00 0.0

CountyRAINS
Highway US0069
From VARIOUS ROADWAYS IN
To RAINS COUNTY
CSJ 6271-67-001
Proj ID SUP - 627167001
Work Type PICNIC AREA MAINTENANCE
 
0.001 28200.00 2075.00 23925.00 84.8
Work Order 05-09-14
Work Began 05-11-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 324
Percent Time Used 88
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6271-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140132
Totals 28200.00 2075.00 23925.00 84.8

CountyGRAYSON
Highway US0075
From VARIOUS
To .
CSJ 6271-95-001
Proj ID SUP - 627195001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 75244.62 0.00 68255.87 90.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 00-00-00
Work Completed  
Time Computed 04-01-14
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6271-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140136
Totals 75244.62 0.00 68255.87 90.7

CountyLAMAR
Highway LP0286
From GROUNDS MAINTENANCE AT
To PARIS_AREA OFFICE
CSJ 6271-99-001
Proj ID SUP - 627199001
Work Type GROUNDS MAINTENANCE
 
0.001 5700.00 0.00 2700.00 47.3
Work Order 06-24-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6271-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140131
Totals 5700.00 0.00 2700.00 47.3

CountyLAMAR
Highway BU0271B
From PARIS DISTRICT HEADQUARTERS
To AT 1365 N MAINT
CSJ 6272-42-001
Proj ID SUP - 627242001
Work Type GROUNDS MAINTENANCE
 
0.001 29960.00 0.00 17380.00 58.0
Work Order 06-01-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 302
Percent Time Used 82
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6272-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140134
Totals 29960.00 0.00 17380.00 58.0

CountyFANNIN
Highway US0082
From MAINTENANCE OFFICE
To LOCATED IN FANNIN COUNTY
CSJ 6272-60-001
Proj ID SUP - 627260001
Work Type JANITORIAL MAINTENANCE
 
0.001 12704.84 717.07 10095.70 79.4
Work Order 05-27-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6272-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140136
Totals 12704.84 717.07 10095.70 79.4

CountyLAMAR
Highway LP0286
From LAMAR MAINT OFFICE
To LOCATION IN LAMAR CO
CSJ 6272-61-001
Proj ID SUP - 627261001
Work Type JANITORIAL MAINTENANCE
 
0.001 10869.20 639.10 8466.00 77.8
Work Order 05-27-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6272-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140135
Totals 10869.20 639.10 8466.00 77.8

CountyFRANKLIN
Highway IH0030
From VARIOUS ROADWAYS IN
To FRANKLIN COUNTY
CSJ 6273-71-001
Proj ID SUP - 627371001
Work Type PICNIC AREA MAINTENANCE
 
0.001 13010.00 570.00 7740.00 59.4
Work Order 06-23-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6273-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140132
Totals 13010.00 570.00 7740.00 59.4

CountyFRANKLIN
Highway IH0030
From FRANKLIN COUNTY MAINT COMPLEX
To AT MT VERNON
CSJ 6275-09-001
Proj ID SUP - 627509001
Work Type JANITORIAL MAINTENANCE
 
0.001 16000.12 1122.04 10001.26 62.5
Work Order 07-29-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140133
Totals 16000.12 1122.04 10001.26 62.5

CountyRAINS
Highway US0069
From RAINS COUNTY
To MAINT COMPLEX
CSJ 6275-10-001
Proj ID SUP - 627510001
Work Type GROUNDS MAINTENANCE
 
0.001 10620.00 310.00 3720.00 35.0
Work Order 07-11-14
Work Began 08-06-14
Work Completed  
Time Computed 08-06-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 238
Percent Time Used 65
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6275-10-001
CARTHAGE DRILLING, INC.(0.00%)
Contract # 06140134
Totals 10620.00 310.00 3720.00 35.0

CountyRED RIVER
Highway US0082
From MAINTENANCE COMPLEX
To IN RED RIVER COUNTY
CSJ 6275-11-001
Proj ID SUP - 627511001
Work Type GROUNDS MAINTENANCE
 
0.001 6550.00 0.00 1075.00 16.4
Work Order 07-11-14
Work Began 08-17-14
Work Completed  
Time Computed 08-17-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 227
Percent Time Used 62
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6275-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140135
Totals 6550.00 0.00 1075.00 16.4

CountyHUNT
Highway IH0030
From VARIOUS LOCATIONS IN
To HUNT AND RAINS COUNTIES
CSJ 6275-56-001
Proj ID RMC - 627556001
Work Type ON CALL TREE REMOVAL
 
0.001 133485.00 23538.00 23538.00 17.6
Work Order 01-28-15
Work Began 02-05-15
Work Completed  
Time Computed 02-12-15
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 6
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140101
Totals 133485.00 23538.00 23538.00 17.6

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN
To HOPKINS AND FRANKLIN COUNTIES
CSJ 6275-57-001
Proj ID RMC - 627557001
Work Type ON CALL TREE REMOVAL
 
0.001 123650.00 30588.00 90232.00 72.9
Work Order 01-12-15
Work Began 01-20-15
Work Completed  
Time Computed 01-27-15
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 12
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140102
Totals 123650.00 30588.00 90232.00 72.9

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS
To IN GRAYSON COUNTY
CSJ 6276-39-001
Proj ID SUP - 627639001
Work Type LITTER PICK UP
 
0.001 44328.43 3664.40 26501.08 59.7
Work Order 08-22-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 57
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6276-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08140131
Totals 44328.43 3664.40 26501.08 59.7

CountyHOPKINS
Highway IH0030
From VARIOUS LOCAITONS IN
To HOPKINS/FRANKLIN COUNTIES
CSJ 6276-40-001
Proj ID SUP - 627640001
Work Type LITTER PICKUP
 
0.001 87552.32 9279.54 54181.18 61.8
Work Order 08-28-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 57
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6276-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08140132
Totals 87552.32 9279.54 54181.18 61.8