Monthly Local Let Maintenance Report For Tyler District As Of Jun 15, 2016 Page 2 Of 8

Last Update: Wednesday, June 15, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySMITH
Highway US0069
From TYLER MAINTENANCE SECTION
To SMITH CO., ETC.
CSJ 6257-82-001
Proj ID SUP - 625782001
Work Type LITTER PICK - UP
 
0.010 369112.69 0.00 344936.31 93.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-13
Work Began 09-27-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131017
Totals 369112.69 0.00 344936.31 93.4

CountyWOOD
Highway US0069
From MINEOLA MAINTENANCE SECTION
To WOOD CO., ETC.
CSJ 6257-83-001
Proj ID SUP - 625783001
Work Type LITTER PICK - UP
 
0.010 125955.30 0.00 113955.30 90.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-13
Work Began 11-26-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 730
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131018
Totals 125955.30 0.00 113955.30 90.4

CountyCHEROKEE
Highway LP0456
From JACKSONVILLE COMPLEX
To JACKSONVILLE COMPLEX
CSJ 6257-84-001
Proj ID SUP - 625784001
Work Type JANITORIAL MAINTENANCE
 
0.010 52047.36 0.00 43329.00 83.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-15-13
Work Began 09-03-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131009
Totals 52047.36 0.00 43329.00 83.2

CountyWOOD
Highway SL0564
From MINEOLA COMPLEX
To MINEOLA COMPLEX
CSJ 6257-85-001
Proj ID SUP - 625785001
Work Type JANITORIAL MAINTENANCE
 
0.010 35884.90 0.00 32107.25 89.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-15-13
Work Began 09-03-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131010
Totals 35884.90 0.00 32107.25 89.4

CountyGREGG
Highway SL0281
From LONGVIEW AREA OFC., MAINTENANCE OFC.
To AT 4549A LOOP 281 W. LONGVIEW, TX. 75604
CSJ 6257-86-001
Proj ID SUP - 625786001
Work Type JANITORIAL MAINTENANCE
 
0.001 64488.00 0.00 54442.42 84.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-30-13
Work Began 06-09-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 814
Addl Days Granted 0
Working Days Charged 821
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6257-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131005
Totals 64488.00 0.00 54442.42 84.4

CountyRUSK
Highway SH0043
From VARIOUS ROADWAYS
To IN HENDERSON MAINT. SECTION
CSJ 6261-65-001
Proj ID RMC - 626165001
Work Type TREE TRIMMING AND BRUSH REMOVAL
 
33.600 47040.00 0.00 47600.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-14-14
Work Began 03-12-14
Work Completed 08-18-14
Time Computed 03-03-14
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 97
Contractor(s)
KASPARIAN UNDERGROUND, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131008
Totals 47040.00 0.00 47600.00 100.0

CountySMITH
Highway US0069
From VARIOUS LOCATIONS IN
To THE TYLER DISTRICT
CSJ 6262-04-001
Proj ID RMC - 626204001
Work Type REPAIR & MTCE OF ILLUMINATION SYSTEMS
 
0.010 62360.00 0.00 204964.35 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-13-14
Work Began 01-21-14
Work Completed 01-27-15
Time Computed 01-20-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 255
Percent Time Used 100
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131003
Totals 62360.00 0.00 204964.35 100.0

CountyHENDERSON
Highway SL0007
From ATHENS AO, MAINT.OFC. REG. DIST
To CTR. (RDC), & REGIONAL SIGN SHOP
CSJ 6263-88-001
Proj ID SUP - 626388001
Work Type JANITORIAL
 
0.001 118864.00 0.00 111864.00 94.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-28-13
Work Began 09-03-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6263-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131005
Totals 118864.00 0.00 111864.00 94.1

CountyANDERSON
Highway SH0019
From PALESTINE MAINTENANCE OFFICE
To PALESTINE MAINTENANCE OFFICE
CSJ 6264-17-001
Proj ID SUP - 626417001
Work Type LAWN MAINTENANCE
 
0.001 27000.00 0.00 15375.00 56.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-17-13
Work Began 09-19-13
Work Completed  
Time Computed 09-17-13
Contract Working Days 713
Addl Days Granted 0
Working Days Charged 713
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6264-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131040
Totals 27000.00 0.00 15375.00 56.9

CountyGREGG
Highway SH0031
From VARIOUS ROADWAYS
To IN THE LONGVIEW MAINTENANCE SECTION
CSJ 6264-68-001
Proj ID RMC - 626468001
Work Type TREE REMOVAL
 
0.001 68875.00 0.00 137825.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-13-14
Work Began 03-04-14
Work Completed 01-31-15
Time Computed 02-10-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 245
Percent Time Used 96
Contractor(s)
3 FARMER ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131001
Totals 68875.00 0.00 137825.00 100.0

CountyHENDERSON
Highway US0175
From VARIOUS LOCATIONS
To IN HENDERSON COUNTY
CSJ 6266-47-001
Proj ID RMC - 626647001
Work Type DEBRIS REMOVAL
 
0.010 20988.00 0.00 23139.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-12-14
Work Began 06-16-14
Work Completed 06-30-15
Time Computed 06-23-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 255
Percent Time Used 100
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6266-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141003
Totals 20988.00 0.00 23139.00 100.0

CountyWOOD
Highway FM0014
From FM 14 IN THE MINEOLA SECTION
To FM 2908 IN THE TYLER SECTION
CSJ 6269-69-001
Proj ID RMC - 626969001
Work Type CULVERT REPAIR
 
0.001 89204.00 0.00 118681.13 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 01-25-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 100
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6269-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09151003
Totals 89204.00 0.00 118681.13 99.9

CountyHENDERSON
Highway US0175
From VARIOUS ROADWAYS IN
To THE ATHENS MAINTENANCE SECTION
CSJ 6270-69-001
Proj ID RMC - 627069001
Work Type SHORTLINE THERMOPLASTIC STRIPING
 
0.010 37924.93 0.00 69564.20 99.9
CountyVAN ZANDT
Highway SH0019
From VARIOUS ROADWAYS IN THE
To CANTON MAINTENANCE SECTION
CSJ 6270-69-002
Proj ID RMC - 627069002
Work Type SHORTLINE THERMOPLASTIC STRIPING
 
0.010 65016.35 0.00 127037.20 99.9
CountyRUSK
Highway US0259
From VARIOUS ROADWAYS IN THE
To HENDERSON MAINTENANCE SECTION
CSJ 6270-69-003
Proj ID RMC - 627069003
Work Type SHORTLINE THERMOPLASTIC STRIPING
 
0.010 34667.33 0.00 8432.25 24.3
CountyCHEROKEE
Highway US0079
From VARIOUS ROADWAYS IN THE
To JACKSONVILLE MAINTENANCE SECTION
CSJ 6270-69-004
Proj ID RMC - 627069004
Work Type SHORTLINE THERMOPLASTIC STRIPING
 
0.010 24216.16 0.00 0.00 0.0
CountyGREGG
Highway US0259
From VARIOUS ROADWAYS IN THE
To LONGVIEW MAINTENANCE SECTION
CSJ 6270-69-005
Proj ID RMC - 627069005
Work Type SHORTLINE THERMOPLASTIC STRIPING
 
0.010 18769.93 0.00 41873.35 99.9
CountyWOOD
Highway US0080
From VARIOUS ROADWAYS IN THE
To MINEOLA MAINTENANCE SECTION
CSJ 6270-69-006
Proj ID RMC - 627069006
Work Type SHORTLINE THERMOPLASTIC STRIPING
 
0.010 42534.38 0.00 39512.45 92.8
CountyANDERSON
Highway US0079
From VARIOUS ROADWAYS IN THE
To PALESTINE MAINTENANCE SECTION
CSJ 6270-69-007
Proj ID RMC - 627069007
Work Type SHORTLINE THERMOPLASTIC STRIPING
 
0.010 12891.27 0.00 9417.00 73.0
CountySMITH
Highway SH0031
From VARIOUS ROADWAYS IN THE
To TYLER MAINTENANCE SECTION
CSJ 6270-69-008
Proj ID RMC - 627069008
Work Type SHORTLINE THERMOPLASTIC STRIPING
 
0.010 46191.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 07-15-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 255
Percent Time Used 100
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6270-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141001
Totals 282212.14 0.00 295836.45 99.9

CountyVAN ZANDT
Highway SH0019
From VARIOUS ROADWAYS IN THE
To CANTON MAINTENANCE SECTION
CSJ 6272-10-001
Proj ID RMC - 627210001
Work Type TREE TRIMMING & BRUSH REMOVAL
 
120.640 144515.74 0.00 144515.74 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-14
Work Began 10-20-14
Work Completed  
Time Computed 10-27-14
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 47
Contractor(s)
FOWLER CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6272-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141001
Totals 144515.74 0.00 144515.74 99.9

CountyCHEROKEE
Highway US0069
From VARIOUS ROADWAYS IN THE
To JACKSONVILLE/RUSK MTCE. SECTION
CSJ 6272-11-001
Proj ID RMC - 627211001
Work Type TREE TRIMMING & BRUSH REMOVAL
 
137.650 180807.35 0.00 180807.35 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-14
Work Began 12-15-14
Work Completed 04-01-15
Time Computed 12-01-14
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 35
Contractor(s)
TERRY ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6272-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141002
Totals 180807.35 0.00 180807.35 100.0

CountyGREGG
Highway FM2906
From VARIOUS LOCATIONS IN THE
To LONGVIEW MAINTENANCE SECTION
CSJ 6272-12-001
Proj ID RMC - 627212001
Work Type TREE TRIMMING & BRUSH REMOVAL
 
19.990 42981.00 0.00 42981.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-17-14
Work Began 01-14-15
Work Completed 04-26-15
Time Computed 01-12-15
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 100
Contractor(s)
L&S EXCAVATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141003
Totals 42981.00 0.00 42981.00 100.0

CountySMITH
Highway SH0031
From VARIOUS LOCATIONS IN THE
To TYLER MAINTENANCE SECTION
CSJ 6272-14-001
Proj ID RMC - 627214001
Work Type TREE REMOVAL
 
0.010 166050.00 0.00 160685.00 96.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-16-14
Work Began 03-16-15
Work Completed  
Time Computed 01-02-15
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 251
Percent Time Used 98
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141005
Totals 166050.00 0.00 160685.00 96.1

CountyHENDERSON
Highway US0175
From SH 175 @ SL 7
To ATHENS - HENDERSON CO.
CSJ 6272-15-001
Proj ID RMC - 627215001
Work Type CONCRETE REPAIR
 
0.001 30250.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 4
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04161002
Totals 30250.00 0.00 0.00 0.0

CountyHENDERSON
Highway SH0334
From FM 344 AT PERSIMMON BRANCH FM 85
To IN HENDERSON COUNTY
CSJ 6272-17-001
Proj ID RMC - 627217001
Work Type BRIDGE RAIL REPAIR
 
0.001 62900.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06161002
Totals 62900.00 0.00 0.00 0.0

CountyANDERSON
Highway SH0019
From VARIOUS LOCATIONS IN THE
To PALESTINE MAINTENANCE SECTION
CSJ 6272-21-001
Proj ID RMC - 627221001
Work Type TREE REMOVAL
 
0.001 137675.00 0.00 212315.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-27-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 254
Percent Time Used 99
Contractor(s)
SG COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6272-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03151001
Totals 137675.00 0.00 212315.00 99.9