AVERAGE LOW BID UNIT PRICE - MAINTENANCE - WACO DISTRICT

Last Update: Wednesday, September 17, 2014
ITEMS 401 2001 TO 496 2060
Items Items Bid Code Range
0104 - 0168
0310 - 0361
0401 - 0496
0500 - 0556
0618 - 0688
0712 - 0776
1122 - 1122
3267 - 3271
5369 - 5369
6005 - 6834
7126 - 7602
8094 - 8852
401 2001 - 496 2060
Item No Description Units August 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
401 2001 FLOWABLE BACKFILL CY     380.000 168.05263 7
403 2001 TEMPORARY SPL SHORING SF     760.000 17.00000 1
416 2030 DRILL SHAFT (TRF SIG POLE) (24 IN) LF     26.000 118.46154 3
416 2031 DRILL SHAFT (TRF SIG POLE) (30 IN) LF     63.000 156.19048 2
416 2032 DRILL SHAFT (TRF SIG POLE) (36 IN) LF     256.000 213.16406 3
416 2033 DRILL SHAFT (TRF SIG POLE) (42 IN) LF     60.000 231.50000 2
416 2034 DRILL SHAFT (TRF SIG POLE) (48 IN) LF     40.000 800.00000 1
420 2001 CL A CONC (MISC) CY     5.000 750.00000 1
420 2002 CL B CONC (FLUME) CY     161.000 481.52174 2
420 2008 CL C CONC (WINGWALLS) CY     42.600 1,162.44131 2
420 2013 CL C CONC (MISC) CY     47.500 510.88000 4
422 2001 REINF CONC SLAB SF     40,036.000 11.00000 1
428 2002 CONC SURF TREAT (CLASS II) SY     4,379.000 2.50000 1
429 2007 CNC STR REP (HORIZONTAL) SF     28.000 90.00000 1
429 2008 CNC STR REP (VERTICAL OR OVERHEAD) SF     825.000 77.00303 7
429 2010 CNC STR REP (BRDG DECK) (FULL DEPTH) SF     50.000 85.00000 1
432 2001 RIPRAP (CONC) (4 IN) CY     10.800 500.00000 2
432 2002 RIPRAP (CONC) (5 IN) CY     1,502.900 228.86290 7
432 2019 RIPRAP (STONE PROTECTION) (12 IN) CY     2,127.000 107.87259 4
432 2021 RIPRAP (STONE PROTECTION) (18 IN) CY     5,747.600 114.58209 6
432 2023 RIPRAP (STONE PROTECTION) (24 IN) CY     633.000 105.63981 4
432 2033 RIPRAP (STONE COMMON) (DRY) (12 IN) CY     223.000 125.00000 1
432 2039 RIPRAP (MOW STRIP) (4 IN) CY     60.000 225.00000 2
432 2071 RIPRAP (STONE COMMON) (DRY) (24 IN) CY     147.000 125.00000 1
438 2001 CLEAN EXIST JOINTS LF     228.000 8.00000 1
438 2002 CLEAN AND SEAL EXIST JOINTS LF     3,752.000 12.97655 2
438 2006 CLEAN AND SEAL CRACKS LF     704.000 6.93182 4
438 2009 CLEAN AND SEAL EXIST JOINTS (CL - 7) LF     680.000 15.00000 2
442 2030 STR STL (PEDESTAL) LB     8,304.000 9.40535 2
442 2048 STRUCTURAL STEEL (MISC NON - BRIDGE) LB     444.000 5.00000 1
450 2039 RAIL (TY SSTR) (MOD) LF     520.000 85.00000 1
450 2062 RAIL (TY SSCB) LF     260.000 85.00000 1
452 2001 REMOV RAIL (CONC ELEMENTS) LF     520.000 40.00000 1
454 2004 ARMOR JOINT LF     358.000 45.00000 1
454 2007 HEADER TYPE EXPANSION JOINT CF     32.000 75.00000 1
454 2008 JOINT SEALANT LF     228.000 3.00000 1
459 2002 GABIONS (GALV) CY     585.000 171.88889 5
467 2240 SET (TY II) (36 IN) (RCP) (6: 1) (C) EA     3.000 600.00000 1
467 2266 SET (TY II) (36 IN) (CMP) (4: 1) (C) EA     4.000 600.00000 1
467 2286 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA     12.000 1,112.50000 3
467 2288 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA     17.000 658.82353 3
467 2303 SET (TY II) (24 IN) (CMP) (6: 1) (P) EA     6.000 866.66667 2
472 2005 REMOV & RE - LAY PIPE (24 IN) LF     32.000 10.00000 1
481 2013 PVC PIPE (SCH 40) (8 IN) LF     6,000.000 32.00000 1
496 2007 REMOV STR (PIPE) LF     18.000 10.00000 1
496 2060 REMOV STR (BRIDGE SLAB) LF     780.000 245.00000 1