Monthly State Let Construction Report For Yoakum District As Of Aug 10, 2015 Page 1 Of 5

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGONZALES
Highway US 90A
From 1.3 MI. WEST OF FM 2091
To TO US 183
CSJ 0025-06-053
Proj ID STP 2014(510)
Work Type ACP OVERLAY
 
4.567 1207655.31 0.00 1644731.20 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-05-14
Work Began 06-09-14
Work Completed 01-27-15
Time Computed 06-01-14
Contract Working Days 45
Addl Days Granted 7
Working Days Charged 43
Percent Time Used 82
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-06-053
COWBELL TRAFFIC SERVICES, INC. (1.07%)
SCR CONSTRUCTION CO., INC. (2.30%)
ROADSAFE TRAFFIC SYSTEMS, INC. (3.43%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
Contract # 03143213
Totals 1207655.31 0.00 1644731.20 100.0

CountyGONZALES
Highway SH 97 ETC
From .16 MI. S. OF S. SANDY FORK CK REL
To US 90
CSJ 0025-07-061
Proj ID STP 2015(238)
Work Type SEAL COAT
 
137.089 5886483.28 353265.38 6140064.24 99.9
Work Order 11-10-14
Work Began 05-05-15
Work Completed  
Time Computed 05-05-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 88
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-07-061
BATTERSON,LLP( 13.93%)
Contract # 10143206
Totals 5886483.28 353265.38 6140064.24 99.9

CountyVICTORIA
Highway US 59
From 0.105 MI. WEST OF BU 59-T
To .396 MI. WEST OF LP 463 IN VICTORIA
CSJ 0088-05-087
Proj ID NH 2014(454)
Work Type ACP OVERLAY
 
3.160 1504543.17 0.00 0.00 0.0
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 06-01-14
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143029
Totals 1504543.17 0.00 0.00 0.0

CountyVICTORIA
Highway US 59
From 0.02 MI. NORTH OF LOOP 463
To 0.03 MI. NORTH OF US 87
CSJ 0088-05-089
Proj ID C 88-5-89
Work Type CONSTRUCT FRONTAGE ROADS
 
3.446 14995694.93 475534.37 11672629.47 77.8
Work Order 08-19-13
Work Began 10-03-13
Work Completed  
Time Computed 09-15-13
Contract Working Days 270
Addl Days Granted 43
Working Days Charged 295
Percent Time Used 94
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-089
FLASHER EQUIPMENT COMPANY(0.68%)
JUST GROOVING, LTD.(0.02%)
THE LEVY COMPANY, L.P. (1.32%)
MURRAY CONSTRUCTION(0.30%)
PRIMATE CONSTRUCTION, INC. (0.24%)
ROADWAY SPECIALTIES, INC.(1.85%)
SHINN & GREGORY, INC.(0.66%)
BILL HALL JR. TRUCKING, LTD. (0.00%)
RAMI MATERIALS TRANSPORT, LLC(0.00%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
BRANNAN PAVING CO., LTD. (1.58%)
NATIONAL WORKS, INC. (0.41%)
Contract # 05133205
Totals 14995694.93 475534.37 11672629.47 77.8

CountyVICTORIA
Highway US 59
From 0.28 MI. SOUTH OF US 87
To 0.25 MI. NORTH OF US 87
CSJ 0088-05-090
Proj ID BR 1302(016)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.530 7826113.14 430186.94 5724988.27 73.1
Work Order 10-17-13
Work Began 06-02-14
Work Completed  
Time Computed 02-14-14
Contract Working Days 270
Addl Days Granted 10
Working Days Charged 203
Percent Time Used 72
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-090
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
ATS DRILLING, INC. ( 10.18%)
HAYWARD BAKER, INC.(1.25%)
PRIMATE CONSTRUCTION, INC. (0.13%)
WEST TEXAS RUMBLE STRIP(0.04%)
A & R DEMOLITION (1.59%)
ROADWAY SPECIALTIES, INC.(2.49%)
FLASHER EQUIPMENT COMPANY(0.43%)
THE LEVY COMPANY, L.P. (1.49%)
MCL CONTRACTING, LLC (0.79%)
BILL HALL JR. TRUCKING, LTD. (0.00%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
VALCO CONSTRUCTION (0.06%)
Contract # 07133043
Totals 7826113.14 430186.94 5724988.27 73.1

CountyVICTORIA
Highway US 59
From SP 91_________________0446020
To 0.157 MI. NORTH OF FM 446
CSJ 0088-05-093
Proj ID NH 2015(996)
Work Type ACP OVERLAY
 
3.359 2446596.31 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-093
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153041
Totals 2446596.31 0.00 0.00 0.0

CountyJACKSON
Highway US 59
From WHARTON C/L
To SH 172
CSJ 0089-05-045
Proj ID NH 2014(641)
Work Type ACP OVERLAY
 
4.659 3274455.77 49505.75 3508155.29 99.9
Work Order 05-20-14
Work Began 10-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 120
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-05-045
PRIMATE CONSTRUCTION, INC. ( 11.39%)
PENHALL COMPANY(0.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.54%)
R & A TRANSPORT, INC.(0.00%)
KL DURHAM CONSTRUCTION, LLC(3.83%)
Contract # 04143006
Totals 3274455.77 49505.75 3508155.29 99.9

CountyWHARTON
Highway US 59
From SL 523 NORTH OF LOUSIE
To SL 523 SOUTH OF LOUISE
CSJ 0089-06-082
Proj ID STP 2014(788)HES
Work Type INSTALL CABLE MEDIAN BARRIER
 
3.670 490190.00 0.00 474030.25 100.0
CountyCOLORADO
Highway SH 71
From 0.4 MI WEST OF FM 1890
To 0.4 MI SOUTH OF US 90
CSJ 0266-02-062
Proj ID STP 2014(789)HES
Work Type INSTALL MEDIAN BARRIER
 
4.006 391124.00 0.00 368276.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-02-14
Work Began 11-07-14
Work Completed 03-12-15
Time Computed 09-18-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 58
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-082
POTTS DISTRIBUTING CO. (0.00%)
Contract # 06143043
Totals 881314.00 0.00 842306.75 100.0

CountyWHARTON
Highway US 59
From AT FM 647, FM 1160 & FM 441
To UNDERPASSES
CSJ 0089-06-083
Proj ID NH 2014(996)
Work Type RAISE STRUCTURES
 
0.719 1645644.60 0.00 603504.62 36.6
Work Order 08-04-14
Work Began 04-08-15
Work Completed  
Time Computed 10-03-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 24
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-083
GMJ PAVING CO. ( 26.32%)
ODUM SERVICES, L.P.(4.22%)
A-1 EROSION CONTROL, LLC (0.85%)
LONESTAR TRAFFIC SAFETY, LLC (0.45%)
Contract # 06143058
Totals 1645644.60 0.00 603504.62 36.6

CountyWHARTON
Highway US 59
From AT INTERSECTION OF SH 71
To IN EL CAMPO
CSJ 0089-07-147
Proj ID NH 1402(107)
Work Type GREEN RIBBON LANDSCAPING
 
0.001 160087.79 0.00 158648.83 99.1
Work Order 10-17-14
Work Began 12-05-14
Work Completed  
Time Computed 12-05-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 64
Contractor(s)
GEORGE MEEKS LANDPRO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-07-147
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143027
Totals 160087.79 0.00 158648.83 99.1

CountyWHARTON
Highway US 59
From AT CR 212
To INTERSECTION
CSJ 0089-08-095
Proj ID NH 2013(917)
Work Type INTERSECTION IMPROVEMENT
 
2.526 2072944.64 0.00 2032302.12 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 02-24-14
Work Completed 12-31-14
Time Computed 01-22-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 71
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-08-095
COWBELL TRAFFIC SERVICES, INC. (0.78%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.36%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.51%)
FUQUAY, INC. (1.00%)
MURRAY CONSTRUCTION(0.64%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (2.45%)
Contract # 09133236
Totals 2072944.64 0.00 2032302.12 100.0

CountyFAYETTE
Highway US 290
From WASHINGTON COUNTY LINE
To LEE COUNTY LINE
CSJ 0114-08-034
Proj ID NH 2015(698)
Work Type PAVEMENT REPAIR & ACP OVERLAY
 
7.640 3140617.52 1846785.92 3280719.35 99.9
Work Order 03-18-15
Work Began 04-20-15
Work Completed  
Time Computed 04-20-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 75
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0114-08-034
DUSTROL, INC.(0.47%)
HUDSON, INC. (3.53%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.86%)
Contract # 02153237
Totals 3140617.52 1846785.92 3280719.35 99.9

CountyGONZALES
Highway US 87
From WILSON COUNTY LINE
To FM 77
CSJ 0143-06-029
Proj ID NH 2015(532)
Work Type PAVEMENT REPAIR AND SURFACING
 
3.254 5409576.71 0.00 41151.44 0.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-26-15
Work Began 07-20-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 9
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-06-029
FLASHER EQUIPMENT COMPANY(1.77%)
ALTUS TRAFFIC MANAGEMENT LLC (0.46%)
Contract # 01153207
Totals 5409576.71 0.00 41151.44 0.7

CountyDEWITT
Highway US 87
From US 183 IN CUERO
To TO SH 72
CSJ 0143-08-087
Proj ID NH 1502(122)
Work Type UPGRADE TRAFFIC SIGNALS
 
0.002 930045.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-15
Work Began 00-00-00
Work Completed  
Time Computed 10-30-15
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0143-08-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153216
Totals 930045.00 0.00 0.00 0.0

CountyDEWITT
Highway US 87
From SH 72
To US 183 IN CUERO
CSJ 0143-08-089
Proj ID NH 2015(425)
Work Type ACP OVERLAY
 
6.986 2789989.26 1231395.58 1231395.58 44.1
Work Order 02-13-15
Work Began 06-29-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 24
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-08-089
CHEROKEE SERVICES(0.69%)
COWBELL TRAFFIC SERVICE, INC.(0.51%)
ROADSAFE TRAFFIC SYSTEMS, INC. (3.03%)
Contract # 12143008
Totals 2789989.26 1231395.58 1231395.58 44.1

CountyGONZALES
Highway US 183
From BU 183 NORTH
To CONE STREET IN GONZALES
CSJ 0153-02-039
Proj ID NH 2013(591)
Work Type ACP OVERLAY
 
3.335 1398785.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-04-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0153-02-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153015
Totals 1398785.73 0.00 0.00 0.0

CountyDEWITT
Highway US 183
From EMIL BLANK ROAD
To 0.20 MI. NORTH OF US 77A
CSJ 0154-04-030
Proj ID C 154-4-30
Work Type CONSTRUCT AUX. LANES FOR SUPER 2
 
13.549 9614974.97 3966.10 9149657.86 95.1
Work Order 04-26-13
Work Began 06-13-13
Work Completed  
Time Computed 05-12-13
Contract Working Days 255
Addl Days Granted 2
Working Days Charged 257
Percent Time Used 100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0154-04-030
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.23%)
FLASHER EQUIPMENT COMPANY(1.84%)
M.V. HENKE ENTERPRISES, INC. (0.14%)
MPB, INC.(0.33%)
MURRAY CONSTRUCTION(0.39%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.41%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.71%)
BRANNAN PAVING COMPANY, INC. (8.08%)
R K STEPHENS CONSTRUCTION, LLC (0.53%)
Contract # 02133003
Totals 9614974.97 3966.10 9149657.86 95.1

CountyDEWITT
Highway US 183
From FM 2718
To GOLIAD C/L
CSJ 0155-01-038
Proj ID NH 1502(123)
Work Type PAVEMENT REPAIR AND RESURFACING
 
11.336 4639995.06 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-15
Work Began 00-00-00
Work Completed  
Time Computed 10-17-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0155-01-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153017
Totals 4639995.06 0.00 0.00 0.0

CountyMATAGORDA
Highway SH 35
From 0.75 MI. N. OF CHANNEL INDUSTRY RD.
To SH 71
CSJ 0179-06-042
Proj ID STP 1402(090)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
12.803 494554.71 0.00 45498.00 9.1
CountyMATAGORDA
Highway SH 71
From SH 111
To SH 35
CSJ 0266-07-020
Proj ID STP 1402(091)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
3.981 155355.94 0.00 0.00 0.0
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 02-14-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 23
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0179-06-042
RICE ENVIRONMENTAL SERVICES(2.08%)
BEAVER CONTRACTORS, LLC( 31.88%)
Contract # 08143232
Totals 649910.65 0.00 45498.00 7.0

CountyJACKSON
Highway SH 35
From MATAGORDA COUNTY LINE
To SH 172
CSJ 0179-09-033
Proj ID STP 2014(589)
Work Type ACP OVERLAY
 
8.109 2381189.69 850561.07 850561.07 35.7
Work Order 05-13-14
Work Began 07-14-15
Work Completed  
Time Computed 08-01-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 22
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0179-09-033
COWBELL TRAFFIC SERVICE, INC.(1.10%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.68%)
CLARK CONSTRUCTION OF TEXAS, INC.( 11.19%)
Contract # 04143214
Totals 2381189.69 850561.07 850561.07 35.7

page 1 | page 2 | page 3 | page 4 | page 5