Monthly State Let Construction Report For Yoakum District As Of Jul 11, 2014 Page 1 Of 3

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGONZALES
Highway US 90A ETC
From US 183
To BU 183V
CSJ 0025-06-052
Proj ID STP 2014(050)
Work Type SEAL COAT
 
126.131 5288542.63 2496223.03 5159578.48 97.5
Work Order 12-05-13
Work Began 05-05-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 57
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-06-052
BATTERSON,LLP( 14.15%)
Contract # 10133212
Totals 5288542.63 2496223.03 5159578.48 97.5

CountyGONZALES
Highway US 90A
From 1.3 MI. WEST OF FM 2091
To TO US 183
CSJ 0025-06-053
Proj ID STP 2014(510)
Work Type ACP OVERLAY
 
4.567 1207655.31 414973.50 414973.50 34.3
Work Order 05-05-14
Work Began 06-09-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 45
Addl Days Granted 7
Working Days Charged 4
Percent Time Used 7
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-06-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143213
Totals 1207655.31 414973.50 414973.50 34.3

CountyGONZALES
Highway SH 97 ETC
From SH 304
To 0.4 MI EAST OF FM 2814
CSJ 0025-07-062
Proj ID STP 2014(816)HESG
Work Type ADDING RUMBLE STRIP
 
204.581 669745.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-07-062
SURFACE PREPARATION TECHNOLOGIES, LLC( 1443.22%)
Contract # 04143035
Totals 669745.79 0.00 0.00 0.0

CountyVICTORIA
Highway US 59
From 0.105 MI. WEST OF BU 59-T
To .396 MI. WEST OF LP 463 IN VICTORIA
CSJ 0088-05-087
Proj ID NH 2014(454)
Work Type ACP OVERLAY
 
3.160 1504543.17 0.00 0.00 0.0
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 06-01-14
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143029
Totals 1504543.17 0.00 0.00 0.0

CountyVICTORIA
Highway US 59
From 0.02 MI. NORTH OF LOOP 463
To 0.03 MI. NORTH OF US 87
CSJ 0088-05-089
Proj ID C 88-5-89
Work Type CONSTRUCT FRONTAGE ROADS
 
3.446 14995694.93 784146.49 6534251.09 43.5
Work Order 08-19-13
Work Began 10-03-13
Work Completed  
Time Computed 09-15-13
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 132
Percent Time Used 48
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-089
FLASHER EQUIPMENT COMPANY(0.68%)
JUST GROOVING, LTD.(0.02%)
THE LEVY COMPANY, L.P. (1.32%)
MURRAY CONSTRUCTION(0.30%)
PRIMATE CONSTRUCTION, INC. (0.24%)
ROADWAY SPECIALTIES, INC.(1.85%)
SHINN & GREGORY, INC.(0.66%)
BILL HALL JR. TRUCKING, LTD. (0.00%)
RAMI MATERIALS TRANSPORT, LLC(0.00%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
Contract # 05133205
Totals 14995694.93 784146.49 6534251.09 43.5

CountyVICTORIA
Highway US 59
From 0.28 MI. SOUTH OF US 87
To 0.25 MI. NORTH OF US 87
CSJ 0088-05-090
Proj ID BR 1302(016)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.530 7826113.14 978228.91 1751195.56 22.3
Work Order 10-17-13
Work Began 06-02-14
Work Completed  
Time Computed 02-14-14
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 5
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-090
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
ATS DRILLING, INC. ( 10.18%)
HAYWARD BAKER, INC.(1.25%)
PRIMATE CONSTRUCTION, INC. (0.13%)
WEST TEXAS RUMBLE STRIP(0.04%)
A & R DEMOLITION (1.59%)
ROADWAY SPECIALTIES, INC.(2.49%)
FLASHER EQUIPMENT COMPANY(0.43%)
THE LEVY COMPANY, L.P. (1.49%)
MCL CONTRACTING, LLC (0.79%)
BILL HALL JR. TRUCKING, LTD. (0.00%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
Contract # 07133043
Totals 7826113.14 978228.91 1751195.56 22.3

CountyJACKSON
Highway US 59
From WHARTON C/L
To SH 172
CSJ 0089-05-045
Proj ID NH 2014(641)
Work Type ACP OVERLAY
 
4.659 3274455.77 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-05-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143006
Totals 3274455.77 0.00 0.00 0.0

CountyWHARTON
Highway US 59
From SL 523 NORTH OF LOUSIE
To SL 523 SOUTH OF LOUISE
CSJ 0089-06-082
Proj ID STP 2014(788)HES
Work Type INSTALL CABLE MEDIAN BARRIER
 
3.670 490190.00 0.00 0.00 0.0
CountyCOLORADO
Highway SH 71
From 0.4 MI WEST OF FM 1890
To 0.4 MI SOUTH OF US 90
CSJ 0266-02-062
Proj ID STP 2014(789)HES
Work Type INSTALL MEDIAN BARRIER
 
4.006 391124.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-082
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143043
Totals 881314.00 0.00 0.00 0.0

CountyWHARTON
Highway US 59
From AT FM 647, FM 1160 & FM 441
To UNDERPASSES
CSJ 0089-06-083
Proj ID NH 2014(996)
Work Type RAISE STRUCTURES
 
0.719 1645644.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143058
Totals 1645644.60 0.00 0.00 0.0

CountyWHARTON
Highway US 59
From AT CR 212
To INTERSECTION
CSJ 0089-08-095
Proj ID NH 2013(917)
Work Type INTERSECTION IMPROVEMENT
 
2.526 2072944.64 592942.64 1970448.22 95.0
Work Order 01-06-14
Work Began 02-24-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 71
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-08-095
COWBELL TRAFFIC SERVICES, INC. (0.78%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.36%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.51%)
FUQUAY, INC. (1.00%)
MURRAY CONSTRUCTION(0.64%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (2.45%)
Contract # 09133236
Totals 2072944.64 592942.64 1970448.22 95.0

CountyDEWITT
Highway US 183
From EMIL BLANK ROAD
To 0.20 MI. NORTH OF US 77A
CSJ 0154-04-030
Proj ID C 154-4-30
Work Type CONSTRUCT AUX. LANES FOR SUPER 2
 
13.549 9614974.97 1387730.22 6779721.36 70.5
Work Order 04-26-13
Work Began 06-13-13
Work Completed  
Time Computed 05-12-13
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 211
Percent Time Used 82
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0154-04-030
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.23%)
FLASHER EQUIPMENT COMPANY(1.84%)
M.V. HENKE ENTERPRISES, INC. (0.14%)
MPB, INC.(0.33%)
MURRAY CONSTRUCTION(0.39%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.41%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.71%)
Contract # 02133003
Totals 9614974.97 1387730.22 6779721.36 70.5

CountyJACKSON
Highway SH 35
From MATAGORDA COUNTY LINE
To SH 172
CSJ 0179-09-033
Proj ID STP 2014(589)
Work Type ACP OVERLAY
 
8.109 2381189.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0179-09-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143214
Totals 2381189.69 0.00 0.00 0.0

CountyAUSTIN
Highway SH 36
From SH 159 NORTH OF BELLVILLE
To WASHINGTON COUNTY LINE
CSJ 0187-02-064
Proj ID C 187-2-64
Work Type CONSTRUCT AUXILLARY LANES
 
8.540 10689701.03 517335.33 10446900.38 97.7
Work Order 10-24-12
Work Began 01-14-13
Work Completed  
Time Computed 12-23-12
Contract Working Days 270
Addl Days Granted 14
Working Days Charged 283
Percent Time Used 99
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0187-02-064
BATTERSON,LLP(2.16%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19%)
TEXAS ALTERNATIVE GRASSER, INC.(0.35%)
CEN TEX HYDROSEED, INC.(0.10%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.83%)
WEST TEXAS RUMBLE STRIP(0.06%)
MURRAY CONSTRUCTION(0.48%)
PEDRO CARLOS CONSTRUCTION CO.(2.35%)
FARR FOUNDATION, INC.(0.51%)
JEFFERY BAILEY TRUCKING, INC.(1.04%)
Contract # 08123209
Totals 10689701.03 517335.33 10446900.38 97.7

CountyAUSTIN
Highway SH 36
From 0.1 MI. NORTH OF US 90
To 0.1 MI. NORTH OF FM 1094
CSJ 0187-03-061
Proj ID NH 2012(466)
Work Type REHABILITATE ROADWAY
 
1.000 3799066.71 0.00 4061459.59 99.9
Work Order 06-29-12
Work Began 08-29-12
Work Completed  
Time Computed 08-28-12
Contract Working Days 210
Addl Days Granted 4
Working Days Charged 202
Percent Time Used 94
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0187-03-061
WOLFF CONSTRUCTION ( 16.03%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.74%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.34%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.07%)
MURRAY CONSTRUCTION(0.45%)
ROGER"S TREE SERVICE (0.15%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.48%)
BILL HALL JR. TRUCKING, LTD. (1.34%)
Contract # 04123202
Totals 3799066.71 0.00 4061459.59 99.9

CountyFAYETTE
Highway FM 155
From AT WILLIAMS CREEK
To .
CSJ 0211-09-029
Proj ID BR 2014(642)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.397 1540168.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0211-09-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143235
Totals 1540168.40 0.00 0.00 0.0

CountyWHARTON
Highway SH 60
From 0.215 MI. S. OF AUSTIN COUNTY LINE
To US 90A
CSJ 0240-02-030
Proj ID STP 2013(485)
Work Type RESTORE ROADWAY
 
4.819 2921571.83 376694.26 1955629.03 67.7
Work Order 05-29-13
Work Began 09-11-13
Work Completed  
Time Computed 07-28-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 125
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0240-02-030
RICE ENVIRONMENTAL SERVICES(1.00%)
D. I. J. CONSTRUCTION, INC.(2.90%)
MURRAY CONSTRUCTION(0.68%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.51%)
A.J.J.A . TRUCKING, INC. (2.83%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
STAFF CONCRETE (4.37%)
MPB, INC.(0.28%)
DEVTEX INC.(0.14%)
Contract # 03133234
Totals 2921571.83 376694.26 1955629.03 67.7

CountyWHARTON
Highway SH 71
From AT TRES PALACIOS RIVER IN EL CAMPO
To STR # 0266-06-036
CSJ 0266-06-044
Proj ID BR 2013(593)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.164 1218475.90 43778.00 662396.77 54.3
Work Order 09-10-13
Work Began 11-13-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 75
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-06-044
ENVIRONMENTAL ALLIES, L.P. (0.13%)
WILLOW CITY SIGN & RAIL, INC.(1.28%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.21%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
MESA ROD BUSTERS, INC. (0.89%)
YORK & YORK FOUNDATION DRILLING, INC.(7.13%)
JUST GROOVING, LTD.(0.29%)
Contract # 04133229
Totals 1218475.90 43778.00 662396.77 54.3

CountyWHARTON
Highway SH 71
From WCR 405
To MATAGORDA COUNTY LINE
CSJ 0266-06-045
Proj ID STP 2014(740)
Work Type PAVEMENT REPAIR AND SURFACING
 
5.473 2333301.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-06-045
PENHALL COMPANY(0.29%)
MURRAY CONSTRUCTION(0.25%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.75%)
Contract # 04143236
Totals 2333301.84 0.00 0.00 0.0

CountyFAYETTE
Highway US 77
From SCHULENBURG SOUTH CITY LIMITS
To LAVACA COUNTY LINE
CSJ 0269-01-027
Proj ID C 269-1-27
Work Type CONSTRUCT AUXILLARY LANES
 
14.309 6078391.95 0.00 6134359.32 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-13-12
Work Began 12-11-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 210
Addl Days Granted 4
Working Days Charged 211
Percent Time Used 98
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0269-01-027
FLASHER EQUIPMENT COMPANY(2.84%)
MURRAY CONSTRUCTION(0.54%)
M.V. HENKE ENTERPRISES, INC. (0.11%)
TEXAS ALTERNATIVE GRASSER, INC.(0.22%)
ROADWAY SPECIALTIES, INC.(3.10%)
RELMCO, INC. (5.29%)
COWBELL TRAFFIC SERVICES, INC. (0.37%)
Contract # 07123214
Totals 6078391.95 0.00 6134359.32 99.9

CountyCOLORADO
Highway IH 10
From COLORADO RIVER
To AUSTIN COUNTY LINE
CSJ 0271-01-076
Proj ID NH 2014(734)
Work Type ACP OVERLAY
 
14.447 8740907.81 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0271-01-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143012
Totals 8740907.81 0.00 0.00 0.0

page 1 | page 2 | page 3