Monthly State Let Construction Report For Yoakum District As Of May 15, 2013 Page 3 Of 4

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyAUSTIN
Highway CR
From AT DRAW CR 5200
To (ZETTEL RD) STR # AA03-00-001
CSJ 0913-20-079
Proj ID BR 2008(612)
Work Type REPLACE BRIDGE
 
0.071 196643.67 4884.50 193969.04 100.0
Work Order 10-12-12
Work Began 11-12-12
Work Completed 04-26-13
Time Computed 10-28-12
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 93
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-079
HEMPHILL PILE DRIVING CO., A CORP. (9.17%)
ODUM SERVICES, L.P.(6.87%)
HOUSTON SAWING & DRILLING(0.56%)
KOSSMAN CONTRACTING CO., INC.(0.60%)
Contract # 09123006
Totals 196643.67 4884.50 193969.04 100.0

CountyAUSTIN
Highway CR
From AT WEST FORK MILL CREEK CR 5178
To (MAREK ROAD) AA02-37-002
CSJ 0913-20-082
Proj ID BR 2010(405)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.075 225407.70 0.00 196508.76 96.0
Work Order 01-18-12
Work Began 05-29-12
Work Completed  
Time Computed 09-03-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 156
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-082
LONE STAR TRAFFIC SERVICE, INC.(0.88%)
HEMPHILL PILE DRIVING CO., A CORP. (7.15%)
CWA CONSTRUCTION, INC. (2.77%)
CEN TEX HYDROSEED, INC.(0.48%)
Contract # 12113003
Totals 225407.70 0.00 196508.76 96.0

CountyAUSTIN
Highway CS
From VARIOUS SCHOOL LOCATIONS
To IN CITY OF SEALY
CSJ 0913-20-083
Proj ID STP 1102(301)SRS
Work Type CONSTRUCT SIDEWALKS, CROSSWALKS
 
1.338 564758.53 6359.78 544739.45 96.4
Work Order 05-16-12
Work Began 09-28-12
Work Completed  
Time Computed 09-13-12
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 88
Contractor(s)
TRIPLE B SERVICES, L.L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-083
STRIPES & STOPS COMPANY, INC.(0.54%)
CHAPA"S CONSTRUCTION ( 32.49%)
SILVA CONTRACTING COMPANY, INC.(5.38%)
RICE ENVIRONMENTAL SERVICES(5.12%)
AMERICAN DRILLING & SAWING (0.38%)
CURB PLANET INC. (0.22%)
JASSO"S SAWING & SEALING (1.09%)
Contract # 04123029
Totals 564758.53 6359.78 544739.45 96.4

CountyMATAGORDA
Highway CS
From SIDEWALKS CONNECTING ELEM. SCHOOLS
To IN PALACIOS
CSJ 0913-21-044
Proj ID STP 1102(321)SRS
Work Type CONSTRUCT SIDEWALKS
 
1.736 363182.49 0.00 293135.89 88.1
Work Order 09-14-11
Work Began 01-20-12
Work Completed  
Time Computed 01-11-12
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 175
Percent Time Used 144
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-044
LONE STAR TRAFFIC SERVICE, INC.(1.65%)
D & P COASTAL MARINE CONSTRUCTION(1.26%)
BATTERSON,LLP(3.09%)
Contract # 08113252
Totals 363182.49 0.00 293135.89 88.1

CountyGONZALES
Highway CR
From AT LIVE OAK CREEK
To (CR 354) AA03-54-001
CSJ 0913-22-034
Proj ID BR 2010(525)
Work Type STRUCTRUAL, GR, SURFACING
 
0.066 244980.00 0.00 224289.00 96.1
Work Order 06-21-12
Work Began 08-20-12
Work Completed  
Time Computed 08-20-12
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 144
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-034
W. W. FOUNDATION DRILLING, LTD.(5.50%)
C. W. & A.,INC (1.42%)
Contract # 05123021
Totals 244980.00 0.00 224289.00 96.1

CountyGONZALES
Highway CR
From AT FIVE MILE CREEK CR 298
To (CR 298) STR # AA02-98-002
CSJ 0913-22-038
Proj ID BR 2011(597)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.139 426647.41 51024.54 172423.81 40.4
Work Order 02-05-13
Work Began 03-12-13
Work Completed  
Time Computed 03-12-13
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 36
Contractor(s)
AARON, DAVID CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-038
HEMPHILL PILE DRIVING CO., A CORP. (8.10%)
ROADWAY SPECIALTIES, INC.(4.97%)
O & S TRAFFIC SUPPLIES (0.45%)
Contract # 12123016
Totals 426647.41 51024.54 172423.81 40.4

CountyGONZALES
Highway PW
From PARKING LOTS AND RV PULLOUTS
To WITHIN PALMETTO STATE PARK
CSJ 0913-22-045
Proj ID C 913-22-45
Work Type WIDEN AND OVERLAY RV PULLOUTS
 
0.001 330812.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 07-09-13
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133016
Totals 330812.00 0.00 0.00 0.0

CountyVICTORIA
Highway CR
From AT DRAW CR 39
To (NURSERY RD) #AA0146002
CSJ 0913-27-051
Proj ID BR 2010(179)
Work Type REP. STRUCTURE, BASE, GRADING
 
0.061 264835.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-08-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133228
Totals 264835.00 0.00 0.00 0.0

CountyVICTORIA
Highway CR
From ON CR 139 (ARNOLD ROAD)
To AT DRAW STR # AA01-20-002
CSJ 0913-27-052
Proj ID BR 2011(294)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.064 348225.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-22-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133027
Totals 348225.00 0.00 0.00 0.0

CountyLAVACA
Highway CR
From AT SANDY CREEK
To (CR 14A) STR # AA05-63-001
CSJ 0913-29-032
Proj ID BR 2007(371)
Work Type STRUCTURES, BASE, SURFACING
 
0.197 674856.10 110568.14 614987.75 91.1
Work Order 06-28-12
Work Began 08-25-12
Work Completed  
Time Computed 08-27-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 85
Percent Time Used 80
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-032
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.80%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.76%)
HOUSTON SAWING & DRILLING(0.21%)
LONE STAR TRAFFIC SERVICE, INC.(0.57%)
SHINN & GREGORY, INC.(7.16%)
EE CONSTRUCTION, LLC ( 13.75%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 14.60%)
Contract # 05123224
Totals 674856.10 110568.14 614987.75 91.1

CountyLAVACA
Highway CR
From AT WILLOW CREEK CR 444
To (CR 122) STR # AA04-44-002
CSJ 0913-29-041
Proj ID BR 2011(164)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 242125.14 24436.53 197736.22 81.6
Work Order 10-18-12
Work Began 12-12-12
Work Completed  
Time Computed 12-12-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 85
Contractor(s)
BPI ENVIRONMENTAL SERVICES INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-041
HIGHWAY TECHNOLOGIES, INC. (0.80%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.00%)
LARGE & SONS_FOUNDATION DRILLING,INC.(9.47%)
Contract # 09123032
Totals 242125.14 24436.53 197736.22 81.6

CountyDEWITT
Highway FM 952
From AT THOMAS CREEK
To STR # 0941-02-002
CSJ 0941-02-014
Proj ID BR 2013(702)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.197 739543.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0941-02-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133011
Totals 739543.00 0.00 0.00 0.0

CountyLAVACA
Highway FM 532
From MAIN STREET
To DEPOT STREET IN MOULTON
CSJ 1007-03-019
Proj ID STP 2013(350)
Work Type LANDSCAPE PROJECT
 
0.001 79102.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1007-03-019
HIGHWAY BARRICADES AND SERVICES, LLC (2.71%)
Contract # 01133225
Totals 79102.00 0.00 0.00 0.0

CountyAUSTIN
Highway FM 949
From 0.4 MI. NORTH OF FM 1094
To SH 36
CSJ 1106-02-020
Proj ID STP 2013(595)HES
Work Type WIDEN ROADWAY
 
8.259 3120993.47 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1106-02-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133204
Totals 3120993.47 0.00 0.00 0.0

CountyWHARTON
Highway FM 1161
From FM 102
To SH 60
CSJ 1303-01-017
Proj ID STP 2013(486)HES
Work Type WIDEN ROADWAY
 
10.413 2257894.57 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1303-01-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133033
Totals 2257894.57 0.00 0.00 0.0

CountyWHARTON
Highway FM 1162
From 0.1 MI. EAST OF US 59
To 0.07 MI. SOUTH OF CR 422
CSJ 1304-01-018
Proj ID STP 2013(245)HES
Work Type WIDEN ROADWAY
 
9.350 1812780.35 415204.23 565975.23 31.2
Work Order 01-18-13
Work Began 02-18-13
Work Completed  
Time Computed 02-03-13
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 44
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1304-01-018
MURRAY CONSTRUCTION(1.36%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.06%)
INTERSTATE BARRICADES & MARKINGS, INC. (4.17%)
STAFF CONCRETE (5.87%)
Contract # 12123031
Totals 1812780.35 415204.23 565975.23 31.2

CountyCALHOUN
Highway FM 1289
From SH 238
To 4.2 MI NORTH OF SH 185
CSJ 1438-01-022
Proj ID STP 2012(378)
Work Type BASE, GR., SURFACING
 
6.879 3292866.80 3303.63 2909788.96 88.5
Work Order 06-01-12
Work Began 06-11-12
Work Completed  
Time Computed 06-11-12
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 156
Percent Time Used 104
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1438-01-022
ENVIRONMENTAL SAFETY SERVICES, INC.(0.79%)
MURRAY CONSTRUCTION(0.22%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.31%)
RAMI MATERIALS TRANSPORT, LLC(1.51%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (1.51%)
Contract # 03123003
Totals 3292866.80 3303.63 2909788.96 88.5

CountyCALHOUN
Highway FM 1289
From 4.2 MI. NORTH OF SH 185
To 0.42 MI. NORTH OF SH 185
CSJ 1438-01-023
Proj ID STP 2012(650)HES
Work Type SET FIXED OBJECTS & CONST. SHLDS.
 
3.241 1648606.49 245453.57 245453.57 14.8
Work Order 09-13-12
Work Began 04-16-13
Work Completed  
Time Computed 11-12-12
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 8
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1438-01-023
D&S TEXAS ICON CONSTRUCTION, LLC (0.61%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.38%)
Contract # 08123007
Totals 1648606.49 245453.57 245453.57 14.8

CountyCALHOUN
Highway FM 1289
From AT MONKEY SLOUGH
To STR # 1438-01-003
CSJ 1438-01-024
Proj ID BR 2012(528)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.109 942515.30 28475.07 28475.07 3.0
Work Order 06-18-12
Work Began 08-25-12
Work Completed  
Time Computed 08-17-12
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1438-01-024
HOUSTON SAWING & DRILLING(0.00%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.42%)
KL DURHAM CONSTRUCTION, LLC(0.00%)
ODUM SERVICES, L.P.(3.16%)
HEMPHILL PILE DRIVING CO., A CORP. (0.00%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.28%)
Contract # 05123010
Totals 942515.30 28475.07 28475.07 3.0

CountyMATAGORDA
Highway FM 1728
From FM 1301
To SH 35
CSJ 1686-01-013
Proj ID STP 2011(780)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
9.516 376154.50 0.00 354579.74 94.2
Work Order 02-15-11
Work Began 04-05-11
Work Completed  
Time Computed 04-05-11
Contract Working Days 105
Addl Days Granted 12
Working Days Charged 117
Percent Time Used 100
Contractor(s)
STONERIDGE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1686-01-013
HIGHWAY TECHNOLOGIES, INC. (1.73%)
Contract # 01113218
Totals 376154.50 0.00 354579.74 94.2

page 1 | page 2 | page 3 | page 4