Monthly State Let Construction Report For Yoakum District As Of Dec 10, 2014 Page 3 Of 4

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWHARTON
Highway CR
From AT MUD CREEK CR 423
To (CR 409) STR # AA04-23-001
CSJ 0913-09-050
Proj ID BR 1102(036)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 348651.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143228
Totals 348651.60 0.00 0.00 0.0

CountyWHARTON
Highway CR
From AT WILLOW CREEK CR 411
To (CR 424) STR # AA04-11-002
CSJ 0913-09-051
Proj ID BR 1102(038)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 448631.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143220
Totals 448631.00 0.00 0.00 0.0

CountyWHARTON
Highway CR
From AT BAUGHMAN SLOUGH CR 231
To (WILKE RD) STR # AA02-66-001
CSJ 0913-09-057
Proj ID BR 2012(410)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.093 465982.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143028
Totals 465982.00 0.00 0.00 0.0

CountyDEWITT
Highway CR
From AT CLEAR CREEK CR 162
To (JACKSON ROAD) AA03-21-001
CSJ 0913-17-035
Proj ID BR 1102(576)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.067 334220.00 2500.00 332826.00 100.0
Work Order 11-14-13
Work Began 02-17-14
Work Completed 10-22-14
Time Computed 01-13-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 98
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-035
HEMPHILL PILE DRIVING CO., A CORP. (2.99%)
ODUM SERVICES, L.P.(3.48%)
CEN TEX HYDROSEED, INC.(0.49%)
JUST GROOVING, LTD.(0.43%)
Contract # 08133023
Totals 334220.00 2500.00 332826.00 100.0

CountyDEWITT
Highway CR
From AT DRAW CR 199
To (OLD GONZALES RD) # AA01-99-003
CSJ 0913-17-036
Proj ID BR 1102(585)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 202141.00 0.00 0.00 0.0
Work Order 08-07-14
Work Began 00-00-00
Work Completed  
Time Computed 10-06-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-036
C. W. & A.,INC ( 10.06%)
CEN TEX HYDROSEED, INC.(1.13%)
Contract # 06143015
Totals 202141.00 0.00 0.00 0.0

CountyDEWITT
Highway CR
From AT DRAW
To (LINCKE RD) STR # AA03-23-001
CSJ 0913-17-037
Proj ID BR 1102(586)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 224026.60 62602.00 87970.75 39.2
Work Order 07-18-14
Work Began 10-28-14
Work Completed  
Time Computed 09-16-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 18
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-037
CEN TEX HYDROSEED, INC.(0.67%)
HEMPHILL PILE DRIVING CO., A CORP. (3.85%)
Contract # 06143213
Totals 224026.60 62602.00 87970.75 39.2

CountyJACKSON
Highway CR
From AT STEM BRANCH CR 284
To (CR 284) AA01-10-001
CSJ 0913-18-023
Proj ID BR 2011(304)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.142 696017.65 83342.90 460789.88 66.2
Work Order 03-25-14
Work Began 06-03-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 67
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-023
LONESTAR TRAFFIC SAFETY, LLC (0.63%)
JUST GROOVING, LTD.(0.30%)
SHINN & GREGORY, INC.(7.77%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.97%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 21.26%)
Contract # 01143021
Totals 696017.65 83342.90 460789.88 66.2

CountyJACKSON
Highway CR
From AT LAVACA RIVER RELIEF CR 174
To (CR 127) STR # AA01-74-001
CSJ 0913-18-027
Proj ID BR 1102(529)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.224 1084856.00 118314.00 548107.26 50.5
Work Order 06-16-14
Work Began 08-18-14
Work Completed  
Time Computed 08-18-14
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 25
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-027
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(4.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.70%)
Contract # 05143017
Totals 1084856.00 118314.00 548107.26 50.5

CountyCALHOUN
Highway CR
From AT SIXMILE CREEK
To (ROYAL RD) STR # AA01-97-001
CSJ 0913-19-026
Proj ID BR 2012(404)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 219241.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143210
Totals 219241.82 0.00 0.00 0.0

CountyCALHOUN
Highway CR
From AT LITTLE CHOCOLATE BAYOU
To WESTERLUND GRADE RD STR#AA02-06-002
CSJ 0913-19-027
Proj ID BR 2012(405)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.058 318903.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LESTER CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143018
Totals 318903.60 0.00 0.00 0.0

CountyAUSTIN
Highway CR
From AT DRAW
To (NELIUS RD) STR # AA03-26-001
CSJ 0913-20-084
Proj ID BR 1102(474)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 525692.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-084
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143206
Totals 525692.63 0.00 0.00 0.0

CountyMATAGORDA
Highway CR
From AT CANEY CREEK CR 194
To (HAWKINS RD) STR # AA01-94-001
CSJ 0913-21-042
Proj ID BR 2014(299)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.171 1323586.20 267366.90 468061.90 35.3
Work Order 04-15-14
Work Began 10-21-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 17
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-042
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(2.74%)
FUQUAY, INC. (0.46%)
JMHP, INC. (1.62%)
JUST GROOVING, LTD.(0.19%)
LONESTAR TRAFFIC SAFETY, LLC (0.17%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 11.59%)
Contract # 02143019
Totals 1323586.20 267366.90 468061.90 35.3

CountyGONZALES
Highway CR
From CR 363 AT GELHORN CREEK
To STR # AA03-63-001
CSJ 0913-22-035
Proj ID BR 2011(495)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.055 236824.41 59182.50 204559.64 86.3
Work Order 05-09-14
Work Began 09-15-14
Work Completed  
Time Computed 07-08-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 60
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-035
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 16.44%)
DUSTIN ALLEN, INC. (5.68%)
FUQUAY, INC. (2.11%)
JUST GROOVING, LTD.(0.35%)
O & S TRAFFIC SUPPLIES (0.86%)
SHINN & GREGORY, INC.(7.83%)
Contract # 04143229
Totals 236824.41 59182.50 204559.64 86.3

CountyGONZALES
Highway CR
From AT BRUSHY CREEK CR 118
To (CR 118) STR # AA01-18-001
CSJ 0913-22-036
Proj ID BR 2011(596)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 247853.06 0.00 233507.94 94.2
Work Order 06-02-14
Work Began 06-18-14
Work Completed  
Time Computed 06-18-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 96
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-036
SHINN & GREGORY, INC.(6.81%)
FUQUAY, INC. (4.06%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.34%)
Contract # 04143026
Totals 247853.06 0.00 233507.94 94.2

CountyGONZALES
Highway CR
From AT FULCHUR CREEK
To CR 296 STR # AA02-96-001
CSJ 0913-22-044
Proj ID BR 2013(440)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 323837.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143215
Totals 323837.00 0.00 0.00 0.0

CountyCOLORADO
Highway CR
From AT DRAW CR 153
To DIETRICH LANE STR # AA-01-53-003
CSJ 0913-26-059
Proj ID BR 2012(732)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.062 249900.02 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-26-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143004
Totals 249900.02 0.00 0.00 0.0

CountyVICTORIA
Highway CR
From AT DRY CREEK CR 114
To (WEBER ROAD) STR # AA01-14-001
CSJ 0913-27-054
Proj ID BR 2011(496)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.097 338315.31 40928.18 234038.46 69.1
Work Order 06-20-14
Work Began 08-21-14
Work Completed  
Time Computed 08-19-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 65
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-054
RICE ENVIRONMENTAL SERVICES(5.16%)
SPECIALTY DRILLING, LTD. ( 14.84%)
LONE STAR TRAFFIC SERVICE, INC.(0.63%)
HOLES INCORPORATED (0.73%)
MESA ROD BUSTERS, INC. (0.48%)
JUST GROOVING, LTD.(315.71%)
Contract # 05143034
Totals 338315.31 40928.18 234038.46 69.1

CountyFAYETTE
Highway CR
From AT DRAW CR 282
To (DUBINA-WEIMAR RD) AA02-84-001
CSJ 0913-28-056
Proj ID BR 2008(549)
Work Type REPLACE BRIDGE
 
0.077 414242.66 27638.77 32114.67 7.7
Work Order 08-27-14
Work Began 00-00-00
Work Completed  
Time Computed 09-12-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-28-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143020
Totals 414242.66 27638.77 32114.67 7.7

CountyFAYETTE
Highway CR
From AT OWL CREEK CR 190
To (OWL CREEK RD) STR # AA03-79-002
CSJ 0913-28-057
Proj ID BR 2008(550)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 404024.62 60930.00 60930.00 15.0
Work Order 08-27-14
Work Began 10-28-14
Work Completed  
Time Computed 10-26-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 21
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0913-28-057
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.21%)
ODUM SERVICES, L.P.(3.16%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.81%)
CEN TEX HYDROSEED, INC.(1.19%)
MESA ROD BUSTERS, INC. (1.10%)
Contract # 07143220
Totals 404024.62 60930.00 60930.00 15.0

CountyLAVACA
Highway CR
From AT LAVACA RIVER CR 12
To (CR 12) STR # AA03-47-001
CSJ 0913-29-044
Proj ID BR 2014(595)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.094 588575.12 34544.80 43824.80 7.4
Work Order 06-20-14
Work Began 11-11-14
Work Completed  
Time Computed 08-19-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 12
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-044
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 10.01%)
ENVIRONMENTAL SAFETY SERVICES, INC.(6.53%)
HEMPHILL PILE DRIVING CO., A CORP. (8.93%)
JUST GROOVING, LTD.(0.21%)
LONESTAR TRAFFIC SAFETY, LLC (0.35%)
Contract # 04143013
Totals 588575.12 34544.80 43824.80 7.4

page 1 | page 2 | page 3 | page 4