Monthly State Let Construction Report For Yoakum District As Of Jan 13, 2015 Page 3 Of 4

Last Update: Tuesday, January 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFAYETTE
Highway FM 153
From BASTROP COUNTY LINE
To US 77
CSJ 0807-03-032
Proj ID STP 2015(429)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
11.432 488019.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0807-03-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143011
Totals 488019.50 0.00 0.00 0.0

CountyVICTORIA
Highway FM 447
From US 87
To FM 236
CSJ 0842-02-021
Proj ID STP 1302(043)
Work Type REPAIR & WIDEN ROADWAY
 
5.401 2015294.58 251007.52 1588582.78 78.8
Work Order 12-03-13
Work Began 01-16-14
Work Completed  
Time Computed 01-16-14
Contract Working Days 165
Addl Days Granted 4
Working Days Charged 147
Percent Time Used 86
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0842-02-021
ROADSAFE TRAFFIC SYSTEMS, INC. (5.83%)
ROADWAY SPECIALTIES, INC.(6.05%)
LHOIST NORTH AMERICA (0.00%)
INGRAM READY MIX (0.00%)
ALAMO CONCRETE (0.00%)
Contract # 09133234
Totals 2015294.58 251007.52 1588582.78 78.8

CountyDEWITT
Highway VA
From VARIOUS LOCATIONS
To IN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ 0913-00-088
Proj ID STP 2012(527)
Work Type CONSTRUCT CURB RAMPS
 
0.100 475081.00 2139.00 577322.17 99.9
Work Order 06-18-12
Work Began 04-05-13
Work Completed  
Time Computed 10-16-12
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 86
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.79%)
SPEEDY PAVING(2.40%)
Contract # 05123217
Totals 475081.00 2139.00 577322.17 99.9

CountyWHARTON
Highway CR
From AT MUD CREEK CR 423
To (CR 409) STR # AA04-23-001
CSJ 0913-09-050
Proj ID BR 1102(036)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 348651.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143228
Totals 348651.60 0.00 0.00 0.0

CountyWHARTON
Highway CR
From AT WILLOW CREEK CR 411
To (CR 424) STR # AA04-11-002
CSJ 0913-09-051
Proj ID BR 1102(038)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 448631.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143220
Totals 448631.00 0.00 0.00 0.0

CountyWHARTON
Highway CR
From AT BAUGHMAN SLOUGH CR 231
To (WILKE RD) STR # AA02-66-001
CSJ 0913-09-057
Proj ID BR 2012(410)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.093 465982.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143028
Totals 465982.00 0.00 0.00 0.0

CountyWHARTON
Highway CR
From AT CANEY CREEK CR 299
To (CR 263) STR. # AA02-99-001
CSJ 0913-09-061
Proj ID BR 1302(064)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.081 770327.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153224
Totals 770327.00 0.00 0.00 0.0

CountyDEWITT
Highway CR
From AT CLEAR CREEK CR 162
To (JACKSON ROAD) AA03-21-001
CSJ 0913-17-035
Proj ID BR 1102(576)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.067 334220.00 0.00 332826.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-13
Work Began 02-17-14
Work Completed 10-22-14
Time Computed 01-13-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 98
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-035
HEMPHILL PILE DRIVING CO., A CORP. (2.99%)
ODUM SERVICES, L.P.(3.48%)
CEN TEX HYDROSEED, INC.(0.49%)
JUST GROOVING, LTD.(0.43%)
Contract # 08133023
Totals 334220.00 0.00 332826.00 100.0

CountyDEWITT
Highway CR
From AT DRAW CR 199
To (OLD GONZALES RD) # AA01-99-003
CSJ 0913-17-036
Proj ID BR 1102(585)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 202141.00 107617.00 107617.00 53.2
Work Order 08-07-14
Work Began 12-03-14
Work Completed  
Time Computed 10-06-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 24
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-036
C. W. & A.,INC ( 10.06%)
CEN TEX HYDROSEED, INC.(1.13%)
Contract # 06143015
Totals 202141.00 107617.00 107617.00 53.2

CountyDEWITT
Highway CR
From AT DRAW
To (LINCKE RD) STR # AA03-23-001
CSJ 0913-17-037
Proj ID BR 1102(586)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 224026.60 33243.25 121214.00 54.1
Work Order 07-18-14
Work Began 10-28-14
Work Completed  
Time Computed 09-16-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 20
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-037
CEN TEX HYDROSEED, INC.(0.67%)
HEMPHILL PILE DRIVING CO., A CORP. (3.85%)
Contract # 06143213
Totals 224026.60 33243.25 121214.00 54.1

CountyJACKSON
Highway CR
From AT STEM BRANCH CR 284
To (CR 284) AA01-10-001
CSJ 0913-18-023
Proj ID BR 2011(304)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.142 696017.65 31918.38 492708.26 70.7
Work Order 03-25-14
Work Began 06-03-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 78
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-023
LONESTAR TRAFFIC SAFETY, LLC (0.63%)
JUST GROOVING, LTD.(0.30%)
SHINN & GREGORY, INC.(7.77%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.97%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 21.26%)
Contract # 01143021
Totals 696017.65 31918.38 492708.26 70.7

CountyJACKSON
Highway CR
From AT LAVACA RIVER RELIEF CR 174
To (CR 127) STR # AA01-74-001
CSJ 0913-18-027
Proj ID BR 1102(529)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.224 1084856.00 60527.80 608635.06 56.1
Work Order 06-16-14
Work Began 08-18-14
Work Completed  
Time Computed 08-18-14
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 32
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-027
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(4.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.70%)
Contract # 05143017
Totals 1084856.00 60527.80 608635.06 56.1

CountyCALHOUN
Highway CR
From AT SIXMILE CREEK
To (ROYAL RD) STR # AA01-97-001
CSJ 0913-19-026
Proj ID BR 2012(404)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 219241.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-026
HIGHWAY BARRICADES AND SERVICES, LLC (1.14%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 21.94%)
Contract # 09143210
Totals 219241.82 0.00 0.00 0.0

CountyCALHOUN
Highway CR
From AT LITTLE CHOCOLATE BAYOU
To WESTERLUND GRADE RD STR#AA02-06-002
CSJ 0913-19-027
Proj ID BR 2012(405)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.058 318903.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LESTER CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-027
ENVIRONMENTAL SAFETY SERVICES, INC.(1.05%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 21.77%)
GONZALEZ CONTRACTING ( 13.54%)
Contract # 10143018
Totals 318903.60 0.00 0.00 0.0

CountyAUSTIN
Highway CR
From AT DRAW
To (NELIUS RD) STR # AA03-26-001
CSJ 0913-20-084
Proj ID BR 1102(474)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 525692.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-02-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-084
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143206
Totals 525692.63 0.00 0.00 0.0

CountyMATAGORDA
Highway CR
From AT CANEY CREEK CR 194
To (HAWKINS RD) STR # AA01-94-001
CSJ 0913-21-042
Proj ID BR 2014(299)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.171 1323586.20 5049.09 473110.99 35.7
Work Order 04-15-14
Work Began 10-21-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 32
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-042
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(2.74%)
FUQUAY, INC. (0.46%)
JMHP, INC. (1.62%)
JUST GROOVING, LTD.(0.19%)
LONESTAR TRAFFIC SAFETY, LLC (0.17%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 11.59%)
Contract # 02143019
Totals 1323586.20 5049.09 473110.99 35.7

CountyGONZALES
Highway CR
From CR 363 AT GELHORN CREEK
To STR # AA03-63-001
CSJ 0913-22-035
Proj ID BR 2011(495)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.055 236824.41 23256.88 227816.52 96.1
Work Order 05-09-14
Work Began 09-15-14
Work Completed  
Time Computed 07-08-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 83
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-035
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 16.44%)
DUSTIN ALLEN, INC. (5.68%)
FUQUAY, INC. (2.11%)
JUST GROOVING, LTD.(0.35%)
O & S TRAFFIC SUPPLIES (0.86%)
SHINN & GREGORY, INC.(7.83%)
Contract # 04143229
Totals 236824.41 23256.88 227816.52 96.1

CountyGONZALES
Highway CR
From AT BRUSHY CREEK CR 118
To (CR 118) STR # AA01-18-001
CSJ 0913-22-036
Proj ID BR 2011(596)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 247853.06 0.00 233507.94 94.2
Work Order 06-02-14
Work Began 06-18-14
Work Completed  
Time Computed 06-18-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 96
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-036
SHINN & GREGORY, INC.(6.81%)
FUQUAY, INC. (4.06%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.34%)
Contract # 04143026
Totals 247853.06 0.00 233507.94 94.2

CountyGONZALES
Highway CR
From AT ROCKY CREEK CR 377
To (CR 360A) STR # AA05-45-001
CSJ 0913-22-043
Proj ID BR 2015(539)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 276692.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153206
Totals 276692.75 0.00 0.00 0.0

CountyGONZALES
Highway CR
From AT FULCHUR CREEK
To CR 296 STR # AA02-96-001
CSJ 0913-22-044
Proj ID BR 2013(440)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 323837.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143215
Totals 323837.00 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4