Monthly State Let Construction Report For Yoakum District As Of Jul 11, 2014 Page 3 Of 3

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGONZALES
Highway CR
From AT BRUSHY CREEK CR 118
To (CR 118) STR # AA01-18-001
CSJ 0913-22-036
Proj ID BR 2011(596)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 247853.06 53680.63 53680.63 21.6
Work Order 06-02-14
Work Began 06-18-14
Work Completed  
Time Computed 06-18-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 6
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-036
SHINN & GREGORY, INC.(6.81%)
FUQUAY, INC. (4.06%)
Contract # 04143026
Totals 247853.06 53680.63 53680.63 21.6

CountyGONZALES
Highway CR
From AT SANDY FORK CREEK CR 437
To (CR 437) STR # AA04-37-001
CSJ 0913-22-042
Proj ID BR 2012(230)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.074 232209.97 46853.70 225749.67 97.2
Work Order 01-17-14
Work Began 03-10-14
Work Completed  
Time Computed 03-10-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 95
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-042
LONE STAR TRAFFIC SERVICE, INC.(0.77%)
SHINN & GREGORY, INC.(8.52%)
Contract # 12133213
Totals 232209.97 46853.70 225749.67 97.2

CountyVICTORIA
Highway CR
From AT DRY CREEK CR 114
To (WEBER ROAD) STR # AA01-14-001
CSJ 0913-27-054
Proj ID BR 2011(496)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.097 338315.31 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143034
Totals 338315.31 0.00 0.00 0.0

CountyFAYETTE
Highway CR
From AT DRAW CR 282
To (DUBINA-WEIMAR RD) AA02-84-001
CSJ 0913-28-056
Proj ID BR 2008(549)
Work Type REPLACE BRIDGE
 
0.077 414242.66 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-28-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143020
Totals 414242.66 0.00 0.00 0.0

CountyFAYETTE
Highway CR
From AT OWL CREEK CR 190
To (OWL CREEK RD) STR # AA03-79-002
CSJ 0913-28-057
Proj ID BR 2008(550)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 404024.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0913-28-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143220
Totals 404024.62 0.00 0.00 0.0

CountyLAVACA
Highway CR
From AT LAVACA RIVER CR 12
To (CR 12) STR # AA03-47-001
CSJ 0913-29-044
Proj ID BR 2014(595)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.094 588575.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143013
Totals 588575.12 0.00 0.00 0.0

CountyLAVACA
Highway CR
From AT NAVIDAD RIVER CR 124
To (CR 214) STR # AA04-95-001
CSJ 0913-29-046
Proj ID BR 2012(430)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.116 639216.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143024
Totals 639216.42 0.00 0.00 0.0

CountyDEWITT
Highway FM 952
From AT THOMAS CREEK
To STR # 0941-02-002
CSJ 0941-02-014
Proj ID BR 2013(702)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.197 739543.00 1327.56 741071.16 99.9
Work Order 07-23-13
Work Began 09-06-13
Work Completed  
Time Computed 09-06-13
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 100
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0941-02-014
AVAILABLE CONSTRUCTION AND TRANSPORT SERVICES, INC.( 25.12%)
O & S TRAFFIC SUPPLIES (0.61%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.63%)
FLASHER EQUIPMENT COMPANY(2.41%)
FUQUAY, INC. (0.85%)
JUST GROOVING, LTD.(0.23%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.27%)
J R RAMON, INC.(2.24%)
SHINN & GREGORY, INC.(4.67%)
PIPE WHOLESALERS OF TEXAS, INC.(0.74%)
Contract # 05133011
Totals 739543.00 1327.56 741071.16 99.9

CountyGONZALES
Highway FM 532
From US 90A
To LAVACA COUNTY LINE
CSJ 1007-02-017
Proj ID STP 2013(919)
Work Type ROADWAY WIDENING
 
13.775 8097588.87 32900.25 1585684.48 19.5
Work Order 10-10-13
Work Began 12-03-13
Work Completed  
Time Computed 12-03-13
Contract Working Days 285
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 34
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1007-02-017
FOX QUALITY CONCRETE, L.L.C. (3.01%)
M.V. HENKE ENTERPRISES, INC. (0.46%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 12.05%)
C-3 ENVIRONMENTAL SPECIALTIES, LP(1.07%)
LAND STABILIZER, LTD (7.21%)
ROADWAY SPECIALTIES, INC.(0.21%)
FLASHER EQUIPMENT COMPANY(1.71%)
ZAMCO TRUCKING, LLC(1.29%)
Contract # 07133251
Totals 8097588.87 32900.25 1585684.48 19.5

CountyAUSTIN
Highway FM 949
From 0.4 MI. NORTH OF FM 1094
To SH 36
CSJ 1106-02-020
Proj ID STP 2013(595)HES
Work Type WIDEN ROADWAY
 
8.259 3120993.47 206268.50 2999096.93 96.0
Work Order 07-23-13
Work Began 07-31-13
Work Completed  
Time Computed 08-08-13
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 95
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1106-02-020
MURRAY CONSTRUCTION(1.25%)
CEN TEX HYDROSEED, INC.(2.12%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.98%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
JEFFERY BAILEY TRUCKING, INC.(0.00%)
Contract # 04133204
Totals 3120993.47 206268.50 2999096.93 96.0

CountyWHARTON
Highway FM 1161
From FM 102
To SH 60
CSJ 1303-01-017
Proj ID STP 2013(486)HES
Work Type WIDEN ROADWAY
 
10.413 2257894.57 32743.70 2101315.36 94.2
Work Order 05-23-13
Work Began 06-27-13
Work Completed  
Time Computed 06-08-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 155
Percent Time Used 129
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1303-01-017
FLASHER EQUIPMENT COMPANY(2.56%)
KOSSMAN CONTRACTING CO., INC.(2.33%)
MURRAY CONSTRUCTION(1.63%)
STAFF CONCRETE (5.76%)
A.J.J.A . TRUCKING, INC. (2.37%)
Contract # 03133033
Totals 2257894.57 32743.70 2101315.36 94.2

CountyWHARTON
Highway FM 1301
From .1 MI E OF ALABAMA RD IN WHARTONCT
To 0.1 MI. EAST OF FM 442
CSJ 1412-03-039
Proj ID STP 2014(418)
Work Type ACP OVERLAY
 
8.785 1948403.88 40029.18 2041700.03 99.9
Work Order 03-13-14
Work Began 04-08-14
Work Completed  
Time Computed 04-08-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 78
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1412-03-039
PRIMATE CONSTRUCTION, INC. (3.17%)
PENHALL COMPANY(0.55%)
BATTERSON,LLP(2.73%)
WEST TEXAS RUMBLE STRIP(0.59%)
Contract # 02143226
Totals 1948403.88 40029.18 2041700.03 99.9

CountyCALHOUN
Highway FM 1289
From AT MONKEY SLOUGH
To STR # 1438-01-003
CSJ 1438-01-024
Proj ID BR 2012(528)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.109 942515.30 70106.79 912051.37 99.6
Work Order 06-18-12
Work Began 08-25-12
Work Completed  
Time Computed 08-17-12
Contract Working Days 90
Addl Days Granted 2
Working Days Charged 137
Percent Time Used 148
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1438-01-024
HOUSTON SAWING & DRILLING(0.16%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.42%)
KL DURHAM CONSTRUCTION, LLC(0.55%)
ODUM SERVICES, L.P.(3.16%)
HEMPHILL PILE DRIVING CO., A CORP. (3.60%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.50%)
Contract # 05123010
Totals 942515.30 70106.79 912051.37 99.6

CountyFAYETTE
Highway FM 615
From AT MIDDLE CREEK
To STR # 1692-01-001
CSJ 1692-01-007
Proj ID BR 2014(932)
Work Type BASE, STURCTURAL, SURFACING
 
0.125 742839.91 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1692-01-007
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143228
Totals 742839.91 0.00 0.00 0.0

CountyVICTORIA
Highway LP 463
From 0.13 MILES SE OF MOCKINGBIRD LANE
To 0.30 MILES NW OF BU 59
CSJ 2350-01-052
Proj ID C 2350-1-52
Work Type CONSTRUCT 4 - LANE OVERPASS
 
2.166 16539199.44 1016785.58 6799664.35 41.1
Work Order 10-17-13
Work Began 11-18-13
Work Completed  
Time Computed 11-18-13
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 46
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-052
N-LINE TRAFFIC MAINTENANCE, L.P. (0.14%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.08%)
D. I. J. CONSTRUCTION, INC.(0.42%)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.38%)
EGGEMEYER LAND CLEARING, LLC (0.03%)
MURRAY CONSTRUCTION(0.20%)
NORTH TEXAS REBAR, LLC (0.14%)
PRIMATE CONSTRUCTION, INC. (0.02%)
ROADWAY SPECIALTIES, INC.(1.02%)
SCOTT DERR PAINTING CO, LLC(0.24%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.76%)
BILL HALL JR. TRUCKING, LTD. (4.02%)
MCL CONTRACTING, LLC (0.12%)
Contract # 06133012
Totals 16539199.44 1016785.58 6799664.35 41.1

page 1 | page 2 | page 3