Monthly State Let Construction Report For Yoakum District As Of Apr 10, 2015 Page 2 Of 4

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFAYETTE
Highway FM 155
From AT WILLIAMS CREEK
To .
CSJ 0211-09-029
Proj ID BR 2014(642)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.397 1540168.40 120066.21 802166.55 52.0
Work Order 07-02-14
Work Began 11-20-14
Work Completed  
Time Computed 10-30-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 27
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0211-09-029
A & R DEMOLITION (1.64%)
JUST GROOVING, LTD.(0.15%)
MESA ROD BUSTERS, INC. (0.55%)
ROADWAY SPECIALTIES, INC.(2.87%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.59%)
SHINN & GREGORY, INC.(9.26%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%)
TRP CONSTRUCTION GROUP, LLC(0.79%)
M.V. HENKE ENTERPRISES, INC. (0.87%)
Contract # 05143235
Totals 1540168.40 120066.21 802166.55 52.0

CountyWHARTON
Highway SH 60
From 0.215 MI. S. OF AUSTIN COUNTY LINE
To US 90A
CSJ 0240-02-030
Proj ID STP 2013(485)
Work Type RESTORE ROADWAY
 
4.819 2921571.83 78804.14 3002755.20 100.0
Work Order 05-29-13
Work Began 09-11-13
Work Completed 03-09-15
Time Computed 07-28-13
Contract Working Days 120
Addl Days Granted 39
Working Days Charged 190
Percent Time Used 119
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0240-02-030
RICE ENVIRONMENTAL SERVICES(1.00%)
D. I. J. CONSTRUCTION, INC.(2.90%)
MURRAY CONSTRUCTION(0.68%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.51%)
A.J.J.A . TRUCKING, INC. (2.83%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
STAFF CONCRETE (4.37%)
MPB, INC.(0.28%)
DEVTEX INC.(0.14%)
R & A HAULING(0.00%)
Contract # 03133234
Totals 2921571.83 78804.14 3002755.20 100.0

CountyWHARTON
Highway SH 60
From FM 442
To MATAGORDA COUNTY LINE
CSJ 0241-01-047
Proj ID STP 2015(628)
Work Type ACP OVERLAY
 
6.168 1235687.82 0.00 0.00 0.0
CountyJACKSON
Highway FM 3131
From SH 111
To FM 1593
CSJ 1756-01-020
Proj ID STP 2015(626)HES
Work Type CENTERLINE TEXTURING
 
25.695 82389.39 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0241-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153227
Totals 1318077.21 0.00 0.00 0.0

CountyWHARTON
Highway SH 71
From AT TRES PALACIOS RIVER IN EL CAMPO
To STR # 0266-06-036
CSJ 0266-06-044
Proj ID BR 2013(593)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.164 1218475.90 0.00 880320.20 75.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-10-13
Work Began 11-13-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 185
Percent Time Used 137
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-06-044
ENVIRONMENTAL ALLIES, L.P. (0.13%)
WILLOW CITY SIGN & RAIL, INC.(1.28%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.21%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
MESA ROD BUSTERS, INC. (0.89%)
YORK & YORK FOUNDATION DRILLING, INC.(7.13%)
JUST GROOVING, LTD.(0.29%)
TEXAS IH CONSTRUCTORS, LLC (5.61%)
Contract # 04133229
Totals 1218475.90 0.00 880320.20 75.0

CountyWHARTON
Highway SH 71
From WCR 405
To MATAGORDA COUNTY LINE
CSJ 0266-06-045
Proj ID STP 2014(740)
Work Type PAVEMENT REPAIR AND SURFACING
 
5.473 2333301.84 0.00 980658.82 42.0
Work Order 06-20-14
Work Began 08-18-14
Work Completed  
Time Computed 08-18-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 58
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-06-045
PENHALL COMPANY(0.29%)
MURRAY CONSTRUCTION(0.25%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.75%)
Contract # 04143236
Totals 2333301.84 0.00 980658.82 42.0

CountyCOLORADO
Highway IH 10
From COLORADO RIVER
To AUSTIN COUNTY LINE
CSJ 0271-01-076
Proj ID NH 2014(734)
Work Type ACP OVERLAY
 
14.447 8740907.81 4481.00 3379013.07 38.6
Work Order 06-30-14
Work Began 08-17-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 30
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0271-01-076
C PAVE, INC. (5.22%)
PENHALL COMPANY(0.27%)
MURRAY CONSTRUCTION(0.19%)
DUSTROL, INC.(3.49%)
BATTERSON,LLP(3.27%)
R & A TRANSPORT, INC.(0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.18%)
Contract # 05143012
Totals 8740907.81 4481.00 3379013.07 38.6

CountyGONZALES
Highway SH 80
From FM 446
To 1.23 MI. NORTH OF FM 1682
CSJ 0287-03-029
Proj ID STP 2014(591)
Work Type ACP OVERLAY
 
10.399 2198746.80 2805.00 2260033.63 100.0
Work Order 05-13-14
Work Began 09-03-14
Work Completed 02-27-15
Time Computed 07-15-14
Contract Working Days 45
Addl Days Granted 4
Working Days Charged 42
Percent Time Used 85
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0287-03-029
BATTERSON,LLP(3.09%)
CHEROKEE SERVICES(0.34%)
WEST TEXAS RUMBLE STRIP(0.24%)
Contract # 04143209
Totals 2198746.80 2805.00 2260033.63 100.0

CountyGONZALES
Highway SH 80
From FM 1682
To CR 167
CSJ 0287-04-033
Proj ID STP 1402(096)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
9.030 203126.50 0.00 197607.00 99.9
Work Order 10-07-14
Work Began 10-22-14
Work Completed  
Time Computed 10-22-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 133
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0287-04-033
RICE ENVIRONMENTAL SERVICES( 29.84%)
ROAD REPAIR, LLC ( 27.38%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.67%)
BEAVER CONTRACTORS, LLC( 27.38%)
Contract # 08143018
Totals 203126.50 0.00 197607.00 99.9

CountyFAYETTE
Highway SH 95
From FLATONIA CITY LIMITS
To LAVACA COUNTY LINE
CSJ 0324-01-024
Proj ID STP 2014(550)
Work Type PAVEMENT REPAIR AND SURFACING
 
3.706 2459856.61 7210.27 2461567.88 100.0
Work Order 05-20-14
Work Began 06-18-14
Work Completed 02-27-15
Time Computed 06-05-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 76
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0324-01-024
COWBELL TRAFFIC SERVICES, INC. (0.56%)
EGGEMEYER LAND CLEARING, LLC (0.58%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.73%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.14%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.46%)
RAMI MATERIALS TRANSPORT, LLC(2.21%)
Contract # 03143210
Totals 2459856.61 7210.27 2461567.88 100.0

CountyLAVACA
Highway SH 111
From DEWITT COUNTY LINE
To US 77
CSJ 0346-06-046
Proj ID STP 2013(594)
Work Type PAVEMENT REPAIR & ACP OVERLAY
 
11.649 2608000.01 12560.00 2751078.79 99.9
Work Order 07-31-13
Work Began 06-19-14
Work Completed  
Time Computed 07-08-13
Contract Working Days 60
Addl Days Granted 16
Working Days Charged 76
Percent Time Used 100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0346-06-046
COWBELL TRAFFIC SERVICES, INC. (1.18%)
FUQUAY, INC. (0.26%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.78%)
M.V. HENKE ENTERPRISES, INC. (0.36%)
MURRAY CONSTRUCTION(0.15%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.19%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (2.63%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.70%)
Contract # 05133035
Totals 2608000.01 12560.00 2751078.79 99.9

CountyLAVACA
Highway SH 111
From US 77
To JACKSON COUNTY LINE
CSJ 0346-06-048
Proj ID STP 1402(043)
Work Type PAVEMENT REPAIR AND RESURFACING
 
10.040 2257868.44 593848.27 720360.50 31.9
Work Order 08-07-14
Work Began 02-25-15
Work Completed  
Time Computed 09-02-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 33
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0346-06-048
PRIMATE CONSTRUCTION, INC. (0.94%)
RED SIXTEEN CONSTRUCTION, INC(0.91%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.55%)
Contract # 06143060
Totals 2257868.44 593848.27 720360.50 31.9

CountyMATAGORDA
Highway FM 1468
From SH 71
To SH 35
CSJ 0346-10-021
Proj ID STP 1402(099)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
10.376 1128804.52 40912.40 439043.28 38.8
Work Order 10-20-14
Work Began 12-09-14
Work Completed  
Time Computed 12-09-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 30
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0346-10-021
BEAVER CONTRACTORS, LLC(5.65%)
RICE ENVIRONMENTAL SERVICES(0.82%)
Contract # 08143039
Totals 1128804.52 40912.40 439043.28 38.8

CountyGONZALES
Highway SH 97
From CO RD 112
To US 183
CSJ 0347-01-028
Proj ID STP 2015(427)
Work Type REHABILITATE ROADWAY
 
12.814 10157843.77 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-18-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0347-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143205
Totals 10157843.77 0.00 0.00 0.0

CountyGONZALES
Highway SH 80
From 0.06 MILES SOUTH OF US 87
To WILSON C/L
CSJ 0348-01-013
Proj ID STP 2015(536)
Work Type RESTORE ROADWAY
 
4.123 2463486.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-18-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0348-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153013
Totals 2463486.16 0.00 0.00 0.0

CountyDEWITT
Highway SH 119
From FM 108
To SH 72
CSJ 0359-03-025
Proj ID STP 1502(051)
Work Type RESTORE ROADWAY
 
3.718 4573832.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0359-03-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153233
Totals 4573832.63 0.00 0.00 0.0

CountyAUSTIN
Highway SH 159
From FM 109
To SH 36
CSJ 0408-02-045
Proj ID STP 2015(428)
Work Type ADD SHOULDERS
 
14.079 11278713.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0408-02-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143204
Totals 11278713.11 0.00 0.00 0.0

CountyLAVACA
Highway US 90A
From @ BRUSHY CREEK
To STR # 0446-01-016
CSJ 0446-01-047
Proj ID BR 2015(245)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.606 3321678.02 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-11-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143213
Totals 3321678.02 0.00 0.00 0.0

CountyCOLORADO
Highway US 90A
From AT EAST SANDY CREEK
To STR # 0446-02-027
CSJ 0446-02-030
Proj ID BR 2014(212)
Work Type REPLACE BRIDGE AND APPROACHES
 
1.060 3488667.34 146572.91 2540109.00 74.4
Work Order 02-06-14
Work Began 03-21-14
Work Completed  
Time Computed 03-21-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 210
Percent Time Used 140
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-02-030
SHINN & GREGORY, INC.(6.49%)
ROADWAY SPECIALTIES, INC.(3.12%)
JUST GROOVING, LTD.(0.13%)
JAMES CONSTRUCTION GROUP, L.L.C. ( 19.79%)
UNITED PAVEMENT & MARKINGS, LLC(0.52%)
LONESTAR TRAFFIC SAFETY, LLC (0.16%)
CD TRUCKING, INC (4.14%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.12%)
REPUBLIC TRAFFIC SAFETY, INC.(0.60%)
Contract # 11133206
Totals 3488667.34 146572.91 2540109.00 74.4

CountyCOLORADO
Highway US 90A
From LAVACA COUNTY LINE
To 2.5 MI. WEST OF SH 71
CSJ 0446-02-035
Proj ID STP 1502(010)
Work Type ACP OVERLAY
 
13.157 3589079.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-02-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153211
Totals 3589079.85 0.00 0.00 0.0

CountyCOLORADO
Highway US 90A
From SH 71
To EAST A STREET IN EAGLE LAKE
CSJ 0446-03-049
Proj ID STP 1502(050)
Work Type CONSTRUCT SUPER 2 LANES
 
7.929 6297396.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 183
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0446-03-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153232
Totals 6297396.25 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4