Monthly State Let Construction Report For Yoakum District As Of Jul 11, 2014 Page 2 Of 3

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGONZALES
Highway SH 80
From FM 446
To 1.23 MI. NORTH OF FM 1682
CSJ 0287-03-029
Proj ID STP 2014(591)
Work Type ACP OVERLAY
 
10.399 2198746.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0287-03-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143209
Totals 2198746.80 0.00 0.00 0.0

CountyFAYETTE
Highway SH 95
From FLATONIA CITY LIMITS
To LAVACA COUNTY LINE
CSJ 0324-01-024
Proj ID STP 2014(550)
Work Type PAVEMENT REPAIR AND SURFACING
 
3.706 2459856.61 475961.37 475961.37 19.3
Work Order 05-20-14
Work Began 06-18-14
Work Completed  
Time Computed 06-05-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 10
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0324-01-024
COWBELL TRAFFIC SERVICES, INC. (0.56%)
EGGEMEYER LAND CLEARING, LLC (0.58%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.73%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.14%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.46%)
RAMI MATERIALS TRANSPORT, LLC(2.21%)
Contract # 03143210
Totals 2459856.61 475961.37 475961.37 19.3

CountyLAVACA
Highway SH 111
From DEWITT COUNTY LINE
To US 77
CSJ 0346-06-046
Proj ID STP 2013(594)
Work Type PAVEMENT REPAIR & ACP OVERLAY
 
11.649 2608000.01 184879.04 184879.04 7.0
Work Order 07-31-13
Work Began 06-19-14
Work Completed  
Time Computed 07-08-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 3
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0346-06-046
COWBELL TRAFFIC SERVICES, INC. (1.18%)
FUQUAY, INC. (0.26%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.78%)
M.V. HENKE ENTERPRISES, INC. (0.36%)
MURRAY CONSTRUCTION(0.15%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.19%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (2.63%)
Contract # 05133035
Totals 2608000.01 184879.04 184879.04 7.0

CountyLAVACA
Highway SH 111
From US 77
To JACKSON COUNTY LINE
CSJ 0346-06-048
Proj ID STP 1402(043)
Work Type PAVEMENT REPAIR AND RESURFACING
 
10.040 2257868.44 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0346-06-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143060
Totals 2257868.44 0.00 0.00 0.0

CountyCOLORADO
Highway US 90A
From AT EAST SANDY CREEK
To STR # 0446-02-027
CSJ 0446-02-030
Proj ID BR 2014(212)
Work Type REPLACE BRIDGE AND APPROACHES
 
1.060 3488667.34 501461.15 1878915.68 53.8
Work Order 02-06-14
Work Began 03-21-14
Work Completed  
Time Computed 03-21-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 40
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-02-030
SHINN & GREGORY, INC.(6.49%)
ROADWAY SPECIALTIES, INC.(3.12%)
JUST GROOVING, LTD.(0.13%)
JAMES CONSTRUCTION GROUP, L.L.C. ( 19.79%)
UNITED PAVEMENT & MARKINGS, LLC(0.80%)
LONESTAR TRAFFIC SAFETY, LLC (0.16%)
CD TRUCKING, INC (4.14%)
Contract # 11133206
Totals 3488667.34 501461.15 1878915.68 53.8

CountyCOLORADO
Highway FM 102
From SENIOR BRIDGE ROAD
To WHARTON COUNTY LINE
CSJ 0709-01-024
Proj ID STP 2013(918)
Work Type PAVEMENT REPAIR & SHOULDER WIDENING
 
5.655 3248432.42 170536.62 473446.44 14.5
Work Order 10-17-13
Work Began 02-19-14
Work Completed  
Time Computed 12-16-13
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 52
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0709-01-024
KOSSMAN CONTRACTING CO., INC.(0.60%)
MURRAY CONSTRUCTION(0.32%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.86%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.16%)
M.V. HENKE ENTERPRISES, INC. (0.43%)
WEST TEXAS RUMBLE STRIP(0.11%)
Contract # 07133048
Totals 3248432.42 170536.62 473446.44 14.5

CountyWHARTON
Highway FM 102
From 0.27 MI. WEST OF FM 960
To 0.53 MI. WEST OF WHARTON CITY LIMIT
CSJ 0709-02-047
Proj ID STP 2013(073)
Work Type ADD SHOULDERS
 
4.109 2875006.16 0.00 2871673.42 99.9
Work Order 11-01-12
Work Began 01-07-13
Work Completed  
Time Computed 12-31-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 120
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0709-02-047
BATTERSON,LLP(3.79%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.45%)
SEMARCK LANDSCAPE SERVICES, INC. (0.64%)
Contract # 09123247
Totals 2875006.16 0.00 2871673.42 99.9

CountyGONZALES
Highway FM 108
From AT DRAW
To STR # 0715-01-008
CSJ 0715-01-017
Proj ID BR 2013(700)
Work Type WIDEN BRIDGE AND APPROACHES
 
0.293 1055377.51 128745.96 1104101.42 99.9
Work Order 09-09-13
Work Began 10-28-13
Work Completed  
Time Computed 09-25-13
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 111
Contractor(s)
BEAR CREEK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0715-01-017
ROADWAY SPECIALTIES, INC.(3.62%)
D. I. J. CONSTRUCTION, INC.(1.13%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.70%)
LONE STAR HIGHWAY PRODUCTS, INC. (1.04%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 22.67%)
Contract # 05133214
Totals 1055377.51 128745.96 1104101.42 99.9

CountyGONZALES
Highway FM 108
From AT ELM CREEK BRANCH
To STR# 0715-02-014
CSJ 0715-02-013
Proj ID BR 2013(701)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.413 1904944.76 128838.61 689018.69 36.1
Work Order 09-06-13
Work Began 11-25-13
Work Completed  
Time Computed 09-22-13
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 36
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0715-02-013
AVAILABLE CONSTRUCTION AND TRANSPORT SERVICES, INC.( 27.69%)
FLASHER EQUIPMENT COMPANY(0.92%)
JUST GROOVING, LTD.(0.29%)
O & S TRAFFIC SUPPLIES (0.57%)
J R RAMON, INC.(2.28%)
ROADWAY SPECIALTIES, INC.(3.66%)
VOGES DRILLING CO. (5.25%)
PIPE WHOLESALERS OF TEXAS, INC.(0.07%)
Contract # 05133218
Totals 1904944.76 128838.61 689018.69 36.1

CountyVICTORIA
Highway FM 447
From US 87
To FM 236
CSJ 0842-02-021
Proj ID STP 1302(043)
Work Type REPAIR & WIDEN ROADWAY
 
5.401 2015294.58 148315.70 555710.03 27.5
Work Order 12-03-13
Work Began 01-16-14
Work Completed  
Time Computed 01-16-14
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 33
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0842-02-021
ROADSAFE TRAFFIC SYSTEMS, INC. (5.83%)
ROADWAY SPECIALTIES, INC.(6.05%)
LHOIST NORTH AMERICA (0.00%)
INGRAM READY MIX (0.00%)
ALAMO CONCRETE (0.00%)
Contract # 09133234
Totals 2015294.58 148315.70 555710.03 27.5

CountyDEWITT
Highway VA
From VARIOUS LOCATIONS
To IN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ 0913-00-088
Proj ID STP 2012(527)
Work Type CONSTRUCT CURB RAMPS
 
0.100 475081.00 5268.23 575183.17 99.9
Work Order 06-18-12
Work Began 04-05-13
Work Completed  
Time Computed 10-16-12
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 86
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.79%)
SPEEDY PAVING(2.40%)
Contract # 05123217
Totals 475081.00 5268.23 575183.17 99.9

CountyDEWITT
Highway CR
From AT DRAW CR 264
To (CABEZA RD) STR # AA03-05-001
CSJ 0913-17-033
Proj ID BR 2011(921)
Work Type STRUCTURE, BASE, SURFACING
 
0.066 487910.26 8613.50 443165.41 96.7
Work Order 05-08-13
Work Began 09-09-13
Work Completed  
Time Computed 07-07-13
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 208
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-033
RICE ENVIRONMENTAL SERVICES(4.64%)
O & S TRAFFIC SUPPLIES (0.28%)
SHINN & GREGORY, INC.( 13.29%)
Contract # 03133214
Totals 487910.26 8613.50 443165.41 96.7

CountyDEWITT
Highway CR
From AT CLEAR CREEK CR 162
To (JACKSON ROAD) AA03-21-001
CSJ 0913-17-035
Proj ID BR 1102(576)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.067 334220.00 27299.00 300362.82 89.8
Work Order 11-14-13
Work Began 02-17-14
Work Completed  
Time Computed 01-13-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 88
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-035
HEMPHILL PILE DRIVING CO., A CORP. (2.99%)
ODUM SERVICES, L.P.(3.48%)
CEN TEX HYDROSEED, INC.(0.49%)
JUST GROOVING, LTD.(0.43%)
Contract # 08133023
Totals 334220.00 27299.00 300362.82 89.8

CountyDEWITT
Highway CR
From AT DRAW CR 199
To (OLD GONZALES RD) # AA01-99-003
CSJ 0913-17-036
Proj ID BR 1102(585)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 202141.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143015
Totals 202141.00 0.00 0.00 0.0

CountyDEWITT
Highway CR
From AT DRAW
To (LINCKE RD) STR # AA03-23-001
CSJ 0913-17-037
Proj ID BR 1102(586)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 224026.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143213
Totals 224026.60 0.00 0.00 0.0

CountyJACKSON
Highway CR
From AT STEM BRANCH CR 284
To (CR 284) AA01-10-001
CSJ 0913-18-023
Proj ID BR 2011(304)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.142 696017.65 67969.12 67969.12 9.7
Work Order 03-25-14
Work Began 06-03-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 3
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-023
LONESTAR TRAFFIC SAFETY, LLC (0.63%)
JUST GROOVING, LTD.(0.30%)
SHINN & GREGORY, INC.(7.77%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.97%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 21.26%)
Contract # 01143021
Totals 696017.65 67969.12 67969.12 9.7

CountyJACKSON
Highway CR
From AT LAVACA RIVER RELIEF CR 174
To (CR 127) STR # AA01-74-001
CSJ 0913-18-027
Proj ID BR 1102(529)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.224 1084856.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-16-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143017
Totals 1084856.00 0.00 0.00 0.0

CountyAUSTIN
Highway CS
From VARIOUS SCHOOL LOCATIONS
To IN CITY OF SEALY
CSJ 0913-20-083
Proj ID STP 1102(301)SRS
Work Type CONSTRUCT SIDEWALKS, CROSSWALKS
 
1.338 564758.53 0.00 556324.45 98.5
Work Order 05-16-12
Work Began 09-28-12
Work Completed  
Time Computed 09-13-12
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 93
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-083
STRIPES & STOPS COMPANY, INC.(0.54%)
CHAPA"S CONSTRUCTION ( 32.49%)
SILVA CONTRACTING COMPANY, INC.(5.38%)
RICE ENVIRONMENTAL SERVICES(5.12%)
AMERICAN DRILLING & SAWING (0.38%)
CURB PLANET INC. (0.22%)
JASSO"S SAWING & SEALING (1.09%)
CANALES TRUCKING INC.(0.79%)
Contract # 04123029
Totals 564758.53 0.00 556324.45 98.5

CountyMATAGORDA
Highway CR
From AT CANEY CREEK CR 194
To (HAWKINS RD) STR # AA01-94-001
CSJ 0913-21-042
Proj ID BR 2014(299)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.171 1323586.20 0.00 0.00 0.0
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 06-14-14
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-042
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(2.74%)
FUQUAY, INC. (0.46%)
JMHP, INC. (1.62%)
JUST GROOVING, LTD.(0.19%)
LONESTAR TRAFFIC SAFETY, LLC (0.17%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 11.59%)
Contract # 02143019
Totals 1323586.20 0.00 0.00 0.0

CountyGONZALES
Highway CR
From CR 363 AT GELHORN CREEK
To STR # AA03-63-001
CSJ 0913-22-035
Proj ID BR 2011(495)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.055 236824.41 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143229
Totals 236824.41 0.00 0.00 0.0