Monthly State Let Construction Report For Yoakum District As Of Dec 10, 2014 Page 2 Of 4

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWHARTON
Highway SH 71
From AT TRES PALACIOS RIVER IN EL CAMPO
To STR # 0266-06-036
CSJ 0266-06-044
Proj ID BR 2013(593)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.164 1218475.90 7097.00 694679.77 57.2
Work Order 09-10-13
Work Began 11-13-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 102
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-06-044
ENVIRONMENTAL ALLIES, L.P. (0.13%)
WILLOW CITY SIGN & RAIL, INC.(1.28%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.21%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
MESA ROD BUSTERS, INC. (0.89%)
YORK & YORK FOUNDATION DRILLING, INC.(7.13%)
JUST GROOVING, LTD.(0.29%)
TEXAS IH CONSTRUCTORS, LLC (5.61%)
Contract # 04133229
Totals 1218475.90 7097.00 694679.77 57.2

CountyWHARTON
Highway SH 71
From WCR 405
To MATAGORDA COUNTY LINE
CSJ 0266-06-045
Proj ID STP 2014(740)
Work Type PAVEMENT REPAIR AND SURFACING
 
5.473 2333301.84 85265.42 699790.52 29.9
Work Order 06-20-14
Work Began 08-18-14
Work Completed  
Time Computed 08-18-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 52
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-06-045
PENHALL COMPANY(0.29%)
MURRAY CONSTRUCTION(0.25%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.75%)
Contract # 04143236
Totals 2333301.84 85265.42 699790.52 29.9

CountyCOLORADO
Highway IH 10
From COLORADO RIVER
To AUSTIN COUNTY LINE
CSJ 0271-01-076
Proj ID NH 2014(734)
Work Type ACP OVERLAY
 
14.447 8740907.81 652187.23 2564119.08 29.3
Work Order 06-30-14
Work Began 08-17-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 21
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0271-01-076
C PAVE, INC. (5.22%)
PENHALL COMPANY(0.27%)
MURRAY CONSTRUCTION(0.19%)
DUSTROL, INC.(3.49%)
BATTERSON,LLP(3.27%)
R & A TRANSPORT, INC.(0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.18%)
Contract # 05143012
Totals 8740907.81 652187.23 2564119.08 29.3

CountyGONZALES
Highway SH 80
From FM 446
To 1.23 MI. NORTH OF FM 1682
CSJ 0287-03-029
Proj ID STP 2014(591)
Work Type ACP OVERLAY
 
10.399 2198746.80 11541.68 2094876.76 95.2
Work Order 05-13-14
Work Began 09-03-14
Work Completed  
Time Computed 07-15-14
Contract Working Days 45
Addl Days Granted 4
Working Days Charged 36
Percent Time Used 73
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0287-03-029
BATTERSON,LLP(3.09%)
CHEROKEE SERVICES(0.34%)
WEST TEXAS RUMBLE STRIP(0.24%)
Contract # 04143209
Totals 2198746.80 11541.68 2094876.76 95.2

CountyGONZALES
Highway SH 80
From FM 1682
To CR 167
CSJ 0287-04-033
Proj ID STP 1402(096)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
9.030 203126.50 44830.00 51232.00 25.2
Work Order 10-07-14
Work Began 10-22-14
Work Completed  
Time Computed 10-22-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 66
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0287-04-033
RICE ENVIRONMENTAL SERVICES( 29.84%)
ROAD REPAIR, LLC ( 27.38%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.67%)
BEAVER CONTRACTORS, LLC( 27.38%)
Contract # 08143018
Totals 203126.50 44830.00 51232.00 25.2

CountyFAYETTE
Highway SH 95
From FLATONIA CITY LIMITS
To LAVACA COUNTY LINE
CSJ 0324-01-024
Proj ID STP 2014(550)
Work Type PAVEMENT REPAIR AND SURFACING
 
3.706 2459856.61 1293.17 2438118.84 99.1
Work Order 05-20-14
Work Began 06-18-14
Work Completed  
Time Computed 06-05-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 76
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0324-01-024
COWBELL TRAFFIC SERVICES, INC. (0.56%)
EGGEMEYER LAND CLEARING, LLC (0.58%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.73%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.14%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.46%)
RAMI MATERIALS TRANSPORT, LLC(2.21%)
Contract # 03143210
Totals 2459856.61 1293.17 2438118.84 99.1

CountyLAVACA
Highway SH 111
From DEWITT COUNTY LINE
To US 77
CSJ 0346-06-046
Proj ID STP 2013(594)
Work Type PAVEMENT REPAIR & ACP OVERLAY
 
11.649 2608000.01 62873.96 2709495.67 99.9
Work Order 07-31-13
Work Began 06-19-14
Work Completed  
Time Computed 07-08-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 126
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0346-06-046
COWBELL TRAFFIC SERVICES, INC. (1.18%)
FUQUAY, INC. (0.26%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.78%)
M.V. HENKE ENTERPRISES, INC. (0.36%)
MURRAY CONSTRUCTION(0.15%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.19%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (2.63%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.70%)
Contract # 05133035
Totals 2608000.01 62873.96 2709495.67 99.9

CountyLAVACA
Highway SH 111
From US 77
To JACKSON COUNTY LINE
CSJ 0346-06-048
Proj ID STP 1402(043)
Work Type PAVEMENT REPAIR AND RESURFACING
 
10.040 2257868.44 0.00 0.00 0.0
Work Order 08-07-14
Work Began 00-00-00
Work Completed  
Time Computed 09-02-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0346-06-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143060
Totals 2257868.44 0.00 0.00 0.0

CountyMATAGORDA
Highway FM 1468
From SH 71
To SH 35
CSJ 0346-10-021
Proj ID STP 1402(099)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
10.376 1128804.52 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0346-10-021
BEAVER CONTRACTORS, LLC(5.65%)
RICE ENVIRONMENTAL SERVICES(0.82%)
Contract # 08143039
Totals 1128804.52 0.00 0.00 0.0

CountyGONZALES
Highway SH 97
From CO RD 112
To US 183
CSJ 0347-01-028
Proj ID STP 2015(427)
Work Type REHABILITATE ROADWAY
 
12.814 10157843.77 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0347-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143205
Totals 10157843.77 0.00 0.00 0.0

CountyAUSTIN
Highway SH 159
From FM 109
To SH 36
CSJ 0408-02-045
Proj ID STP 2015(428)
Work Type ADD SHOULDERS
 
14.079 11278713.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0408-02-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143204
Totals 11278713.11 0.00 0.00 0.0

CountyLAVACA
Highway US 90A
From @ BRUSHY CREEK
To STR # 0446-01-016
CSJ 0446-01-047
Proj ID BR 2015(245)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.606 3321678.02 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143213
Totals 3321678.02 0.00 0.00 0.0

CountyCOLORADO
Highway US 90A
From AT EAST SANDY CREEK
To STR # 0446-02-027
CSJ 0446-02-030
Proj ID BR 2014(212)
Work Type REPLACE BRIDGE AND APPROACHES
 
1.060 3488667.34 2692.42 2021124.60 57.9
Work Order 02-06-14
Work Began 03-21-14
Work Completed  
Time Computed 03-21-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 148
Percent Time Used 98
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-02-030
SHINN & GREGORY, INC.(6.49%)
ROADWAY SPECIALTIES, INC.(3.12%)
JUST GROOVING, LTD.(0.13%)
JAMES CONSTRUCTION GROUP, L.L.C. ( 19.79%)
UNITED PAVEMENT & MARKINGS, LLC(0.80%)
LONESTAR TRAFFIC SAFETY, LLC (0.16%)
CD TRUCKING, INC (4.14%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.12%)
Contract # 11133206
Totals 3488667.34 2692.42 2021124.60 57.9

CountyCOLORADO
Highway FM 102
From SENIOR BRIDGE ROAD
To WHARTON COUNTY LINE
CSJ 0709-01-024
Proj ID STP 2013(918)
Work Type PAVEMENT REPAIR & SHOULDER WIDENING
 
5.655 3248432.42 278479.98 1534714.56 48.4
Work Order 10-17-13
Work Began 02-19-14
Work Completed  
Time Computed 12-16-13
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 140
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0709-01-024
KOSSMAN CONTRACTING CO., INC.(0.60%)
MURRAY CONSTRUCTION(0.32%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.86%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.16%)
M.V. HENKE ENTERPRISES, INC. (0.43%)
WEST TEXAS RUMBLE STRIP(0.11%)
DUSTROL, INC.(2.69%)
Contract # 07133048
Totals 3248432.42 278479.98 1534714.56 48.4

CountyWHARTON
Highway FM 102
From 0.27 MI. WEST OF FM 960
To 0.53 MI. WEST OF WHARTON CITY LIMIT
CSJ 0709-02-047
Proj ID STP 2013(073)
Work Type ADD SHOULDERS
 
4.109 2875006.16 0.00 2874765.70 99.9
Work Order 11-01-12
Work Began 01-07-13
Work Completed  
Time Computed 12-31-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 120
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0709-02-047
BATTERSON,LLP(3.79%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.45%)
SEMARCK LANDSCAPE SERVICES, INC. (0.64%)
Contract # 09123247
Totals 2875006.16 0.00 2874765.70 99.9

CountyGONZALES
Highway FM 108
From AT DRAW
To STR # 0715-01-008
CSJ 0715-01-017
Proj ID BR 2013(700)
Work Type WIDEN BRIDGE AND APPROACHES
 
0.293 1055377.51 5060.94 1116012.36 99.9
Work Order 09-09-13
Work Began 10-28-13
Work Completed  
Time Computed 09-25-13
Contract Working Days 90
Addl Days Granted 10
Working Days Charged 100
Percent Time Used 100
Contractor(s)
BEAR CREEK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0715-01-017
ROADWAY SPECIALTIES, INC.(3.62%)
D. I. J. CONSTRUCTION, INC.(1.13%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.70%)
LONE STAR HIGHWAY PRODUCTS, INC. (1.04%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 22.67%)
Contract # 05133214
Totals 1055377.51 5060.94 1116012.36 99.9

CountyGONZALES
Highway FM 108
From AT ELM CREEK BRANCH
To STR# 0715-02-014
CSJ 0715-02-013
Proj ID BR 2013(701)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.413 1904944.76 129273.73 1293737.60 67.9
Work Order 09-06-13
Work Began 11-25-13
Work Completed  
Time Computed 09-22-13
Contract Working Days 220
Addl Days Granted 1
Working Days Charged 173
Percent Time Used 78
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0715-02-013
AVAILABLE CONSTRUCTION AND TRANSPORT SERVICES, INC.( 27.69%)
FLASHER EQUIPMENT COMPANY(0.92%)
JUST GROOVING, LTD.(0.29%)
O & S TRAFFIC SUPPLIES (0.57%)
J R RAMON, INC.(2.28%)
ROADWAY SPECIALTIES, INC.(3.66%)
VOGES DRILLING CO. (5.25%)
PIPE WHOLESALERS OF TEXAS, INC.(0.07%)
DOUBLE S PAVING, INC.(5.93%)
Contract # 05133218
Totals 1904944.76 129273.73 1293737.60 67.9

CountyFAYETTE
Highway FM 153
From BASTROP COUNTY LINE
To US 77
CSJ 0807-03-032
Proj ID STP 2015(429)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
11.432 488019.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0807-03-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143011
Totals 488019.50 0.00 0.00 0.0

CountyVICTORIA
Highway FM 447
From US 87
To FM 236
CSJ 0842-02-021
Proj ID STP 1302(043)
Work Type REPAIR & WIDEN ROADWAY
 
5.401 2015294.58 96232.52 1337575.26 66.3
Work Order 12-03-13
Work Began 01-16-14
Work Completed  
Time Computed 01-16-14
Contract Working Days 165
Addl Days Granted 4
Working Days Charged 136
Percent Time Used 80
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0842-02-021
ROADSAFE TRAFFIC SYSTEMS, INC. (5.83%)
ROADWAY SPECIALTIES, INC.(6.05%)
LHOIST NORTH AMERICA (0.00%)
INGRAM READY MIX (0.00%)
ALAMO CONCRETE (0.00%)
Contract # 09133234
Totals 2015294.58 96232.52 1337575.26 66.3

CountyDEWITT
Highway VA
From VARIOUS LOCATIONS
To IN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ 0913-00-088
Proj ID STP 2012(527)
Work Type CONSTRUCT CURB RAMPS
 
0.100 475081.00 0.00 575183.17 99.9
Work Order 06-18-12
Work Began 04-05-13
Work Completed  
Time Computed 10-16-12
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 86
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.79%)
SPEEDY PAVING(2.40%)
Contract # 05123217
Totals 475081.00 0.00 575183.17 99.9