Seq No County Project ID CCSJ Highway Reason for change
001 JEFFERSON NH 1702(506) 0739-02-161 IH 10 due to need for a STIP revision
018 BOWIE STP 1702(446)HES 0217-02-035 US 71 due to pending agreement with State of Arkansas
020 DALLAS BR 1702(459) 2374-03-090 IH 20 due to being combined with 2374-01-187
024 CAMERON STP 1702(342)MM 0921-06-280 CS due to late PS&E outside source
025 HARDIN BR 1702(507) 0920-03-034 CR due to a redesign requested by the local government and environmental stewardship
030 JEFFERSON STP 1702(503)HES 0200-11-101 US 69 due to the work being done on another CSJ
040 ORANGE BR 1702(508) 0920-30-079 CS due to not getting FHWA approval in time
204 SAN PATRICIO NH 1702(490) 0101-04-097 US 181 due to local development affecting location of proposed overpass
204 MAVERICK NH 1702(331) 0300-01-080
US 277
due to STIP Revision Required
204 TRAVIS 3136-01-015  
SL 1
due to pending ENV clearance
205 WILLACY NH 1702(492) 0327-10-057 US 77 due to STIP Revision Required
224 TARRANT CM 2007(227) 0902-48-576 CS due to unclear utilities
230 HIDALGO BR 2011(281) 0921-02-212 CR due to FHWA coordination
241 SMITH STP 1702(466) 0910-00-108 VA due to a PS&E revision being required

 