Detail Letting Schedule for Comal County (FY 2019)

Last Update: Monday, November 13, 2017
Comal County (FY 2019)

CCSJ: 0016-19-024

District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 482Let Status:Tentative
Project ID:STP ( )CSJ:0016-19-024
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:0.4 MILES SW OF KRUEGER CANYONFund Cat:1
Limits To:IH 35ESTIMATE:$138,380
Length:2.6Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 78Let Status:Tentative
Project ID:STP ( )CSJ:0025-10-095
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:FM 3009Fund Cat:1
Limits To:WEST SIDE OF LP 539ESTIMATE:$50,425
Length:1.3Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 78Let Status:Tentative
Project ID:STP ( )CSJ:0025-10-096
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:EAST SIDE OF LP 539Fund Cat:1
Limits To:SANTA CLARA CREEKESTIMATE:$162,090
Length:4.1Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 78Let Status:Tentative
Project ID:STP ( )CSJ:0025-11-001
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:WEST SIDE OF LP 539Fund Cat:1
Limits To:EAST SIDE OF LP 539ESTIMATE:$39,611
Length:1.0Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:US 83Let Status:Tentative
Project ID:STP ( )CSJ:0036-08-053
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:1.65 MILES NORTH OF FM 1051Fund Cat:1
Limits To:0.4 MI N OF SH 55ESTIMATE:$838,485
Length:18.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:US 87Let Status:Tentative
Project ID:STP ( )CSJ:0072-02-020
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:GILLESPIE/KENDALL C/LFund Cat:1
Limits To:KENDALL/KERR C/LESTIMATE:$207,733
Length:2.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:US 87Let Status:Tentative
Project ID:STP ( )CSJ:0072-03-016
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:KENDALL/KERR C/LFund Cat:1
Limits To:KERR/KENDALL C/LESTIMATE:$100,818
Length:1.3Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:US 87Let Status:Tentative
Project ID:STP ( )CSJ:0072-04-035
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:KERR/KENDALL C/LFund Cat:1
Limits To:IH 10ESTIMATE:$445,598
Length:7.3Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:US 181Let Status:Tentative
Project ID:NH ( )CSJ:0100-04-040
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:0.13 MI S OF FM FM 537Fund Cat:1
Limits To:KARNES COUNTY LINEESTIMATE:$228,900
Length:9.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 27Let Status:Tentative
Project ID:STP ( )CSJ:0142-03-030
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:IH 10Fund Cat:1
Limits To:SH 39ESTIMATE:$490,537
Length:13.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 466Let Status:Tentative
Project ID:STP ( )CSJ:0216-03-033
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:SH 123Fund Cat:1
Limits To:FM 1117ESTIMATE:$178,630
Length:5.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 80Let Status:Tentative
Project ID:STP ( )CSJ:0287-02-015
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:IH 10Fund Cat:1
Limits To:GONZALES COUNTYESTIMATE:$138,487
Length:3.1Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 16Let Status:Tentative
Project ID:STP ( )CSJ:0291-07-035
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:0.4 MI E OF FM 1283Fund Cat:1
Limits To:MEDINA C/LESTIMATE:$404,993
Length:7.6Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 16Let Status:Tentative
Project ID:STP ( )CSJ:0291-08-024
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:BANDERA/MEDINA C/LFund Cat:1
Limits To:MEDINA/BEXAR C/LESTIMATE:$145,509
Length:2.7Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 119Let Status:Tentative
Project ID:NH ( )CSJ:0359-05-011
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:US 87Fund Cat:1
Limits To:FM 1347ESTIMATE:$115,896
Length:4.0Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 173Let Status:Tentative
Project ID:STP ( )CSJ:0421-02-029
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:IH 35Fund Cat:1
Limits To:FRIO C/LESTIMATE:$158,851
Length:3.3Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 173Let Status:Tentative
Project ID:STP ( )CSJ:0421-03-014
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:FRIO C/LFund Cat:1
Limits To:ATASCOSA C/LESTIMATE:$258,350
Length:5.3Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 173Let Status:Tentative
Project ID:STP ( )CSJ:0421-04-032
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:ATASCOSA C/LFund Cat:1
Limits To:FM 2504ESTIMATE:$51,322
Length:1.1Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:IH 410Let Status:Tentative
Project ID:NH ( )CSJ:0521-05-147
Description:SEAL COAT AND PAVEMENT MARKINGS ON FRONTAGE ROADSHandling
Code:
 
Limits From:SH 16Fund Cat:1
Limits To:PEARSALL ROADESTIMATE:$386,162
Length:5.3Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SL 98Let Status:Tentative
Project ID:STP ( )CSJ:0526-01-019
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:JAMES ROADFund Cat:1
Limits To:SH 16ESTIMATE:$153,371
Length:2.2Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 1796Let Status:Tentative
Project ID:STP ( )CSJ:0595-01-009
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:RM 187 NFund Cat:1
Limits To:MEDINA C/LESTIMATE:$98,722
Length:3.8Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 173Let Status:Tentative
Project ID:STP ( )CSJ:0609-01-022
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:SH 16Fund Cat:1
Limits To:LP 534ESTIMATE:$119,534
Length:2.0Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 16Let Status:Tentative
Project ID:STP ( )CSJ:0613-01-062
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:IH 410Fund Cat:1
Limits To:ATASCOSA C/LESTIMATE:$1,061,716
Length:10.5Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:SH 16Let Status:Tentative
Project ID:STP ( )CSJ:0613-02-064
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:BEXAR C/LFund Cat:1
Limits To:FM 476ESTIMATE:$825,291
Length:8.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:RM 187Let Status:Tentative
Project ID:STP ( )CSJ:0678-02-037
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:KERR C/LFund Cat:1
Limits To:0.1 MI E OF LOST MAPLES ENTRANCEESTIMATE:$264,100
Length:14.1Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 140Let Status:Tentative
Project ID:STP ( )CSJ:0748-05-042
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:COUNTY ROAD 343Fund Cat:1
Limits To:SH 16ESTIMATE:$290,974
Length:9.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 775Let Status:Tentative
Project ID:STP ( )CSJ:0850-01-025
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:FM 2538Fund Cat:1
Limits To:GUADALUPE/WILSON C/LESTIMATE:$199,800
Length:6.5Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 465Let Status:Tentative
Project ID:STP ( )CSJ:0850-01-026
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:FM 78Fund Cat:1
Limits To:IH 10ESTIMATE:$101,590
Length:3.6Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 775Let Status:Tentative
Project ID:STP ( )CSJ:0850-02-047
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:GUADALUPE/WILSON C/LFund Cat:1
Limits To:LOOP 321ESTIMATE:$48,655
Length:1.6Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 3432Let Status:Tentative
Project ID:STP ( )CSJ:0850-04-029
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:BEXAR C/LFund Cat:1
Limits To:FM 775ESTIMATE:$128,283
Length:3.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 1350Let Status:Tentative
Project ID:STP ( )CSJ:0855-05-012
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:RM 480Fund Cat:1
Limits To:SH 27ESTIMATE:$57,159
Length:2.1Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:RM 334Let Status:Tentative
Project ID:STP ( )CSJ:0876-03-010
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:KINNEY C/LFund Cat:1
Limits To:SH 55ESTIMATE:$187,337
Length:7.2Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 536Let Status:Tentative
Project ID:STP ( )CSJ:1009-01-039
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:ATASCOSA C/LFund Cat:1
Limits To:FM 2579ESTIMATE:$298,847
Length:9.5Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 541Let Status:Tentative
Project ID:STP ( )CSJ:1011-01-036
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:FM 2505Fund Cat:1
Limits To:US 181ESTIMATE:$296,947
Length:11.4Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 775Let Status:Tentative
Project ID:STP ( )CSJ:1125-01-012
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:IH 10Fund Cat:1
Limits To:FM 2538ESTIMATE:$222,740
Length:7.4Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 1150Let Status:Tentative
Project ID:STP ( )CSJ:1269-01-022
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:US 90AFund Cat:1
Limits To:FM 1104ESTIMATE:$106,852
Length:4.1Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 1102Let Status:Tentative
Project ID:STP ( )CSJ:1273-01-037
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:FM 2439/WATSON LANEFund Cat:1
Limits To:FM 306ESTIMATE:$240,509
Length:4.6Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 140Let Status:Tentative
Project ID:STP ( )CSJ:1431-02-017
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:CHARLOTTE CITY LIMITSFund Cat:1
Limits To:COUNTY ROAD 343ESTIMATE:$75,872
Length:2.6Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 1343Let Status:Tentative
Project ID:STP ( )CSJ:1436-01-023
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:US 90Fund Cat:1
Limits To:SH 173ESTIMATE:$989,824
Length:13.2Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 481Let Status:Tentative
Project ID:STP ( )CSJ:1590-01-022
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:US 90 MAIN STFund Cat:1
Limits To:ZAVALA C/LESTIMATE:$386,865
Length:14.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 476Let Status:Tentative
Project ID:STP ( )CSJ:1740-02-033
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:BEXAR C/LFund Cat:1
Limits To:FM 2504ESTIMATE:$495,347
Length:8.1Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 539Let Status:Tentative
Project ID:STP ( )CSJ:2233-01-016
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:US 87Fund Cat:1
Limits To:GUADALUPE C/LESTIMATE:$330,848
Length:7.9Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 725Let Status:Tentative
Project ID:STP ( )CSJ:2710-01-018
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:FM 78Fund Cat:1
Limits To:FM 467ESTIMATE:$187,546
Length:7.3Actual$0
 
District:SAN ANTONIOLet Date:Oct 2018
Highway:FM 3445Let Status:Tentative
Project ID:STP ( )CSJ:3439-01-007
Description:SEAL COAT AND PAVEMENT MARKINGSHandling
Code:
 
Limits From:SH 16Fund Cat:1
Limits To:0.25 MILES EAST OF SAN MIGUEL CREEKESTIMATE:$234,330
Length:7.2Actual$0
 
Back...
Totals for 0016-19-024
Length:276
Estimate:$11,943,836
Actual:

CCSJ: 0511-02-021

District:SAN ANTONIOLet Date:Sep 2018
Highway:RM 32Let Status:Tentative
Project ID:STP ( )HESCSJ:0511-02-021
Description:INSTALL FLASHING BEACON & SAFETY ILLUMINATION ATHandling
Code:
 
Limits From:AT RM 484Fund Cat:8
Limits To:.ESTIMATE:$61,832
Length:0.2Actual$0
 
Back...
Totals for 0511-02-021
Length:0.2
Estimate:$61,832
Actual:

CCSJ: 0915-17-066

District:SAN ANTONIOLet Date:May 2019
Highway:CSLet Status:Tentative
Project ID:STP ( )TPCSJ:0915-17-066
Description:CONSTRUCT SIDEWALKS, RAMPS, & OTHER PEDESTRIAN RELATEDHandling
Code:
LC
Limits From:IN NEW BRAUNFELS ON SAN ANTONIO ST,Fund Cat:3
Limits To:WALNUT, MCQUEENEY, NEAR SEELE ELEMESTIMATE:$1,516,711
Length:2.2Actual$0
 
Back...
Totals for 0915-17-066
Length:2.2
Estimate:$1,516,711
Actual:

CCSJ: 1272-01-019

District:SAN ANTONIOLet Date:Sep 2018
Highway:FM 1101Let Status:Tentative
Project ID:STP ( )HESCSJ:1272-01-019
Description:PROFILE EDGELINE & CENTERLINE MARKINGSHandling
Code:
 
Limits From:SH 46Fund Cat:8
Limits To:GUADALUPE C/LESTIMATE:$155,056
Length:7.0Actual$0
 
Back...
Totals for 1272-01-019
Length:7
Estimate:$155,056
Actual:

CCSJ: 1541-01-015

District:SAN ANTONIOLet Date:Sep 2018
Highway:FM 311Let Status:Tentative
Project ID:STP ( )HESCSJ:1541-01-015
Description:PROFILE EDGELINE & CENTERLINE MARKINGSHandling
Code:
 
Limits From:US 281Fund Cat:8
Limits To:SH 46ESTIMATE:$177,364
Length:8.0Actual$0
 
Back...
Totals for 1541-01-015
Length:8
Estimate:$177,364
Actual:

CCSJ: 2650-01-025

District:SAN ANTONIOLet Date:Sep 2018
Highway:FM 2673Let Status:Tentative
Project ID:STP ( )HESCSJ:2650-01-025
Description:PROFILE EDGELINE & CENTERLINE MARKINGSHandling
Code:
 
Limits From:RM 2722Fund Cat:8
Limits To:FM 306ESTIMATE:$137,004
Length:6.2Actual$0
 
Back...
Totals for 2650-01-025
Length:6.2
Estimate:$137,004
Actual:

CCSJ: 8408-15-006

District:SAN ANTONIOLet Date:May 2019
Highway:MHLet Status:Tentative
Project ID:BR ( )CSJ:8408-15-006
Description:REHABILITATE BRIDGE & APPROACHESHandling
Code:
 
Limits From:IN NEW BRAUNFELS ON SAN ANTONIO STFund Cat:6
Limits To:AT COMAL RIVERESTIMATE:$4,493,110
Length:0.0Actual$0
 
Back...
Totals for 8408-15-006
Length:0
Estimate:$4,493,110
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract