Letting Schedule for Waco District (FY 2019)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Waco District (FY 2019) |
Bell | Bosque | Coryell | Falls | Hamilton | Hill | Limestone | Mclennan | | |||||||
Bell County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0320-01-073 | SS 290 | Actual | Jan 2019 | $1,421,278 | 11 | MILL AND INLAY | 0.0 |
0836-02-075 | SH 195 | Actual | Jan 2019 | $320,716 | 8 | INSTALL TRAFFIC SIGNAL, ADVANCED WARNING SIGNAL, AND SIGNS | 0.0 |
0184-03-038 | SH 53 | Actual | Jan 2019 | $1,204,128 | 1 | MILL/OVERLAY | 0.0 |
0836-02-025 | SH 195 | Actual | Nov 2018 | $339,204 | 1 | SAFETY LIGHTING | 0.0 |
0909-36-157 | CS | Actual | Nov 2018 | $2,375,101 | 3 | CONSTRUCT HIKE AND BIKE TRAIL AND SIDEWALKS WITH LANDSCAPING | 0.0 |
0015-14-126 | IH 35 | Actual | Jan 2019 | $7,788,332 | 1 | MILL AND PFC OVERLAY | 0.0 |
2136-01-015 | FM 2268 | Actual | Feb 2019 | $4,229,503 | 6 | REPLACE BRIDGE AND APPROACHES | 8.0 |
1835-02-056 | FM 1741 | Approved | Aug 2019 | $2,100,000 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0231-03-145 | US 190 | Approved | Jun 2019 | $2,834,780 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
3409-01-006 | FM 3481 | Approved | Aug 2019 | $1,849,028 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0909-36-164 | CS | Tentative | Aug 2019 | $250,000 | 8 | UPGRADE RR CROSSING SIGNALS FEDERAL SAFETY PROGRAM (FSP) | 0.0 |
0320-01-072 | SH 95 | Actual | Apr 2019 | $5,231,397 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0184-03-040 | SH 53 | Actual | Mar 2019 | $1,473,450 | 1 | PREVENTIVE MAINTENANCE | 3.0 |
0836-02-073 | SH 195 | Approved | May 2019 | $3,800,502 | 1 | HIGHWAY/RAILROAD IMPROVEMENT | 4.0 |
0015-05-050 | SH 317 | Approved | May 2019 | $526,577 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0185-01-030 | US 190 | Approved | Jul 2019 | $62,800,000 | 1 | Widen Road - Add Lanes | 0.0 |
Bosque County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
2872-01-007 | FM 2840 | Tentative | Aug 2019 | $31,144 | 10 | REPLACE CONCRETE CROSSING SURFACE | 0.0 |
Coryell County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0055-04-031 | US 84 | Approved | Aug 2019 | $190,950 | 8 | Hazard Elimination & Safety | 0.0 |
1187-01-029 | FM 929 | Actual | Sep 2018 | $8,219,885 | 1 | SEAL COAT | 0.0 |
0567-01-020 | FM 107 | Approved | May 2019 | $2,276,526 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0724-01-053 | FM 116 | Actual | Jan 2019 | $1,751,017 | 11 | BASE REPAIR, SEAL AND OVERLAY | 0.0 |
Falls County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0049-04-063 | SH 6 | Actual | Apr 2019 | $782,215 | 1 | OVERLAY | 3.0 |
0382-02-036 | SH 7 | Actual | Feb 2019 | $7,235,206 | 1 | MILL/OVERLAY | 2.0 |
0909-38-082 | CR | Approved | Jun 2019 | $861,440 | 6 | BRIDGE REPLACEMENT | 0.0 |
0909-38-081 | CR | Actual | Mar 2019 | $1,400,650 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0909-38-080 | CR | Approved | May 2019 | $1,064,773 | 6 | REPLACE BRIDGE AND APPROACHES | 5.0 |
Hamilton County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0120-05-025 | FM 218 | Actual | Nov 2018 | $510,929 | 1 | INSTALL CHEVRONS ON CURVE, INCREASE SUPERELELVATION | 0.0 |
0183-03-050 | SH 36 | Approved | May 2019 | $12,013,826 | 11 | Widen Road - Add Lanes | 4.5 |
Hill County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0048-09-029 | IH 35E | Approved | May 2019 | $102,403,120 | 1 | Widen Road - Add Lanes | 8.0 |
0014-07-103 | SH 81 | Approved | Aug 2019 | $475,128 | 1 | Hazard Elimination & Safety | 0.0 |
Limestone County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0056-02-033 | US 84 | Actual | Nov 2018 | $9,150,814 | 1 | WIDEN SHOULDERS AND ADD PASSING LANES | 6.5 |
Mclennan County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0909-22-176 | CR | Actual | Apr 2019 | $948,046 | 3 | REPLACE BRIDGE AND APPROACHES | 6.0 |
2061-02-030 | FM 2114 | Actual | Oct 2018 | $9,370,224 | 1 | REHABILITATE AND WIDEN ROADWAY | 7.0 |
0015-01-243 | IH 35 | Actual | Dec 2018 | $383,763,647 | 1 | RECONST, WIDEN MAINLANES FROM 6 TO 8, RECONST FRONTAGE RD | 11.0 |
0833-03-045 | FM 1637 | Approved | May 2019 | $9,395,341 | 8 | Hazard Elimination & Safety | 6.0 |
0909-22-177 | CR | Approved | Jul 2019 | $875,000 | 3 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0055-08-122 | US 84 | Approved | Aug 2019 | $1,787,971 | 1 | Hazard Elimination & Safety | 0.0 |
1192-01-024 | FM 939 | Actual | Jan 2019 | $6,879,586 | 1 | WIDEN PAVEMENT TO ADD SHOULDERS, PROVIDE SAFETY UPGRADES AND | 6.5 |
0209-01-063 | SL 2 | Actual | Feb 2019 | $864,347 | 11 | MILL AND OVERLAY | 0.0 |
0162-01-094 | US 84 | Actual | Dec 2018 | $93,974 | 8 | IMPROVE TRAFFIC SIGNAL, INSTALL ADVANCE WARNING SIGNALS AND | 0.0 |
2506-01-041 | FM 1695 | Tentative | Aug 2019 | $66,408 | 10 | REPLACE CONCRETE CROSSING SURFACE | 0.0 |
0909-22-183 | CS | Approved | Aug 2019 | $217,757 | 3 | Hazard Elimination & Safety | 0.0 |
|