Monthly Local Let Maintenance Report For Dallas District As Of Jan 10, 2023 Page 1 Of 8

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6201-06-001
Proj IDRMC - 620106001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.001191208.00162028.5784.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-11
Work Began05-18-11
Work Completed
Time Computed07-17-11
Contract Working Days730
Addl Days Granted80
Working Days Charged810
Percent Time Used100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04111801
Totals191208.000.00162028.5784.7

CountyKAUFMAN
HighwayMR0682
FromVARIOUS LOCATIONS AT THE
ToTERRELL STATE HOSPITAL
CSJ6207-65-001
Proj IDRMC - 620765001
Work TypeREHABILITATE ROADWAYS
 
0.001179519.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07101802
Totals179519.150.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6208-46-001
Proj IDRMC - 620846001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
88.77750652.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09101801
Totals50652.700.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH30 AT PARKER CREEK, PARKER CREEK
ToBRANCH, FM551 HACKBERRY CREEK, US175
CSJ6259-42-001
Proj IDBPM - 625942001
Work TypeREPLACE WINGWALLS & REPAIR SPALLING
 
0.001130385.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11131801
Totals130385.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromAT PRICE CREEK
ToIN COLLIN COUNTY
CSJ6274-02-001
Proj IDBPM - 627402001
Work TypeREPAIR OF ABUTMENT SLOPES
 
0.00149292.000.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed06-10-15
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141803
Totals49292.000.000.00100.0

CountyDALLAS
HighwayIH0030
FromIH 30 AT ST PAUL UNDERPASS IN THE
ToNORTHEAST DALLAS MAINTENANCE SECTION
CSJ6286-56-001
Proj IDRMC - 628656001
Work TypeINSTALL FENCE
 
0.001102710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151804
Totals102710.000.000.000.0

CountyNAVARRO
HighwaySH0022
FromVARIOUS ROADWAYS IN THE NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6292-76-001
Proj IDRMC - 629276001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001163060.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161805
Totals163060.000.000.000.0

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6341-60-001
Proj IDRMC - 634160001
Work TypeON-CALL REFLECTORIZED PAVEMENT MARKINGS
 
0.001282300.00195552.0369.2
Work Order09-08-21
Work Began09-15-21
Work Completed
Time Computed09-15-21
Contract Working Days730
Addl Days Granted0
Working Days Charged465
Percent Time Used63
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6341-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07191804
Totals282300.000.00195552.0369.2

CountyKAUFMAN
HighwayFM2727
FromDALLAS
ToDISTRICT COMPLEX
CSJ6355-86-001
Proj IDSUP - 635586001
Work TypeDAY LABOR
 
0.01086598.0068775.0079.4
Work Order03-17-21
Work Began03-17-21
Work Completed
Time Computed03-24-21
Contract Working Days365
Addl Days Granted365
Working Days Charged649
Percent Time Used88
Contractor(s)
WORKQUEST
SUBCONTRACTOR(S) FOR CCSJ: 6355-86-001
A LIFT FOR LIFE OUTREACH, INC. (0.00)
Contract #03211830
Totals86598.002100.0068775.0079.4

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6363-78-001
Proj IDRMC - 636378001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
216637.50160240.1873.9
Work Order07-19-21
Work Began07-27-21
Work Completed
Time Computed07-29-21
Contract Working Days730
Addl Days Granted0
Working Days Charged517
Percent Time Used70
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6363-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05211803
Totals216637.5015707.92160240.1873.9

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6365-66-001
Proj IDRMC - 636566001
Work TypeON-CALL RETROFLECTORIZED PAVEMENT MARKGS
 
0.001204733.8072282.6135.3
Work Order05-17-21
Work Began05-24-21
Work Completed
Time Computed05-24-21
Contract Working Days730
Addl Days Granted0
Working Days Charged582
Percent Time Used79
Contractor(s)
PMI PAVEMENT MARKING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6365-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201802
Totals204733.800.0072282.6135.3

CountyNAVARRO
HighwaySH0031
FromROADWAY MATERIAL
ToNAVARRO COUNTY
CSJ6366-06-001
Proj IDMMC - 636606001
Work TypeAGGREGATE (MATERIAL ONLY)
 
0.001100000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6366-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08201823
Totals100000.000.000.000.0

CountyDALLAS
HighwayUS0080
FromDISTRICT COMPLEX
ToDISTRICT COMPLEX
CSJ6375-99-001
Proj IDSUP - 637599001
Work TypeGROUNDS MAINTENANCE
 
0.010273434.64132807.5648.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted401
Working Days Charged664
Percent Time Used86
Contractor(s)
WORKQUEST
SUBCONTRACTOR(S) FOR CCSJ: 6375-99-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #03211831
Totals273434.644185.64132807.5648.5

CountyROCKWALL
HighwayIH0030
FromROCKWALL COUNTY
ToMAINTENANCE OFFICE
CSJ6376-66-001
Proj IDSUP - 637666001
Work TypeJANITORIAL MAINTENANCE
 
0.01045848.0034376.5674.9
Work Order02-01-21
Work Began02-08-21
Work Completed
Time Computed02-08-21
Contract Working Days365
Addl Days Granted0
Working Days Charged686
Percent Time Used187
Contractor(s)
WORKQUEST
ACHIEVE
SUBCONTRACTOR(S) FOR CCSJ: 6376-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211830
Totals45848.001050.0034376.5674.9

CountyDALLAS
HighwayUS0067
FromSW DALLAS COUNTY
ToMAINTENANCE SECTION
CSJ6376-68-001
Proj IDSUP - 637668001
Work TypeJANITORIAL MAINTENANCE
 
0.01070510.0063173.0089.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged693
Percent Time Used94
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211832
Totals70510.002839.0063173.0089.5

CountyCOLLIN
HighwayUS0380
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6377-11-001
Proj IDRMC - 637711001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.010151898.25133302.99100.0
Work Order10-05-21
Work Began10-11-21
Work Completed12-09-22
Time Computed10-12-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06211802
Totals151898.250.00133302.99100.0

CountyDENTON
HighwayIH0035E
FromVARIOUS ROADWAYS IN
ToDENTON COUNTY
CSJ6378-73-001
Proj IDRMC - 637873001
Work TypeREPAIR/REPLACE CONCRETE BARRIER
 
0.010246475.00221306.0989.7
Work Order04-18-22
Work Began04-25-22
Work Completed
Time Computed04-25-22
Contract Working Days730
Addl Days Granted0
Working Days Charged243
Percent Time Used33
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6378-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03221805
Totals246475.000.00221306.0989.7

CountyCOLLIN
HighwaySH0005
FromDENTON COUNTY
ToAREA AND MAINTENANCE OFFICE
CSJ6380-99-001
Proj IDSUP - 638099001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.010102548.7674983.1973.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-12-21
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted550
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
SUBCONTRACTOR(S) FOR CCSJ: 6380-99-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #04211830
Totals102548.763184.6674983.1973.1

CountyCOLLIN
HighwayFM0547
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6381-15-001
Proj IDRMC - 638115001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.01052577.0041317.0078.5
Work Order11-23-21
Work Began12-01-21
Work Completed
Time Computed12-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
BUSHWACKERS CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6381-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08211803
Totals52577.000.0041317.0078.5

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6382-88-001
Proj IDRMC - 638288001
Work TypeRAISED PAVEMENT MARKERS
 
0.010166552.50214293.00100.0
Work Order10-25-21
Work Began11-07-21
Work Completed12-29-22
Time Computed11-07-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6382-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08211807
Totals166552.500.00214293.00100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8