Monthly Local Let Maintenance Report For Dallas District As Of Nov 10, 2024 Page 7 Of 7
Last Update: Sunday, November 10, 2024
 |
|
| Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
| County | COLLIN |
| Highway | SH0078 |
| From | VARIOUS ROADWAYS IN |
| To | COLLIN COUNTY MAINTENANCE SECTION |
| CSJ | 6474-19-001 |
| Proj ID | SUP - 647419001 |
| Work Type | PICNIC AREA MAINTENANCE |
| |
| 0.010 | 66890.00 | | 3750.00 | 5.6 |
| Work Order | 09-24-24 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 10-01-24 |
| Contract Working Days | 365 |
| Addl Days Granted | 0 |
| Working Days Charged | 25 |
| Percent Time Used | 6 |
| Contractor(s) |
WORKQUEST LIBERTY PROCLAIMED MINISTRY |
SUBCONTRACTOR(S) FOR CCSJ: 6474-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09241833 |
| Totals | 66890.00 | 3750.00 | 3750.00 | 5.6 |
|
| County | ELLIS |
| Highway | FM0876 |
| From | ELLIS |
| To | MAINTENANCE SECTION |
| CSJ | 6474-73-001 |
| Proj ID | MMC - 647473001 |
| Work Type | WINTER WEATHER MATERIAL |
| |
| 0.010 | 164650.00 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 180 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| NSG LOGISTICS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6474-73-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 10241817 |
| Totals | 164650.00 | 0.00 | 0.00 | 0.0 |
|
| County | KAUFMAN |
| Highway | FM2728 |
| From | KAUFMAN/ROCKWALL |
| To | MAINTENANCE SECTION |
| CSJ | 6475-36-001 |
| Proj ID | MMC - 647536001 |
| Work Type | ASPHALTIC PATCHING MATERIAL |
| |
| 0.010 | 159552.00 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 180 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| WALLER COUNTY ASPHALT INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6475-36-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 10241812 |
| Totals | 159552.00 | 0.00 | 0.00 | 0.0 |
|
| County | DENTON |
| Highway | US0380 |
| From | FROM DENTON COUNTY |
| To | TO MAINTENANCE SECTION |
| CSJ | 6475-45-001 |
| Proj ID | MMC - 647545001 |
| Work Type | WINTER WEATHER MATERIAL |
| |
| 0.010 | 64680.00 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 180 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| THE BARGAIN SOURCE |
SUBCONTRACTOR(S) FOR CCSJ: 6475-45-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 10241815 |
| Totals | 64680.00 | 0.00 | 0.00 | 0.0 |
|
| County | DALLAS |
| Highway | IH0030 |
| From | VARIOUS ROADWAYS IN |
| To | DALLAS COUNTY |
| CSJ | 6475-46-001 |
| Proj ID | MMC - 647546001 |
| Work Type | WINTER WEATHER MATERIAL |
| |
| 0.010 | 329167.00 | | 0.00 | 0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order | 00-00-00 |
| Work Began | 00-00-00 |
| Work Completed | |
| Time Computed | 00-00-00 |
| Contract Working Days | 180 |
| Addl Days Granted | 0 |
| Working Days Charged | 0 |
| Percent Time Used | 0 |
| Contractor(s) |
| THE BARGAIN SOURCE |
SUBCONTRACTOR(S) FOR CCSJ: 6475-46-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 10241816 |
| Totals | 329167.00 | 0.00 | 0.00 | 0.0 |
|