Monthly Local Let Maintenance Report For Lufkin District As Of Jul 13, 2021 Page 1 Of 9

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN AUGUSTINE
HighwayUS0096
FromUS 96 & VARIOUS LOCATIONS WITHIN
ToSAN AUGUSTINE MAINT SECTION
CSJ6243-02-001
Proj IDSUP - 624302001
Work TypePICNIC/GROUNDS/CURB AND GUTTER MAINT
 
0.01086588.8057479.6066.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-17-12
Work Began07-01-12
Work Completed
Time Computed07-01-12
Contract Working Days250
Addl Days Granted0
Working Days Charged151
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04121131
Totals86588.800.0057479.6066.3

CountySAN AUGUSTINE
HighwayUS0096
FromUS 96 & VARIOUS LOCATINS WITHIN
ToSAN AUGUSTINE MAINT SECTION
CSJ6243-89-001
Proj IDSUP - 624389001
Work TypeLITTER PICKUP MAINTENANCE
 
0.010261391.74257418.6398.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-07-12
Work Began08-01-12
Work Completed
Time Computed08-01-12
Contract Working Days190
Addl Days Granted0
Working Days Charged109
Percent Time Used57
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6243-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05121136
Totals261391.740.00257418.6398.4

CountyNACOGDOCHES
HighwayUS0059
FromUS 59 & VARIOUS LOCATIONS WITHIN
ToNACOGDOCHES MAINT SECTION
CSJ6244-23-001
Proj IDSUP - 624423001
Work TypeLITTER PICKUP MAINTENANCE
 
0.010208704.36151515.7872.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-12
Work Began08-01-12
Work Completed
Time Computed08-01-12
Contract Working Days190
Addl Days Granted0
Working Days Charged115
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6244-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05121138
Totals208704.360.00151515.7872.5

CountyTRINITY
HighwaySH0019
FromSH 19 AND VARIOUS ROADWAYS
ToIN TRINITY COUNTY
CSJ6261-02-001
Proj IDSUP - 626102001
Work TypeLITTER PICKUP
 
0.01058785.2835917.2761.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-13
Work Began08-01-13
Work Completed
Time Computed08-01-13
Contract Working Days190
Addl Days Granted0
Working Days Charged52
Percent Time Used27
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6261-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07131132
Totals58785.280.0035917.2761.0

CountySAN JACINTO
HighwayUS0059
FromUS 59 AND VARIOUS ROADWAYS
ToIN SAN JACINTO COUNTY
CSJ6261-11-001
Proj IDSUP - 626111001
Work TypeLITTER PICKUP
 
0.010141236.34110183.5578.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-13
Work Began08-01-13
Work Completed
Time Computed08-01-13
Contract Working Days190
Addl Days Granted0
Working Days Charged118
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6261-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07131134
Totals141236.340.00110183.5578.0

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS IN
ToSAN AUGUSTINE COUNTY
CSJ6261-33-001
Proj IDSUP - 626133001
Work TypeREM/REPL DEL POST/OBJ MRK, MAILBOX UGRD/
 
0.100100000.0097002.0097.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-01-13
Work Completed
Time Computed07-01-13
Contract Working Days150
Addl Days Granted0
Working Days Charged100
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06131141
Totals100000.000.0097002.0097.0

CountyANGELINA
HighwayBU0059
From1805 N. TIMBERLAND DR.
ToLUFKIN, TX
CSJ6261-53-001
Proj IDSUP - 626153001
Work TypeGROUNDS MAINT AT LUFKIN DIST. COMPLEX
 
0.01025400.0013335.0052.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-01-13
Work Completed
Time Computed07-01-13
Contract Working Days150
Addl Days Granted0
Working Days Charged21
Percent Time Used14
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06131132
Totals25400.000.0013335.0052.5

CountyANGELINA
HighwayUS0069
FromLOCATED WITHIN THE LUFKIN STATE
ToSUPPORTED LIVING CENTER ON US 69
CSJ6273-13-001
Proj IDRMC - 627313001
Work TypeSEAL COAT, REHAB & MISC. CONSTRUCTION
 
0.010164328.00157822.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-17-15
Work Completed09-21-15
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged24
Percent Time Used60
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151104
Totals164328.000.00157822.00100.0

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS WITHIN
ToSHELBY COUNTY
CSJ6275-22-001
Proj IDSUP - 627522001
Work TypeMAILBOX AND DELINEATOR MAINTENANCE
 
0.0100.0056420.130.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-14
Work Began07-01-14
Work Completed06-30-15
Time Computed07-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged343
Percent Time Used93
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141139
Totals0.000.0056420.130.0

CountySHELBY
HighwayFM0414
From0.89 MILES NORTHEAST OF SH 87 ON THE
ToSOUTH SIDE OF FM 414
CSJ6301-55-001
Proj IDRMC - 630155001
Work TypeCULVERT INSTALLATION
 
0.010109175.00120789.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began07-26-16
Work Completed01-31-17
Time Computed07-18-16
Contract Working Days25
Addl Days Granted0
Working Days Charged25
Percent Time Used100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161101
Totals109175.000.00120789.00100.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN THE SAN JACINTO
ToCOUNTY MAINTENANCE SECTION
CSJ6318-77-001
Proj IDRMC - 631877001
Work TypeCULVERT AND DITCH CLEANING
 
0.010222810.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&S EXCAVATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171107
Totals222810.000.000.000.0

CountyTRINITY
HighwaySH0094
FromVARIOUS LOCATIONS IN TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6318-79-001
Proj IDRMC - 631879001
Work TypeDITCH CLEANING
 
0.010236475.000.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-18
Work Began00-00-00
Work Completed02-15-19
Time Computed11-05-18
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&S EXCAVATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171109
Totals236475.000.000.00100.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN THE SAN JACINTO
ToMAINTENANCE SECTION
CSJ6327-67-001
Proj IDRMC - 632767001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010176695.00130402.5073.8
Work Order09-18-18
Work Began09-18-18
Work Completed
Time Computed09-18-18
Contract Working Days365
Addl Days Granted386
Working Days Charged750
Percent Time Used99
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6327-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07181105
Totals176695.000.00130402.5073.8

CountyHOUSTON
HighwayUS0287
FromHOUSTON COUNTY
ToVARIOUS ROADWAYS
CSJ6330-11-001
Proj IDRMC - 633011001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVL
 
0.010180381.34180376.5099.9
Work Order06-01-20
Work Began06-01-20
Work Completed
Time Computed06-01-20
Contract Working Days52
Addl Days Granted52
Working Days Charged55
Percent Time Used52
Contractor(s)
DON YATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02201101
Totals180381.340.00180376.5099.9

CountySHELBY
HighwaySH0087
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6331-45-001
Proj IDRMC - 633145001
Work TypeDITCH AND CULVERT CLEANING
 
0.010169450.00159651.2094.2
Work Order02-18-20
Work Began03-16-20
Work Completed
Time Computed03-16-20
Contract Working Days45
Addl Days Granted45
Working Days Charged34
Percent Time Used37
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6331-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08181107
Totals169450.000.00159651.2094.2

CountyPOLK
HighwayUS0059
FromVARIOUS ROADWAYS IN THE POLK COUNTY
ToMAINTENACE SECTION
CSJ6340-52-001
Proj IDRMC - 634052001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010259658.80452551.2499.9
Work Order05-15-19
Work Began05-28-19
Work Completed
Time Computed05-28-19
Contract Working Days82
Addl Days Granted82
Working Days Charged194
Percent Time Used118
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6340-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02191110
Totals259658.800.00452551.2499.9

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSABINE COUNTY MAINTENANCE SECTION
CSJ6341-09-001
Proj IDRMC - 634109001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010245711.0098200.0039.9
Work Order05-10-19
Work Began06-01-19
Work Completed
Time Computed06-03-19
Contract Working Days730
Addl Days Granted0
Working Days Charged584
Percent Time Used80
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6341-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03191115
Totals245711.002115.0098200.0039.9

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE SHELBY
ToCOUNTY MAINTENANCE SECTION
CSJ6341-10-001
Proj IDRMC - 634110001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010227285.00366310.0099.9
Work Order04-22-19
Work Began04-29-19
Work Completed
Time Computed04-22-19
Contract Working Days730
Addl Days Granted730
Working Days Charged762
Percent Time Used52
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6341-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03191116
Totals227285.0015995.00366310.0099.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ6341-86-001
Proj IDRMC - 634186001
Work TypeINSTALLATION OF WATERBASE STRIPING
 
0.001262750.00549014.3499.9
Work Order05-01-19
Work Began05-08-19
Work Completed
Time Computed05-08-19
Contract Working Days365
Addl Days Granted485
Working Days Charged785
Percent Time Used92
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6341-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02191109
Totals262750.000.00549014.3499.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICTWIDE
CSJ6343-79-001
Proj IDRMC - 634379001
Work TypeINSTALL SPOT PAINT AND BEAD STRIPING
 
0.001324300.00772364.1699.9
Work Order05-01-19
Work Began05-08-19
Work Completed
Time Computed05-08-19
Contract Working Days365
Addl Days Granted515
Working Days Charged785
Percent Time Used89
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6343-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04191117
Totals324300.0063377.76772364.1699.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9