Monthly Local Let Maintenance Report For Lufkin District As Of Nov 10, 2024 Page 6 Of 6

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6472-89-001
Proj IDSUP - 647289001
Work TypeGROUNDS MAINTENANCE
 
0.01086518.917412.808.5
Work Order09-01-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6472-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241132
Totals86518.917412.807412.808.5

CountyTRINITY
HighwaySH0019
FromTRINITY COUNTY
ToVARIOUS LOCATIONS
CSJ6472-90-001
Proj IDSUP - 647290001
Work TypeSTATE USE CONTRACT
 
0.01053509.824224.027.8
Work Order09-01-24
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6472-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241133
Totals53509.821870.484224.027.8

CountyNACOGDOCHES
HighwayFM0343
FromNACOGDOCHES COUNTY
ToVARIOUS LOCATIONS
CSJ6473-61-001
Proj IDSUP - 647361001
Work TypeSTATE USE CONTRACT
 
0.01048910.004660.009.5
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days396
Addl Days Granted0
Working Days Charged61
Percent Time Used15
Contractor(s)
WORKQUEST
SAUMYA, INC
SUBCONTRACTOR(S) FOR CCSJ: 6473-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241134
Totals48910.001730.004660.009.5

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY
ToVARIOUS LOCATIONS
CSJ6473-62-001
Proj IDSUP - 647362001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.01024200.0018612.0076.9
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days396
Addl Days Granted0
Working Days Charged61
Percent Time Used15
Contractor(s)
WORKQUEST
TEJAS ROADRUNNERS, NON-PROFIT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6473-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241135
Totals24200.007902.0018612.0076.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6473-92-001
Proj IDRMC - 647392001
Work TypeMAINTENANCE OF LARGE SIGNS
 
0.010347200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ODUM SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241106
Totals347200.000.000.000.0

CountyHOUSTON
HighwayFM2022
FromVARIOUS LOCATIONS IN HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6474-08-001
Proj IDRMC - 647408001
Work TypeDITCH CLEANING AND RESHAPING
 
0.010380104.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6474-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241107
Totals380104.920.000.000.0

CountyNACOGDOCHES
HighwayFM0343
FromNACOGDOCHES COUNTY
ToNACOGDOCHES COUNTY
CSJ6474-74-001
Proj IDSUP - 647474001
Work TypeLITTER REMOVAL
 
0.01067525.581486.532.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6474-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241130
Totals67525.581486.531486.532.2

CountySABINE
HighwayFM0083
FromSABINE COUNTY
ToSABINE COUNTY
CSJ6474-75-001
Proj IDSUP - 647475001
Work TypeLITTER REMOVAL
 
0.01072823.542963.834.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6474-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241131
Totals72823.542963.832963.834.0

CountySAN AUGUSTINE
HighwaySH0021
FromSAN AUGUSTINE COUNTY
ToSAN AUGUSTINE COUNTY
CSJ6474-76-001
Proj IDSUP - 647476001
Work TypeLITTER REMOVAL
 
0.010107672.624127.143.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6474-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241132
Totals107672.624127.144127.143.8

CountySAN JACINTO
HighwaySH0150
FromSAN JACINTO COUNTY
ToSAN JACINTO COUNTY
CSJ6474-77-001
Proj IDSUP - 647477001
Work TypeLITTER REMOVAL
 
0.01072418.725629.517.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6474-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241133
Totals72418.725629.515629.517.7

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY
ToSHELBY COUNTY
CSJ6475-99-001
Proj IDSUP - 647599001
Work TypeGROUNDS MAINTENANCE
 
0.010147179.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-24
Work Began00-00-00
Work Completed
Time Computed11-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6475-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241130
Totals147179.910.000.000.0

CountyPOLK
HighwayUS0059
FromPOLK COUNTY
ToPOLK COUNTY
CSJ6476-01-001
Proj IDSUP - 647601001
Work TypeJANITORIAL MAINTENANCE
 
0.01034628.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6476-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241131
Totals34628.520.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6