Monthly Local Let Maintenance Report For Lufkin District As Of Nov 10, 2024 Page 5 Of 6

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySABINE
HighwayUS0096
FromSABINE COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6469-00-001
Proj IDSUP - 646900001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.01099787.5539258.0039.3
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed06-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6469-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05241133
Totals99787.5510810.2039258.0039.3

CountySAN AUGUSTINE
HighwayUS0096
FromSAN AUGUSTINE COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6469-01-001
Proj IDSUP - 646901001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.01058211.750.000.0
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed06-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6469-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05241134
Totals58211.750.000.000.0

CountyHOUSTON
HighwaySL0304
FromLUFKIN AREA MAINTENANCE SECTIONS
ToLUFKIN AREA MAINTENANCE SECTIONS
CSJ6470-34-001
Proj IDMMC - 647034001
Work TypeAGGREGATE
 
0.010243800.000.000.0
Work Order00-00-00
Work Began09-12-24
Work Completed
Time Computed09-12-24
Contract Working Days180
Addl Days Granted0
Working Days Charged50
Percent Time Used27
Contractor(s)
ARCOSA LWS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6470-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241161
Totals243800.000.000.000.0

CountyANGELINA
HighwayBU0069J
FromLUFKIN AREA MAINTENANCE SECTIONS
ToLUFKIN AREA MAINTENANCE SECTIONS
CSJ6470-40-001
Proj IDMMC - 647040001
Work TypeHYDRAULIC CEMENT
 
0.01061098.246944.0011.3
Work Order00-00-00
Work Began08-07-24
Work Completed
Time Computed08-07-24
Contract Working Days180
Addl Days Granted0
Working Days Charged86
Percent Time Used47
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6470-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241162
Totals61098.240.006944.0011.3

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY MAINTENANCE OFFICE
ToSHELBY COUNTY MAINTENANCE OFFICE
CSJ6470-53-001
Proj IDSUP - 647053001
Work TypeJANITORIAL MAINTENANCE
 
0.01016285.726292.2138.6
Work Order06-24-24
Work Began06-24-24
Work Completed
Time Computed06-24-24
Contract Working Days281
Addl Days Granted0
Working Days Charged130
Percent Time Used46
Contractor(s)
WORKQUEST
UNITED RESOURCE GROUP,US
SUBCONTRACTOR(S) FOR CCSJ: 6470-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06241130
Totals16285.721480.526292.2138.6

CountyTRINITY
HighwayUS0287
FromLIVINGSTON AREA MAINTENANCE SECTIONS
ToLIVINGSTON AREA MAINTENANCE SECTIONS
CSJ6470-74-001
Proj IDMMC - 647074001
Work TypeFLEXIBLE BASE
 
0.010203500.0054731.0726.8
Work Order09-19-24
Work Began09-19-24
Work Completed
Time Computed09-19-24
Contract Working Days180
Addl Days Granted0
Working Days Charged43
Percent Time Used23
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6470-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241160
Totals203500.0026715.8654731.0726.8

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6470-90-001
Proj IDRMC - 647090001
Work TypeSPOT PAVEMENT MARKINGS
 
0.010432900.0031808.157.3
Work Order10-28-24
Work Began10-28-24
Work Completed
Time Computed10-28-24
Contract Working Days365
Addl Days Granted0
Working Days Charged4
Percent Time Used1
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6470-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241110
Totals432900.0031808.1531808.157.3

CountyANGELINA
HighwayBU0069J
FromANGELINA COUNTY
ToANGELINA COUNTY
CSJ6471-11-001
Proj IDSUP - 647111001
Work TypeLITTER REMOVAL
 
0.01054192.310.000.0
Work Order00-00-00
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
SAUMYA, INC
SUBCONTRACTOR(S) FOR CCSJ: 6471-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241135
Totals54192.310.000.000.0

CountyANGELINA
HighwayBU0069J
FromANGELINA COUNTY
ToANGELINA COUNTY
CSJ6471-12-001
Proj IDSUP - 647112001
Work TypeGROUNDS MAINTENANCE
 
0.01043268.487620.3017.6
Work Order00-00-00
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6471-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241136
Totals43268.482584.347620.3017.6

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY
ToVARIOUS LOCATIONS
CSJ6471-13-001
Proj IDSUP - 647113001
Work TypeCURB & GUTTER MAINT
 
0.01064219.9215718.5824.4
Work Order00-00-00
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6471-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241137
Totals64219.9215718.5815718.5824.4

CountySABINE
HighwayUS0096
FromSABINE COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6471-14-001
Proj IDSUP - 647114001
Work TypeGROUNDS MAINTENANCE
 
0.01055290.6614374.5125.9
Work Order00-00-00
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6471-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241138
Totals55290.664785.2614374.5125.9

CountySAN AUGUSTINE
HighwayUS0096
FromSAN AUGUSTINE COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6471-15-001
Proj IDSUP - 647115001
Work TypeGROUNDS MAINTENANCE
 
0.01024522.355733.5623.3
Work Order00-00-00
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6471-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07241139
Totals24522.351789.825733.5623.3

CountyANGELINA
HighwayBU0069J
FromDISTRICTWIDE COUNTY MAINTENANCE YARDS
ToDISTRICTWIDE COUNTY MAINTENANCE YARDS
CSJ6471-30-001
Proj IDMMC - 647130001
Work TypeWINTER WEATHER MATERIAL
 
0.01052722.600.000.0
Work Order00-00-00
Work Began10-01-24
Work Completed
Time Computed10-01-24
Contract Working Days240
Addl Days Granted0
Working Days Charged31
Percent Time Used12
Contractor(s)
CLEMENTS FLUIDS HENDERSON, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6471-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241161
Totals52722.600.000.000.0

CountySAN AUGUSTINE
HighwaySH0103
FromSAN AUG COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6471-49-001
Proj IDRMC - 647149001
Work TypeTREE REMOVAL
 
0.010186380.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241111
Totals186380.000.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATION IN THE HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6471-51-001
Proj IDRMC - 647151001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.01097685.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AAD CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241112
Totals97685.000.000.000.0

CountyNACOGDOCHES
HighwaySH0021
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6471-79-001
Proj IDBPM - 647179001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010323160.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6471-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241110
Totals323160.000.000.000.0

CountySAN JACINTO
HighwaySH0150
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6471-80-001
Proj IDBPM - 647180001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010737340.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6471-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241112
Totals737340.000.000.000.0

CountyTRINITY
HighwayUS0287
FromTRINITY COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6471-81-001
Proj IDRMC - 647181001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010173970.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6471-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241109
Totals173970.000.000.000.0

CountyHOUSTON
HighwaySL0304
FromHOUSTON COUNTY
ToVARIOUS LOCATIONS
CSJ6472-87-001
Proj IDSUP - 647287001
Work TypeLITTER REMOVAL
 
0.01063086.392338.363.7
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6472-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241130
Totals63086.392338.362338.363.7

CountyPOLK
HighwayUS0059
FromPOLK COUNTY MAINTENANCE YARD
ToPOLK COUNTY MAINTENANCE YARD
CSJ6472-88-001
Proj IDSUP - 647288001
Work TypeLITTER REMOVAL
 
0.010101050.436969.326.8
Work Order00-00-00
Work Began09-01-24
Work Completed
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6472-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08241131
Totals101050.434834.546969.326.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6