Monthly Local Let Maintenance Report For Odessa District As Of Jul 13, 2021 Page 1 Of 5

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyECTOR
HighwayLP0338
FromODESSA MAINTENANCE OFFICE
ToODESSA MAINTENANCE OFFICE
CSJ6173-64-001
Proj IDSUP - 617364001
Work TypeGROUNDS MAINTENANCE
 
0.0017717.506615.0085.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-26-08
Work Began03-11-08
Work Completed
Time Computed03-01-08
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6173-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01080631
Totals7717.500.006615.0085.7

CountyMARTIN
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6197-11-001
Proj IDRMC - 619711001
Work TypeROADSIDE MOWING
 
234.30083691.9668030.0781.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-10
Work Began06-09-10
Work Completed
Time Computed06-09-10
Contract Working Days56
Addl Days Granted0
Working Days Charged19
Percent Time Used33
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6197-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01100606
Totals83691.960.0068030.0781.2

CountyWINKLER
HighwaySH0302
FromVARIOUS
ToVARIOUS
CSJ6234-97-001
Proj IDRMC - 623497001
Work TypeROADSIDE MOWING
 
0.00146995.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KRAFT WERKS
SUBCONTRACTOR(S) FOR CCSJ: 6234-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05120601
Totals46995.260.000.000.0

CountyWARD
HighwayBI0020D
FromVARIOUS
ToVARIOUS
CSJ6297-63-001
Proj IDRMC - 629763001
Work TypeRETROREFLECTIVITY MEASUREMENT
 
0.00121323.8721323.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began05-16-16
Work Completed01-31-17
Time Computed05-16-16
Contract Working Days60
Addl Days Granted0
Working Days Charged59
Percent Time Used98
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160602
Totals21323.870.0021323.88100.0

CountyANDREWS
HighwayUS0385
FromVARIOUS
ToVARIOUS
CSJ6319-44-001
Proj IDRMC - 631944001
Work TypeLANDSCAPE MAINTENANCE
 
0.00159200.0096200.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-21-17
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted731
Working Days Charged1,338
Percent Time Used91
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6319-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170601
Totals59200.001480.0096200.0099.9

CountyREEVES
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6324-69-001
Proj IDRMC - 632469001
Work TypeROADSIDE MOWING
 
0.001220688.00354284.0099.9
Work Order02-01-18
Work Began06-20-18
Work Completed
Time Computed02-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,246
Percent Time Used85
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180601
Totals220688.0019996.00354284.0099.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6324-70-001
Proj IDRMC - 632470001
Work TypeROADSIDE MOWING
 
0.001297328.00435906.0099.9
Work Order03-01-18
Work Began07-02-18
Work Completed
Time Computed03-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,218
Percent Time Used83
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180602
Totals297328.000.00435906.0099.9

CountyMARTIN
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6324-71-001
Proj IDRMC - 632471001
Work TypeROADSIDE MOWING
 
0.001198528.00339264.0099.9
Work Order03-09-18
Work Began06-12-18
Work Completed
Time Computed04-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,187
Percent Time Used81
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180603
Totals198528.0038592.00339264.0099.9

CountyWARD
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6324-73-001
Proj IDRMC - 632473001
Work TypeROADSIDE MOWING
 
0.001258680.00439118.4999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-15-18
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted731
Working Days Charged1,157
Percent Time Used79
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180605
Totals258680.0053429.40439118.4999.9

CountyANDREWS
HighwayUS0385
FromVARIOUS
ToVARIOUS
CSJ6324-74-001
Proj IDRMC - 632474001
Work TypeROADSIDE MOWING
 
0.001181272.00277515.3099.9
Work Order03-09-18
Work Began06-05-18
Work Completed
Time Computed03-09-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,210
Percent Time Used82
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180606
Totals181272.000.00277515.3099.9

CountyREEVES
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6324-75-001
Proj IDRMC - 632475001
Work TypeROADSIDE MOWING
 
0.001286858.00471005.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-24-18
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted731
Working Days Charged1,187
Percent Time Used81
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180607
Totals286858.0056239.40471005.4099.9

CountyTERRELL
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6324-77-001
Proj IDRMC - 632477001
Work TypeROADSIDE MOWING
 
0.001183549.60261784.4099.9
Work Order03-26-18
Work Began08-03-18
Work Completed
Time Computed04-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,187
Percent Time Used81
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180608
Totals183549.600.00261784.4099.9

CountyTERRELL
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6326-53-001
Proj IDRMC - 632653001
Work TypePICNIC AREA MAINTENANCE
 
0.00198560.00159405.0099.9
Work Order02-01-18
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,246
Percent Time Used85
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6326-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180609
Totals98560.003760.00159405.0099.9

CountyWINKLER
HighwaySH0302
FromVARIOUS
ToVARIOUS
CSJ6327-61-001
Proj IDRMC - 632761001
Work TypeROADSIDE MOWING
 
0.001172028.00336371.0099.9
Work Order05-07-18
Work Began05-15-18
Work Completed
Time Computed05-21-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,157
Percent Time Used79
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6327-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02180601
Totals172028.000.00336371.0099.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6328-52-001
Proj IDRMC - 632852001
Work TypeLANDSCAPE MAINTENANCE
 
0.00183008.40102021.6599.9
Work Order05-22-18
Work Began06-01-18
Work Completed
Time Computed07-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,126
Percent Time Used77
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6328-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04180602
Totals83008.402815.05102021.6599.9

CountyMIDLAND
HighwayBI0020E
FromVARIOUS
ToVARIOUS
CSJ6329-50-001
Proj IDRMC - 632950001
Work TypePUMP STATION MAINTENANCE
 
0.001200204.00335296.0099.9
Work Order06-01-18
Work Began12-10-18
Work Completed
Time Computed06-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,126
Percent Time Used77
Contractor(s)
E.V.G. ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6329-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04180603
Totals200204.000.00335296.0099.9

CountyCRANE
HighwayUS0385
FromVARIOUS
ToVARIOUS
CSJ6334-10-001
Proj IDRMC - 633410001
Work TypeROADSIDE MOWING
 
0.001154744.00178876.5099.9
Work Order09-26-18
Work Began11-12-18
Work Completed
Time Computed10-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,004
Percent Time Used68
Contractor(s)
ABESCAPE GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 6334-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08180602
Totals154744.000.00178876.5099.9

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6338-70-001
Proj IDRMC - 633870001
Work TypeCULVERT CLEANING
 
0.00179660.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AAA SWEEPING SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03190601
Totals79660.000.000.000.0

CountyMIDLAND
HighwayBI0020E
FromVARIOUS
ToVARIOUS
CSJ6341-49-001
Proj IDRMC - 634149001
Work TypeINSTALL RAISED PAVEMENT MARKINGS(CALLOUT
 
0.001172364.11231458.5599.9
Work Order08-01-19
Work Began01-20-20
Work Completed
Time Computed08-01-19
Contract Working Days366
Addl Days Granted365
Working Days Charged700
Percent Time Used95
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6341-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01190605
Totals172364.11134940.53231458.5599.9

CountyPECOS
HighwayUS0285
FromVARIOUS
ToVARIOUS
CSJ6341-50-001
Proj IDRMC - 634150001
Work TypeINSTALL RAISED PAV MARKINGS(CALLOUT)
 
0.001169004.8438436.4522.7
Work Order06-01-19
Work Began11-04-19
Work Completed
Time Computed06-01-19
Contract Working Days366
Addl Days Granted366
Working Days Charged730
Percent Time Used99
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6341-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01190604
Totals169004.840.0038436.4522.7

page 1 | page 2 | page 3 | page 4 | page 5