Monthly Local Let Maintenance Report For Odessa District As Of Nov 10, 2024 Page 4 Of 5

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6464-30-001
Proj IDSUP - 646430001
Work TypeLITTER REMOVAL
 
0.010400771.80239373.5559.7
Work Order03-22-24
Work Began04-15-24
Work Completed
Time Computed04-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
WORKQUEST
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6464-30-001
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED (0.00)
Contract #02240633
Totals400771.8039475.15239373.5559.7

CountyWINKLER
HighwaySH0302
FromVARIOUS
ToVARIOUS
CSJ6464-44-001
Proj IDSUP - 646444001
Work TypeLITTER REMOVAL
 
0.010277769.2697818.7635.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-06-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
WORKQUEST
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6464-44-001
WORK SERVICES CORPORATION (0.00)
Contract #03240632
Totals277769.2611135.0097818.7635.2

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6465-07-001
Proj IDSUP - 646507001
Work TypeLITTER REMOVAL
 
0.010517511.32179955.2034.7
Work Order04-01-24
Work Began04-01-24
Work Completed
Time Computed04-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-07-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #03240633
Totals517511.3245352.68179955.2034.7

CountyPECOS
HighwayBI0010G
FromVARIOUS
ToVARIOUS
CSJ6465-28-001
Proj IDMMC - 646528001
Work TypeFLEXIBLE BASE
 
0.01056000.0030857.6055.1
Work Order07-01-24
Work Began07-01-24
Work Completed
Time Computed07-01-24
Contract Working Days120
Addl Days Granted120
Working Days Charged123
Percent Time Used51
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6465-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05240601
Totals56000.000.0030857.6055.1

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6465-29-001
Proj IDMMC - 646529001
Work TypeFLEXIBLE BASE
 
0.01033000.0043409.0599.9
Work Order05-24-24
Work Began06-06-24
Work Completed
Time Computed06-01-24
Contract Working Days120
Addl Days Granted120
Working Days Charged152
Percent Time Used63
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6465-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04240601
Totals33000.000.0043409.0599.9

CountyECTOR
HighwaySL0338
FromVARIOUS
ToVARIOUS
CSJ6465-30-001
Proj IDMMC - 646530001
Work TypeFLEXIBLE BASE
 
0.01033000.0016294.7849.3
Work Order06-25-24
Work Began07-01-24
Work Completed
Time Computed07-01-24
Contract Working Days120
Addl Days Granted120
Working Days Charged123
Percent Time Used51
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6465-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04240602
Totals33000.000.0016294.7849.3

CountyMIDLAND
HighwayBI0020E
FromVARIOUS
ToVARIOUS
CSJ6465-50-001
Proj IDSUP - 646550001
Work TypeLANDSCAPE MAINTENANCE
 
0.010256244.0091245.4535.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-11-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6465-50-001
RELIEF ENTERPRISES (0.00)
Contract #04240631
Totals256244.0018358.0091245.4535.6

CountyMIDLAND
HighwaySL0250
FromVARIOUS
ToVARIOUS
CSJ6465-51-001
Proj IDSUP - 646551001
Work TypeLANDSCAPE MAINTENANCE
 
0.010274672.65128098.5146.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-03-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6465-51-001
RELIEF ENTERPRISES (0.00)
Contract #04240632
Totals274672.6536044.46128098.5146.6

CountyPECOS
HighwayBI0010G
FromVARIOUS
ToVARIOUS
CSJ6465-57-001
Proj IDMMC - 646557001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010100700.0022968.1222.8
Work Order08-01-24
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days120
Addl Days Granted0
Working Days Charged92
Percent Time Used76
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05240602
Totals100700.000.0022968.1222.8

CountyECTOR
HighwaySL0338
FromVARIOUS
ToVARIOUS
CSJ6465-58-001
Proj IDMMC - 646558001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010160200.00167296.6299.9
Work Order07-11-24
Work Began07-12-24
Work Completed
Time Computed07-11-24
Contract Working Days120
Addl Days Granted0
Working Days Charged114
Percent Time Used95
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05240603
Totals160200.000.00167296.6299.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6466-40-001
Proj IDSUP - 646640001
Work TypePICNIC AREA MAINTENANCE
 
0.01097456.9236932.6637.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-03-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6466-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04240633
Totals97456.926728.3036932.6637.8

CountyMIDLAND
HighwayIH0020
FromMM 140
ToMM 142
CSJ6466-78-001
Proj IDSUP - 646678001
Work TypePICNIC AREA MAINTENANCE
 
0.01040923.3010291.8025.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
WORKQUEST
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6466-78-001
RELIEF ENTERPRISES (0.00)
Contract #05240631
Totals40923.303201.9010291.8025.1

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6468-85-001
Proj IDRMC - 646885001
Work TypeCRACK SEAL
 
0.010370358.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days37
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6468-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08240601
Totals370358.600.000.000.0

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6468-86-001
Proj IDRMC - 646886001
Work TypeCRACK SEAL
 
0.010565230.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-05-24
Work Began00-00-00
Work Completed
Time Computed11-05-24
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6468-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08240602
Totals565230.000.000.000.0

CountyPECOS
HighwayBI0010G
FromVARIOUS
ToVARIOUS
CSJ6468-92-001
Proj IDRMC - 646892001
Work TypeCRACK SEAL
 
0.010259484.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6468-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08240603
Totals259484.000.000.000.0

CountyPECOS
HighwayBI0010G
FromVARIOUS
ToVARIOUS
CSJ6468-93-001
Proj IDMMC - 646893001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010137504.00488157.7599.9
Work Order07-17-24
Work Began07-18-24
Work Completed
Time Computed07-17-24
Contract Working Days120
Addl Days Granted0
Working Days Charged107
Percent Time Used89
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6468-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06240601
Totals137504.00213366.59488157.7599.9

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6468-94-001
Proj IDMMC - 646894001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010247596.00324159.6799.9
Work Order07-08-24
Work Began07-08-24
Work Completed
Time Computed07-08-24
Contract Working Days120
Addl Days Granted120
Working Days Charged116
Percent Time Used48
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6468-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06240602
Totals247596.0018791.67324159.6799.9

CountyECTOR
HighwaySL0338
FromVARIOUS
ToVARIOUS
CSJ6468-95-001
Proj IDMMC - 646895001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010213783.00149058.6969.7
Work Order07-10-24
Work Began08-01-24
Work Completed
Time Computed08-01-24
Contract Working Days120
Addl Days Granted0
Working Days Charged92
Percent Time Used76
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6468-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06240603
Totals213783.0041101.47149058.6969.7

CountyPECOS
HighwayBI0010G
FromVARIOUS
ToVARIOUS
CSJ6469-56-001
Proj IDMMC - 646956001
Work TypeAGGREGATE
 
0.01047500.0057890.0099.9
Work Order08-12-24
Work Began08-12-24
Work Completed
Time Computed08-12-24
Contract Working Days120
Addl Days Granted0
Working Days Charged81
Percent Time Used67
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6469-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07240601
Totals47500.000.0057890.0099.9

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6469-57-001
Proj IDMMC - 646957001
Work TypeAGGREGATE
 
0.01052500.0036089.0068.7
Work Order08-14-24
Work Began08-14-24
Work Completed
Time Computed08-14-24
Contract Working Days120
Addl Days Granted0
Working Days Charged79
Percent Time Used65
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6469-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07240602
Totals52500.000.0036089.0068.7

page 1 | page 2 | page 3 | page 4 | page 5