Monthly Local Let Maintenance Report For Odessa District As Of Nov 10, 2024 Page 5 Of 5

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyECTOR
HighwaySL0338
FromVARIOUS
ToVARIOUS
CSJ6469-58-001
Proj IDMMC - 646958001
Work TypeAGGREGATE
 
0.01028750.0028210.2898.1
Work Order09-18-24
Work Began09-26-24
Work Completed
Time Computed09-24-24
Contract Working Days120
Addl Days Granted0
Working Days Charged38
Percent Time Used31
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6469-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08240604
Totals28750.000.0028210.2898.1

CountyECTOR
HighwayBI0020E
FromDISTRICT COMPLEX
ToDISTRICT COMPLEX
CSJ6470-75-001
Proj IDMMC - 647075001
Work TypePAINT AND BEADS
 
0.010133272.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6470-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08240605
Totals133272.000.000.000.0

CountyPECOS
HighwayFM1776
FromVARIOUS
ToVARIOUS
CSJ6471-84-001
Proj IDRMC - 647184001
Work TypePAINT
 
0.010269292.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAFFIC HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6471-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09240601
Totals269292.920.000.000.0

CountyPECOS
HighwayBI0010G
FromVARIOUS
ToVARIOUS
CSJ6472-35-001
Proj IDMMC - 647235001
Work TypeWINTER WEATHER MATERIAL
 
0.01029100.000.000.0
Work Order10-09-24
Work Began00-00-00
Work Completed
Time Computed10-09-24
Contract Working Days240
Addl Days Granted0
Working Days Charged23
Percent Time Used9
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6472-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09240602
Totals29100.000.000.000.0

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6472-36-001
Proj IDMMC - 647236001
Work TypeWINTER WEATHER MATERIAL
 
0.01023000.000.000.0
Work Order10-07-24
Work Began00-00-00
Work Completed
Time Computed10-07-24
Contract Working Days240
Addl Days Granted0
Working Days Charged25
Percent Time Used10
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6472-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09240603
Totals23000.000.000.000.0

CountyECTOR
HighwaySL0338
FromVARIOUS
ToVARIOUS
CSJ6472-37-001
Proj IDMMC - 647237001
Work TypeWINTER WEATHER MATERIAL
 
0.01023000.000.000.0
Work Order10-07-24
Work Began00-00-00
Work Completed
Time Computed10-07-24
Contract Working Days240
Addl Days Granted0
Working Days Charged25
Percent Time Used10
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6472-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09240604
Totals23000.000.000.000.0

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6472-39-001
Proj IDMMC - 647239001
Work TypeEMULSION
 
0.01095880.000.000.0
Work Order10-17-24
Work Began00-00-00
Work Completed
Time Computed10-17-24
Contract Working Days120
Addl Days Granted0
Working Days Charged15
Percent Time Used12
Contractor(s)
WRIGHT ASPHALT PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6472-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09240605
Totals95880.000.000.000.0

CountyECTOR
HighwaySL0338
FromVARIOUS
ToVARIOUS
CSJ6472-40-001
Proj IDMMC - 647240001
Work TypeEMULSION
 
0.01062580.000.000.0
Work Order10-16-24
Work Began00-00-00
Work Completed
Time Computed10-17-24
Contract Working Days120
Addl Days Granted0
Working Days Charged15
Percent Time Used12
Contractor(s)
WRIGHT ASPHALT PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6472-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09240606
Totals62580.000.000.000.0

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6473-83-001
Proj IDRMC - 647383001
Work TypeCABLE MEDIAN BARRIER SYSTEM REPAIR
 
0.010363685.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10240604
Totals363685.000.000.000.0

CountyPECOS
HighwayBI0010G
FromVARIOUS
ToVARIOUS
CSJ6473-84-001
Proj IDMMC - 647384001
Work TypeWINTER WEATHER MATERIAL
 
0.010200913.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10240601
Totals200913.000.000.000.0

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6473-86-001
Proj IDRMC - 647386001
Work TypeCABLE MEDIAN BARRIER SYSTEM REPAIR
 
0.010463943.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-05-24
Work Began00-00-00
Work Completed
Time Computed12-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10240605
Totals463943.000.000.000.0

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6473-87-001
Proj IDMMC - 647387001
Work TypeWINTER WEATHER MATERIAL
 
0.010160726.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10240602
Totals160726.500.000.000.0

CountyECTOR
HighwaySL0338
FromVARIOUS
ToVARIOUS
CSJ6473-88-001
Proj IDMMC - 647388001
Work TypeWINTER WEATHER MATERIAL
 
0.010120129.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10240603
Totals120129.000.000.000.0

CountyWINKLER
HighwaySH0115
FromVARIOUS
ToVARIOUS
CSJ6473-89-001
Proj IDRMC - 647389001
Work TypeCUTBACK
 
0.010313830.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-04-24
Work Began00-00-00
Work Completed
Time Computed11-11-24
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SKIDABRADER GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09240607
Totals313830.400.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5