|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HENDERSON |
Highway | 0000000 |
From | 2400 NE LOOP 317, ATHENS, HENDERSON CO |
To | TEXAS 75752 |
CSJ | 4704-01-343 |
Proj ID | CBC - 470401343 |
Work Type | RENOVATION OR REPAIR |
|
| 0.001 | 596334.00 | | 538073.10 | 100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | 01-01-16 |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 199 |
Percent Time Used | 165 |
Contractor(s) |
CENTURION INDUSTRIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-343 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07144218 |
| Totals | 596334.00 | 0.00 | 538073.10 | 100.0 |
|
County | SMITH |
Highway | 0000000 |
From | 2907 WEST FRONT, TYLER, TX 75702 |
To | 2907 WEST FRONT, TYLER, TX 75702 |
CSJ | 4704-01-428 |
Proj ID | CBC - 470401428 |
Work Type | RENOVATION OR REPAIR |
|
| 0.001 | 898100.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 210 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
HCI GENERAL CONTRACTORS |
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-428 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02164220 |
| Totals | 898100.00 | 0.00 | 0.00 | 0.0 |
|
County | SMITH |
Highway | 0000000 |
From | 2709 W. FRONT STREET, TYLER, TX. 75702 |
To | 2709 W. FRONT STREET, TYLER, TX. 75702 |
CSJ | 4704-01-503 |
Proj ID | CBC - 470401503 |
Work Type | RENOVATION OR REPAIR |
|
| 0.001 | 353750.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
VALCORP ENTERPRISES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-503 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06164212 |
| Totals | 353750.00 | 0.00 | 0.00 | 0.0 |
|
County | SMITH |
Highway | US0069 |
From | VARIOUS ROADWAYS IN THE TYLER DISTRICT |
To | TO INCLUDE SEALCOAT ROADS |
CSJ | 6241-15-001 |
Proj ID | RMC - 624115001 |
Work Type | SL THERMO AND RAISED PAVEMENT MARKERS |
|
| 0.010 | 413930.54 | | 379811.06 | 91.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-27-12 |
Work Began | 08-20-12 |
Work Completed | |
Time Computed | 07-11-12 |
Contract Working Days | 255 |
Addl Days Granted | 0 |
Working Days Charged | 223 |
Percent Time Used | 87 |
Contractor(s) |
HIGHWAY TECHNOLOGIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6241-15-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05124003 |
| Totals | 413930.54 | 0.00 | 379811.06 | 91.7 |
|
County | VAN ZANDT |
Highway | SH0019 |
From | VAN ZANDT COUNTY, ETC |
To | DISTRICT WIDE |
CSJ | 6255-21-001 |
Proj ID | RMC - 625521001 |
Work Type | RESURFACING |
|
| 0.100 | 858848.60 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 85 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6255-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05134013 |
| Totals | 858848.60 | 0.00 | 0.00 | 0.0 |
|
County | HENDERSON |
Highway | SH0019 |
From | VARIOUS LOCATIONS IN THE |
To | TYLER DISTRICT |
CSJ | 6279-02-001 |
Proj ID | RMC - 627902001 |
Work Type | CRACKSEAL - HOT POUR |
|
| 756.230 | 385408.61 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 80 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TEXAS ROAD MAINTENANCE |
SUBCONTRACTOR(S) FOR CCSJ: 6279-02-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06154004 |
| Totals | 385408.61 | 0.00 | 0.00 | 0.0 |
|
County | RUSK |
Highway | SH0042 |
From | VARIOUS ROADWAYS |
To | IN RUSK COUNTY |
CSJ | 6349-71-001 |
Proj ID | RMC - 634971001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 489250.00 | | 1425342.55 | 100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-11-20 |
Work Completed | 10-29-24 |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 850 |
Working Days Charged | 1,572 |
Percent Time Used | 99 |
Contractor(s) |
DREWERY CONSTRUCTION COMPANY, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6349-71-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02204008 |
| Totals | 489250.00 | 79629.40 | 1425342.55 | 100.0 |
|
County | HENDERSON |
Highway | SH0031 |
From | VARIOUS LOCATIONS IS |
To | HENDERSON & ANDERSON COUNTIES |
CSJ | 6359-35-001 |
Proj ID | RMC - 635935001 |
Work Type | TRAFFIC CONTROL |
|
| 0.010 | 880357.94 | | 2167687.03 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-20 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 850 |
Working Days Charged | 1,520 |
Percent Time Used | 96 |
Contractor(s) |
AREA WIDE PROTECTIVE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6359-35-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05204223 |
| Totals | 880357.94 | 73935.91 | 2167687.03 | 99.9 |
|
County | SMITH |
Highway | US0069 |
From | VARIOUS LOCATIONS IN |
To | SMITH & CHEROKEE COUNTIES |
CSJ | 6359-37-001 |
Proj ID | RMC - 635937001 |
Work Type | TRAFFIC CONTROL |
|
| 0.010 | 832200.00 | | 2861840.10 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-20 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 850 |
Working Days Charged | 1,516 |
Percent Time Used | 95 |
Contractor(s) |
FIREMAN EXCAVATING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6359-37-001 L & M MOWING CONTRACTORS, LLC (268.16)
|
Contract # | 05204023 |
| Totals | 832200.00 | 83407.83 | 2861840.10 | 99.9 |
|
County | GREGG |
Highway | SH0031 |
From | VARIOUS LOCATIONS IN |
To | GREGG & RUSK COUNTIES |
CSJ | 6359-38-001 |
Proj ID | RMC - 635938001 |
Work Type | TRAFFIC CONTROL |
|
| 0.010 | 1028550.43 | | 2790763.44 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-28-20 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 820 |
Working Days Charged | 1,493 |
Percent Time Used | 96 |
Contractor(s) |
AREA WIDE PROTECTIVE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6359-38-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05204222 |
| Totals | 1028550.43 | 62297.76 | 2790763.44 | 99.9 |
|
County | HENDERSON |
Highway | US0175 |
From | VARIOUS ROADWAYS IN |
To | HENDERSON COUNTY |
CSJ | 6372-91-001 |
Proj ID | RMC - 637291001 |
Work Type | ROW MOWING |
|
| 0.010 | 700709.08 | | 1497997.94 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-06-21 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 114 |
Addl Days Granted | 119 |
Working Days Charged | 224 |
Percent Time Used | 96 |
Contractor(s) |
CROSS PLUS CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6372-91-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12204021 |
| Totals | 700709.08 | 170090.25 | 1497997.94 | 99.9 |
|
County | VAN ZANDT |
Highway | SH0019 |
From | VARIOUS ROADWAYS IN |
To | VAN ZANDT COUNTY |
CSJ | 6372-92-001 |
Proj ID | RMC - 637292001 |
Work Type | ROW MOWING |
|
| 0.010 | 517662.52 | | 1115569.81 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-21 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 98 |
Addl Days Granted | 98 |
Working Days Charged | 187 |
Percent Time Used | 95 |
Contractor(s) |
SERNA CONTRACTORS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6372-92-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12204022 |
| Totals | 517662.52 | 121878.94 | 1115569.81 | 99.9 |
|
County | HENDERSON |
Highway | SH0031 |
From | VARIOUS ROADWAYS IN HENDERSON CO. |
To | ATHENS MAINTENANCE SECTION |
CSJ | 6382-94-001 |
Proj ID | RMC - 638294001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 485500.00 | | 460668.00 | 94.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 1,029 |
Percent Time Used | 70 |
Contractor(s) |
PATTERSON'S COMPLETE TREE SERVICE LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6382-94-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08214015 |
| Totals | 485500.00 | 18654.00 | 460668.00 | 94.8 |
|
County | CHEROKEE |
Highway | US0069 |
From | VARIOUS ROADWAYS |
To | IN CHEROKEE COUNTY |
CSJ | 6392-51-001 |
Proj ID | RMC - 639251001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 454736.86 | | 660005.66 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 102 |
Addl Days Granted | 102 |
Working Days Charged | 141 |
Percent Time Used | 69 |
Contractor(s) |
S G COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6392-51-001 REAGAN"S ENVIRONMENTAL SERVICES & LAWN CARE (10.27)
|
Contract # | 12214019 |
| Totals | 454736.86 | 64153.78 | 660005.66 | 99.9 |
|
County | ANDERSON |
Highway | US0079 |
From | VARIOUS ROADWAYS |
To | IN ANDERSON COUNTY |
CSJ | 6392-52-001 |
Proj ID | RMC - 639252001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 604286.56 | | 794380.02 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 98 |
Addl Days Granted | 98 |
Working Days Charged | 157 |
Percent Time Used | 80 |
Contractor(s) |
S G COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6392-52-001 REAGAN"S ENVIRONMENTAL SERVICES & LAWN CARE (4.77)
|
Contract # | 12214018 |
| Totals | 604286.56 | 68579.75 | 794380.02 | 99.9 |
|
County | ANDERSON |
Highway | SH0019 |
From | VARIOUS ROADWAYS |
To | IN ANDERSON COUNTY |
CSJ | 6396-67-001 |
Proj ID | RMC - 639667001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 352983.43 | | 497687.20 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-16-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 617 |
Percent Time Used | 84 |
Contractor(s) |
ROAD SOLUTIONS L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 6396-67-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03224220 |
| Totals | 352983.43 | 48297.00 | 497687.20 | 99.9 |
|
County | WOOD |
Highway | US0080 |
From | VARIOUS LOCATIONS IN |
To | THE TYLER DISTRICT |
CSJ | 6399-79-001 |
Proj ID | BPM - 639979001 |
Work Type | CONCRETE SPALL REPAIR |
|
| 0.010 | 320000.00 | | 1372862.94 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 705 |
Percent Time Used | 96 |
Contractor(s) |
RED BARON BUILDING COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6399-79-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09224031 |
| Totals | 320000.00 | 8080.00 | 1372862.94 | 99.9 |
|
County | GREGG |
Highway | US0080 |
From | VARIOUS LOCATIONS IN GREGG COUNTY |
To | AND RUSK COUNTY |
CSJ | 6400-24-001 |
Proj ID | RMC - 640024001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 695329.00 | | 615369.00 | 88.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-08-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 717 |
Percent Time Used | 98 |
Contractor(s) |
T&L CLEANING SERVICES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6400-24-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06224013 |
| Totals | 695329.00 | 12465.00 | 615369.00 | 88.5 |
|
County | WOOD |
Highway | US0080 |
From | VARIOUS LOCATIONS IN WOOD COUNTY |
To | AND VAN ZANDT COUNTY |
CSJ | 6400-26-001 |
Proj ID | RMC - 640026001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 449833.00 | | 319569.75 | 71.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-16-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 745 |
Percent Time Used | 51 |
Contractor(s) |
CATOCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6400-26-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06224014 |
| Totals | 449833.00 | 64297.00 | 319569.75 | 71.0 |
|
County | SMITH |
Highway | US0069 |
From | VARIOUS LOCATION IN SMITH COUNTY |
To | AND CHEROKEE COUNTY |
CSJ | 6400-47-001 |
Proj ID | RMC - 640047001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 517456.00 | | 321570.45 | 62.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 711 |
Percent Time Used | 97 |
Contractor(s) |
CATOCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6400-47-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06224015 |
| Totals | 517456.00 | 9720.00 | 321570.45 | 62.1 |
|