Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | SMITH |
Highway | US0069 |
From | VARIOUS LOCATIONS IN |
To | THE TYLER DISTRICT |
CSJ | 6420-81-001 |
Proj ID | RMC - 642081001 |
Work Type | TRAFFIC SIGNAL MAINTENANCE |
|
| 0.010 | 832600.00 | | 303553.00 | 36.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-17-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 562 |
Percent Time Used | 76 |
Contractor(s) |
TEXAS TRAFFIC CONTROL SYSTEMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6420-81-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11224212 |
| Totals | 832600.00 | 2522.00 | 303553.00 | 36.4 |
|
County | SMITH |
Highway | SH0031 |
From | VARIOUS LOCATIONS IN |
To | THE TYLER DISTRICT |
CSJ | 6420-89-001 |
Proj ID | RMC - 642089001 |
Work Type | LARGE SIGN REPLACEMENT |
|
| 0.010 | 577920.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-30-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 183 |
Percent Time Used | 25 |
Contractor(s) |
CROSS PLUS CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6420-89-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234035 |
| Totals | 577920.00 | 0.00 | 0.00 | 0.0 |
|
County | WOOD |
Highway | US0080 |
From | VARIOUS ROADWAYS IN |
To | WOOD AND VAN ZANDT COUNTIES |
CSJ | 6422-44-001 |
Proj ID | RMC - 642244001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 1979844.70 | | 2044417.35 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-23-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 646 |
Percent Time Used | 88 |
Contractor(s) |
SOUTH TEXAS ILLUMINATION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6422-44-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11224213 |
| Totals | 1979844.70 | 114088.80 | 2044417.35 | 99.9 |
|
County | CHEROKEE |
Highway | US0069 |
From | VARIOUS ROADWAYS IN |
To | CHEROKEE COUNTY |
CSJ | 6423-17-001 |
Proj ID | RMC - 642317001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 623618.00 | | 248288.00 | 39.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-04-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 536 |
Percent Time Used | 73 |
Contractor(s) |
S G COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6423-17-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12224025 |
| Totals | 623618.00 | 0.00 | 248288.00 | 39.8 |
|
County | SMITH |
Highway | US0271 |
From | VARIOUS ROADWAYS IN |
To | SMITH COUNTY |
CSJ | 6423-24-001 |
Proj ID | RMC - 642324001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 898125.48 | | 792145.82 | 88.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 102 |
Addl Days Granted | 120 |
Working Days Charged | 69 |
Percent Time Used | 31 |
Contractor(s) |
JASCO |
SUBCONTRACTOR(S) FOR CCSJ: 6423-24-001 SERVIN MOWING CONTRACTORS, LLC (100.00)
|
Contract # | 12224026 |
| Totals | 898125.48 | 129659.00 | 792145.82 | 88.1 |
|
County | SMITH |
Highway | US0069 |
From | VARIOUS ROADWAYS IN |
To | SMITH COUNTY |
CSJ | 6426-20-001 |
Proj ID | RMC - 642620001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 586800.00 | | 364285.00 | 62.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 578 |
Percent Time Used | 79 |
Contractor(s) |
PATTERSON'S COMPLETE TREE SERVICE LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6426-20-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12224039 |
| Totals | 586800.00 | 31805.00 | 364285.00 | 62.0 |
|
County | VAN ZANDT |
Highway | US0080 |
From | VARIOUS LOCATIONS IN THE CANTON MTCE |
To | IN VAN ZANDT COUNTY |
CSJ | 6430-96-001 |
Proj ID | MMC - 643096001 |
Work Type | HOT MIX |
|
| 0.010 | 1016100.00 | | 3101966.60 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 552 |
Percent Time Used | 75 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6430-96-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234033 |
| Totals | 1016100.00 | 173858.81 | 3101966.60 | 99.9 |
|
County | RUSK |
Highway | US0259 |
From | HENDERSON MTCE SECTION |
To | RUSK COUNTY |
CSJ | 6430-97-001 |
Proj ID | MMC - 643097001 |
Work Type | HOT MIX |
|
| 0.010 | 1244870.00 | | 4262193.14 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-15-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 522 |
Percent Time Used | 71 |
Contractor(s) |
LONGVIEW ASPHALT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6430-97-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234234 |
| Totals | 1244870.00 | 817789.84 | 4262193.14 | 99.9 |
|
County | GREGG |
Highway | IH0020 |
From | IH 20 THROUGH GREGG, SMITH, AND |
To | VAN ZANDT COUNTIES |
CSJ | 6431-16-001 |
Proj ID | RMC - 643116001 |
Work Type | TOTAL MAINTENANCE |
|
| 0.010 | 4768998.00 | | 3674541.24 | 77.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 425 |
Percent Time Used | 58 |
Contractor(s) |
FIREMAN EXCAVATING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6431-16-001 CATOCON, INC. (1.88) SERVIN MOWING CONTRACTORS, LLC (1.76) STRIPING TECHNOLOGY, L.P. (0.00) CEN-TEX IRRIGATION SYSTEMS, INC. (5.75)
|
Contract # | 05234026 |
| Totals | 4768998.00 | 402682.26 | 3674541.24 | 77.0 |
|
County | GREGG |
Highway | IH0020 |
From | IH 20 THROUGH GREGG, SMITH, AND |
To | VAN ZANDT COUNTIES |
CSJ | 6431-18-001 |
Proj ID | RMC - 643118001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 3321534.69 | | 3232514.54 | 97.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 210 |
Addl Days Granted | 0 |
Working Days Charged | 172 |
Percent Time Used | 81 |
Contractor(s) |
DREWERY CONSTRUCTION COMPANY, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6431-18-001 STRIPING TECHNOLOGY, L.P. (1.72) SURFACE PREPARATION TECHNOLOGIES, LLC (0.34)
|
Contract # | 11234028 |
| Totals | 3321534.69 | 0.00 | 3232514.54 | 97.3 |
|
County | SMITH |
Highway | US0069 |
From | VARIOUS LOCATIONS IN THE TYLER DISTRICT |
To | TYLER DISTRICT |
CSJ | 6431-60-001 |
Proj ID | MMC - 643160001 |
Work Type | HOT MIX |
|
| 0.010 | 2527200.00 | | 3256505.62 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-21-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 528 |
Percent Time Used | 72 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6431-60-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02234040 |
| Totals | 2527200.00 | 822666.87 | 3256505.62 | 99.9 |
|
County | CHEROKEE |
Highway | US0069 |
From | VARIOUS LOCATION IN CHEROKEE, ETC. |
To | TO INCLUDE SURROUNDING COUNTIES |
CSJ | 6431-88-001 |
Proj ID | MMC - 643188001 |
Work Type | HOT MIX |
|
| 0.010 | 3236840.00 | | 3880050.70 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-22-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 527 |
Percent Time Used | 72 |
Contractor(s) |
LONGVIEW ASPHALT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6431-88-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02234041 |
| Totals | 3236840.00 | 857041.81 | 3880050.70 | 99.9 |
|
County | RUSK |
Highway | US0259 |
From | ANDERSON, HENDERSON, CHEROKEE, SMITH, |
To | RUSK, GREGG, VAN ZANDT & WOOD CO. |
CSJ | 6433-90-001 |
Proj ID | MMC - 643390001 |
Work Type | ROCK/RIPRAP |
|
| 0.010 | 756000.00 | | 597920.95 | 79.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 08-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 456 |
Percent Time Used | 62 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6433-90-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234034 |
| Totals | 756000.00 | 118121.25 | 597920.95 | 79.0 |
|
County | HENDERSON |
Highway | SH0019 |
From | VARIOUS ROADWAYS IN HENDERSON |
To | AND ANDERSON COUNTIES |
CSJ | 6435-20-001 |
Proj ID | RMC - 643520001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 674323.00 | | 226163.00 | 33.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 389 |
Percent Time Used | 53 |
Contractor(s) |
JCW CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6435-20-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234038 |
| Totals | 674323.00 | 35967.50 | 226163.00 | 33.5 |
|
County | VAN ZANDT |
Highway | FM0773 |
From | VARIOUS ROADWAYS |
To | IN VAN ZANDT COUNTY |
CSJ | 6440-57-001 |
Proj ID | RMC - 644057001 |
Work Type | BASE FAILURE PAVEMENT REPAIR |
|
| 0.010 | 1085594.00 | | 682791.60 | 62.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-29-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 275 |
Percent Time Used | 75 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6440-57-001 FREDONIA CONSTRUCTION SERVICES (0.00)
|
Contract # | 11234029 |
| Totals | 1085594.00 | 0.00 | 682791.60 | 62.8 |
|
County | RUSK |
Highway | FM1798 |
From | VARIOUS ROADWAYS |
To | IN RUSK COUNTY |
CSJ | 6440-59-001 |
Proj ID | RMC - 644059001 |
Work Type | BASE FAILURE PAVEMENT REPAIR |
|
| 0.010 | 1049287.00 | | 599834.60 | 57.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-29-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 168 |
Percent Time Used | 46 |
Contractor(s) |
RAYFORD'S TRUCK & TRACTOR |
SUBCONTRACTOR(S) FOR CCSJ: 6440-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234039 |
| Totals | 1049287.00 | 9000.00 | 599834.60 | 57.1 |
|
County | WOOD |
Highway | US0080 |
From | MINEOLA MTCE SECTION |
To | WOOD COUNTY |
CSJ | 6446-50-001 |
Proj ID | RMC - 644650001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 615616.00 | | 453457.00 | 73.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-30-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 359 |
Percent Time Used | 49 |
Contractor(s) |
CATOCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6446-50-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234041 |
| Totals | 615616.00 | 109546.00 | 453457.00 | 73.6 |
|
County | HENDERSON |
Highway | US0175 |
From | VARIOUS LOCATIONS IN |
To | THE TYLER DISTRICT |
CSJ | 6447-69-001 |
Proj ID | MMC - 644769001 |
Work Type | AGGREGATE |
|
| 0.010 | 3028375.00 | | 1453228.55 | 47.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-30-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 387 |
Percent Time Used | 53 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6447-69-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234043 |
| Totals | 3028375.00 | 212621.50 | 1453228.55 | 47.9 |
|
County | SMITH |
Highway | FM3341 |
From | VARIOUS LOCATIONS |
To | IN THE TYLER DISTRICT |
CSJ | 6451-11-001 |
Proj ID | BPM - 645111001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 527250.00 | | 409437.50 | 77.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 85 |
Addl Days Granted | 0 |
Working Days Charged | 79 |
Percent Time Used | 92 |
Contractor(s) |
GARRET SHIELDS INFRASTRUCTURE |
SUBCONTRACTOR(S) FOR CCSJ: 6451-11-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234219 |
| Totals | 527250.00 | 29835.00 | 409437.50 | 77.6 |
|
County | VAN ZANDT |
Highway | FM2339 |
From | VARIOUS LOCATIONS |
To | IN THE TYLER DISTRICT |
CSJ | 6451-13-001 |
Proj ID | BPM - 645113001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 739192.55 | | 2221387.19 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-20-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 102 |
Addl Days Granted | 244 |
Working Days Charged | 151 |
Percent Time Used | 43 |
Contractor(s) |
RED BARON BUILDING COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6451-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234220 |
| Totals | 739192.55 | 293135.07 | 2221387.19 | 99.9 |
|