Monthly State Let Maintenance Report For Tyler District As Of Nov 10, 2024 Page 3 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySMITH
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToSMITH & CHEROKEE COUNTIES
CSJ6456-39-001
Proj IDRMC - 645639001
Work TypePAVEMENT MARKINGS
 
0.0104944538.30555688.1111.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged268
Percent Time Used36
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6456-39-001
STRIPING TECHNOLOGY, L.P. (99.97)
BRYDL CONTRACTING, LLC (11.03)
WEST TEXAS ROCK RESOURCES, LLC (0.40)
Contract #11234030
Totals4944538.309163.18555688.1111.2

CountyGREGG
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToGREGG & RUSK COUNTIES
CSJ6456-41-001
Proj IDRMC - 645641001
Work TypePAVEMENT MARKINGS
 
0.0105035050.97554372.8611.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-14-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged259
Percent Time Used35
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6456-41-001
STRIPING TECHNOLOGY, L.P. (79.83)
BRYDL CONTRACTING, LLC (12.50)
WEST TEXAS ROCK RESOURCES, LLC (0.51)
Contract #11234221
Totals5035050.9737372.10554372.8611.0

CountyHENDERSON
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToHENDERSON & ANDERSON COUNTIES
CSJ6456-91-001
Proj IDRMC - 645691001
Work TypePAVEMENT MARKINGS
 
0.0104796393.50994554.2220.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged182
Percent Time Used24
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244214
Totals4796393.50247733.96994554.2220.7

CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN
ToWOOD & VAN ZANDT COUNTIES
CSJ6456-93-001
Proj IDRMC - 645693001
Work TypePAVEMENT MARKINGS
 
0.0104729775.001116004.4423.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-15-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged198
Percent Time Used27
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6456-93-001
WEST TEXAS ROCK RESOURCES, LLC (0.36)
REYNOLDS & KAY, LTD. (1.34)
BRYDL CONTRACTING, LLC (13.20)
Contract #02244013
Totals4729775.00368451.401116004.4423.5

CountyANDERSON
HighwayUS0079
FromVARIOUS LOCATION IN TYLER DISTRICT
ToTYLER DISTRICT
CSJ6457-46-001
Proj IDMMC - 645746001
Work TypeHOT MIX
 
0.0101341800.00737462.3254.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged302
Percent Time Used82
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6457-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234222
Totals1341800.00225896.48737462.3254.9

CountyHENDERSON
HighwayUS0175
FromVARIOUS LOCATION IN TYLER DISTRICT
ToTYLER DISTRICT
CSJ6457-59-001
Proj IDMMC - 645759001
Work TypeHOT MIX
 
0.0101524500.001130048.4074.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6457-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234223
Totals1524500.00178982.801130048.4074.1

CountySMITH
HighwayUS0069
FromVARIOUS BRIDGES IN
ToTHE TYLER DISTRICT
CSJ6460-94-001
Proj IDBPM - 646094001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010514291.68193133.0037.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days105
Addl Days Granted0
Working Days Charged27
Percent Time Used25
Contractor(s)
RISE UP CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05244016
Totals514291.68188674.00193133.0037.5

CountyRUSK
HighwayUS0079
FromVARIOUS LOCATIONS
ToIN RUSK COUNTY
CSJ6461-63-001
Proj IDRMC - 646163001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010689948.44183820.6227.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-24
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged65
Percent Time Used59
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6461-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244024
Totals689948.441791.77183820.6227.3

CountyRUSK
HighwayUS0059
FromVARIOUS LOCATIONS
ToIN RUSK COUNTY
CSJ6462-63-001
Proj IDRMC - 646263001
Work TypeTREE REMOVAL
 
0.0101069580.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6462-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08244004
Totals1069580.000.000.000.0

CountyWOOD
HighwayUS0069
FromVARIOUS LOCATIONS
ToWOOD COUNTY
CSJ6464-12-001
Proj IDRMC - 646412001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010623147.24303297.7748.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-24
Work Completed
Time Computed00-00-00
Contract Working Days106
Addl Days Granted0
Working Days Charged42
Percent Time Used39
Contractor(s)
SOUTHERN EDGE CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6464-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244027
Totals623147.2484452.52303297.7748.6

CountyHENDERSON
HighwayUS0175
FromVARIOUS ROADWAYS IN HENDERSON
ToAND ANDERSON COUNTIES
CSJ6465-85-001
Proj IDRMC - 646585001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101051801.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09244003
Totals1051801.000.000.000.0

CountySMITH
HighwayUS0069
FromVARIOUS ROADWAYS IN SMITH
ToAND CHEROKEE COUNTIES
CSJ6465-86-001
Proj IDRMC - 646586001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101341365.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6465-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09244004
Totals1341365.000.000.000.0

CountyGREGG
HighwayUS0080
FromVARIOUS ROADWAYS IN GREGG
ToAND RUSK COUNTIES
CSJ6465-87-001
Proj IDRMC - 646587001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101425453.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09244005
Totals1425453.000.000.000.0

CountyWOOD
HighwayUS0080
FromWOOD COUNTY, MINEOLA MO SECTION
ToWOOD COUNTY, MINEOLA
CSJ6469-27-001
Proj IDMMC - 646927001
Work TypeHOT MIX
 
0.0101896800.0060404.413.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged29
Percent Time Used7
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6469-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08244023
Totals1896800.0060404.4160404.413.1

CountyCHEROKEE
HighwaySH0135
FromVARIOUS ROADWAYS
ToIN CHEROKEE COUNTY
CSJ6469-54-001
Proj IDRMC - 646954001
Work TypeMILL AND INLAY
 
0.0101926120.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days16
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6469-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09244012
Totals1926120.950.000.000.0

CountyWOOD
HighwaySL0173
FromVARIOUS ROADWAYS IN GREGG,
ToWOOD, AND VAN ZANDT COUNTIES
CSJ6469-55-001
Proj IDRMC - 646955001
Work TypeMILL AND INLAY
 
0.0102296091.210.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days21
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6469-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09244013
Totals2296091.210.000.000.0

CountyGREGG
HighwayIH0020
FromVARIOUS LOCATIONS ON IH 20
ToIN THE TYLER DISTRICT
CSJ6469-73-001
Proj IDRMC - 646973001
Work TypeMILL AND INLAY
 
0.0103163446.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6469-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10244007
Totals3163446.000.000.000.0

page 1 | page 2 | page 3