Monthly State Let Construction Report For San Antonio District As Of Nov 10, 2024 Page 1 Of 7

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOMAL
HighwayIH 35
FromAT FM 725
To.
CSJ0016-05-120
Proj IDC 16-5-120
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
0.2765144829.213900259.7376.3
CountyCOMAL
HighwayIH 35
FromAT FM 725
To.
CSJ0016-05-124
Proj IDROW 0016-05-124
Work TypeRIGHT OF WAY
 
0.276846.000.000.0
Work Order07-20-21
Work Began01-10-22
Work Completed
Time Computed08-19-21
Contract Working Days283
Addl Days Granted49
Working Days Charged371
Percent Time Used111
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-120
FLASHER EQUIPMENT COMPANY (0.45)
TRP CONSTRUCTION GROUP, LLC (1.64)
F & W ELECTRICAL CONTRACTORS, INC. (11.45)
ROADWAY SPECIALTIES, INC. (0.24)
TEXAS HIGHWAY WALLS (5.29)
CAPITAL EXCAVATION COMPANY (5.98)
G 6 CONSTRUCTION, INC. (13.04)
SCOTT DERR PAINTING CO, LLC (0.03)
LONE STAR EROSION CONTROL (1.72)
FARR FOUNDATION, INC. (4.70)
Contract #06213209
Totals5145675.21175674.903900259.7376.3

CountyCOMAL ETC
HighwayIH 35 ETC
FromSCHWAB RD
ToSOLMS RD
CSJ0016-05-126
Proj IDC 16-5-126
Work TypeSEAL COAT
 
306.85516993738.720.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days132
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-126
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243206
Totals16993738.720.000.000.0

CountyBEXAR
HighwaySL 368
FromAT SALADO CREEK AND IRA LEE RD.
To.
CSJ0016-08-039
Proj IDBR 2021(485)
Work TypeBRIDGE REPLACEMENT
 
0.1406694601.995607782.5483.7
CountyBEXAR
HighwaySL 368
FromAT SALADO CREEK AND IRA LEE RD.
To.
CSJ0016-08-044
Proj IDROW 16-8-44
Work TypeRIGHT OF WAY
 
0.140280195.000.000.0
Work Order05-20-21
Work Began07-12-21
Work Completed
Time Computed06-21-21
Contract Working Days481
Addl Days Granted60
Working Days Charged525
Percent Time Used97
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-08-039
TEXAS ICON CONSTRUCTION, LLC (0.98)
TEXAS MATERIALS GROUP, INC. (4.13)
HB FARMER FOUNDATION, LLC (6.57)
FLASHER EQUIPMENT COMPANY (0.53)
LIGHT IT UP ELECTRIC (3.49)
TORO BRAVO CONSTRUCTION, LLC (0.64)
Contract #04213003
Totals6974796.9942545.005607782.5480.4

CountyBEXAR
HighwaySL 368 ETC
FromWALZEM RD
ToCORINNE RD
CSJ0016-08-043
Proj IDSTP 2022(685)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.2361884493.202268251.1499.9
Work Order07-27-22
Work Began11-14-22
Work Completed
Time Computed08-26-22
Contract Working Days312
Addl Days Granted0
Working Days Charged249
Percent Time Used79
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-08-043
ALAMO CRANE SERVICE, INC. (0.26)
FIBERTEL, LLC (1.24)
LOZANO CONSTRUCTION COMPANY, INC. (0.82)
M & M STRIPING & POWER WASHING, LLC (8.82)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.27)
B&T DEPENDABLE SERVICES LLC (0.10)
Contract #06223626
Totals1884493.200.002268251.1499.9

CountyBEXAR
HighwaySL 368
FromROY SMITH
ToBURR RD.
CSJ0016-08-047
Proj IDF 2024(414)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.30710471624.977577750.6172.3
CountyBEXAR
HighwaySL 368
FromROY SMITH
ToBURR RD.
CSJ0016-08-048
Proj IDROW 16-8-48
Work TypeRIGHT OF WAY
 
2.30724098.5823070.0095.7
Work Order12-13-23
Work Began02-19-24
Work Completed
Time Computed01-12-23
Contract Working Days245
Addl Days Granted0
Working Days Charged165
Percent Time Used67
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0016-08-047
RUCOBA & MAYA CONSTRUCTION, LLC (10.99)
FLASHER EQUIPMENT COMPANY (3.55)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.46)
A K FUQUAY CONSTRUCTION (0.59)
EGGEMEYER LAND CLEARING, LLC (0.43)
E-Z BEL CONSTRUCTION, LLC (17.00)
MEX UTILITIES LLC (1.17)
TEXAS REEXCAVATION (0.19)
Contract #11233028
Totals10495723.551222942.767600820.6172.4

CountyBEXAR ETC
HighwaySL 353 ETC
FromLP 13
ToIH 35
CSJ0017-01-026
Proj IDF 2022(032)
Work TypeSEAL COAT
 
179.0806922525.536377414.6092.1
Work Order12-30-21
Work Began07-21-22
Work Completed
Time Computed05-03-22
Contract Working Days93
Addl Days Granted0
Working Days Charged80
Percent Time Used86
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-01-026
INTERSTATE BARRICADES & MARKINGS, INC. (9.48)
COX PAVING OF TEXAS, INC. (16.60)
Contract #10213021
Totals6922525.530.006377414.6092.1

CountyBEXAR
HighwayIH 35
FromOUSSETT ROAD
To0.3 MI N OF IH 410
CSJ0017-02-078
Proj IDC 17-2-78
Work TypeOVERLAY
 
7186869.467083523.0698.5
CountyBEXAR
HighwayIH 35
From0.42 MI S. OF KINNEY ROAD
ToOUSSETT ROAD
CSJ0017-03-068
Proj IDC 17-3-68
Work TypeOVERLAY
 
3.4606132153.705611067.5991.5
Work Order04-19-23
Work Began07-31-23
Work Completed
Time Computed07-18-23
Contract Working Days243
Addl Days Granted0
Working Days Charged152
Percent Time Used62
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-078
FLASHER EQUIPMENT COMPANY (4.02)
A K FUQUAY CONSTRUCTION (1.60)
GREYCO CONSTRUCTION, LLC (1.20)
PRIMATE CONSTRUCTION, LP (1.20)
ROADWAY SPECIALTIES, INC. (8.53)
WEST TEXAS ROCK RESOURCES, LLC (0.07)
Contract #03233006
Totals13319023.1682835.6112694590.6595.3

CountyATASCOSA
HighwayIH 35
FromATASCOSA/BEXAR COUNTY LINE
ToATASCOSA/MEDINA COUNTY LINE
CSJ0017-04-042
Proj IDNH 2019(646)
Work TypeBSE, SURF, PAV'T MRKINGS
 
2.5063383807.084857768.8699.9
CountyZERO COUNTIES
Highway
From
To
CSJ0017-04-047
Proj ID
Work Type
 
0.00527938.440.0
CountyMEDINA
HighwayIH 35
FromFRIO/MEDINA COUNTY LINE
ToMEDINA/ATASCOSA COUNTY LINE
CSJ0017-05-094
Proj IDNH 2019(646)
Work TypeBSE, SURF, PAV'T MRKINGS
 
12.6849526910.4010255852.1799.9
CountyZERO COUNTIES
Highway
From
To
CSJ0017-05-098
Proj ID
Work Type
 
0.001511210.020.0
Work Order04-25-19
Work Began07-10-19
Work Completed
Time Computed05-25-19
Contract Working Days345
Addl Days Granted0
Working Days Charged345
Percent Time Used100
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-042
DEPENDABLE FENCE & WELDING CO. INC. (5.02)
RELMCO, INC. (8.01)
FLASHER EQUIPMENT COMPANY (5.81)
PERFORMANCE EQUIPMENT SERVICE (3.99)
ALL AMERICAN TRUCKING, INC. (1.47)
BUYERS BARRICADES SAN ANTONIO, LLC (0.02)
ROADWAY SPECIALTIES, INC. (12.48)
WEST TEXAS ROCK RESOURCES, LLC (0.15)
CHEROKEE SERVICES (1.35)
G 6 CONSTRUCTION, INC. (1.28)
TRP CONSTRUCTION GROUP, LLC (0.32)
J & P PAVING CO. (0.37)
Contract #03193204
Totals12910717.4864316.6217152769.4999.9

CountyATASCOSA
HighwayIH 35
From0.5 MI SOUTH OF FM 3175
ToFM 2790
CSJ0017-04-044
Proj IDF 2022(046)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.0396383622.467720603.0599.9
Work Order10-14-21
Work Began04-04-22
Work Completed
Time Computed11-13-21
Contract Working Days282
Addl Days Granted30
Working Days Charged340
Percent Time Used108
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-044
ADCOCK 4 INVESTMENTS, LLC (7.30)
CUATRO T CONSTRUCTION, INC. (0.23)
A BROTHERS MILLING, LLC (1.82)
ACEE CONSTRUCTION LLC. (16.66)
DIIBS SPECIALISTS, LLC (2.33)
EGGEMEYER LAND CLEARING, LLC (0.15)
INTERSTATE BARRICADES & MARKINGS, INC. (1.31)
THE LEVY COMPANY, INC. (1.48)
LONE STAR EROSION CONTROL (1.44)
TRP CONSTRUCTION GROUP, LLC (0.66)
PERFORMANCE EQUIPMENT SERVICE (0.28)
STATEWIDE SAFETY SYSTEMS (0.18)
LONGHORN SERVICES, INC (0.21)
FUQUAY, INC. (1.42)
HIGHWAY BARRICADES AND SERVICES, LLC (0.61)
TEXAS ICON CONSTRUCTION, LLC (0.25)
RPV CONSTRUCTION, LLC (0.07)
Contract #09213026
Totals6383622.460.007720603.0599.9

CountyMEDINA
HighwayIH 35
FromAT CHACON CREEK
To.
CSJ0017-05-096
Proj IDBR 2025(167)
Work TypeBRIDGE REPLACEMENT
 
0.44012823667.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days318
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-05-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243010
Totals12823667.140.000.000.0

CountyMEDINA ETC
HighwayIH 35 ETC
FromMEDINA/FRIO C.L.
ToCR 770
CSJ0017-05-102
Proj IDF 2024(471)
Work TypeSEAL COAT
 
276.52616608123.1814427491.9386.8
Work Order11-16-23
Work Began05-01-24
Work Completed
Time Computed12-16-23
Contract Working Days153
Addl Days Granted0
Working Days Charged123
Percent Time Used80
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-05-102
CENTERLINE TECHNOLOGIES, LLC (10.57)
COX PAVING OF TEXAS, INC. (14.90)
D. I. J. CONSTRUCTION, INC. (1.70)
INTERSTATE BARRICADES & MARKINGS, INC. (2.06)
RED SIXTEEN CONSTRUCTION, INC (0.00)
Contract #10233006
Totals16608123.18317730.6814427491.9386.8

CountyFRIO
HighwayIH 35
FromUS 57
ToFRIO/MEDINA COUNTY LINE
CSJ0017-06-086
Proj IDC 17-6-86
Work TypeOVERLAY
 
11872494.752525637.3821.2
Work Order02-02-24
Work Began10-21-24
Work Completed
Time Computed10-21-24
Contract Working Days149
Addl Days Granted0
Working Days Charged9
Percent Time Used6
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-06-086
ACEE CONSTRUCTION LLC. (3.16)
A K FUQUAY CONSTRUCTION (1.22)
FLASHER EQUIPMENT COMPANY (0.19)
HIGHWAY BARRICADES AND SERVICES, LLC (2.62)
PERFORMANCE EQUIPMENT SERVICE (3.75)
PRIMATE CONSTRUCTION, LP (0.89)
RPV CONSTRUCTION, LLC (4.41)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.16)
Contract #01243207
Totals11872494.752525637.382525637.3821.2

CountyBEXAR ETC
HighwayIH 35 ETC
From0.34 MI WEST OF SOMERSET RD
To0.71 MI WEST OF CASSIN RD
CSJ0017-09-111
Proj IDSTP 2022(432)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
16.1412720941.842630857.2697.4
Work Order05-12-22
Work Began01-23-23
Work Completed
Time Computed06-11-22
Contract Working Days176
Addl Days Granted0
Working Days Charged202
Percent Time Used114
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-111
ROADWAY SPECIALTIES, INC. (32.03)
BARRICADES UNLIMITED (0.79)
KHONSU ENTERPRISE LLC (8.81)
LONE STAR EROSION CONTROL (1.94)
Contract #04223012
Totals2720941.8427789.622630857.2697.4

CountyBEXAR
HighwayIH 35
FromLAREDO ST.
ToAUSTIN ST.
CSJ0017-10-289
Proj IDBR 2023(047)
Work TypeRESTORATION
 
3.1337801107.506008981.8877.0
CountyBEXAR
HighwayIH 10
From0.1 MI EAST OF HILDERBRAND
ToIH 35
CSJ0072-12-191
Proj IDBR 2023(047)
Work TypeRESTORATION
 
3.00418155195.065770797.5531.7
Work Order11-09-22
Work Began05-01-23
Work Completed
Time Computed02-07-23
Contract Working Days822
Addl Days Granted20
Working Days Charged398
Percent Time Used47
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-289
AARON CONCRETE CONTRACTORS, L.P. (0.75)
FLASHER EQUIPMENT COMPANY (1.59)
THE LEVY COMPANY, INC. (2.83)
AUSTIN BRIDGE & ROAD SERVICES, LP (32.78)
S & S BRIDGE PAINTING, INC. (4.44)
DIIBS SPECIALISTS, LLC (0.15)
SERNA"S TRUCKING (0.00)
MACIAS SPECIALTY CONTRACTING LLC (3.66)
ROY JORGENSEN ASSOCIATES, INC. (0.17)
AIMS COMPANIES (0.00)
IBCTX, LLC (4.01)
LLOYD D. NABORS DEMOLITION LLC (1.63)
Contract #10223203
Totals25956302.561380337.8011779779.4345.3

CountyFRIO
HighwayBI 35-E
From0.3 MI NORTH OF FIELDS ST
ToE. FLORIDA ST
CSJ0017-15-028
Proj IDSTP 2024(938)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.0001111692.000.000.0
CountyBEXAR
HighwaySL 13
FromBERGQUIST DR
ToSELFRIDGE BLVD
CSJ0521-03-062
Proj IDSTP 2024(938)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.351995159.0014759.001.4
Work Order05-08-24
Work Began10-28-24
Work Completed
Time Computed10-28-24
Contract Working Days150
Addl Days Granted0
Working Days Charged4
Percent Time Used2
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-15-028
GRATR LANDSCAPES, LTD. (0.58)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.65)
LOZANO CONSTRUCTION COMPANY, INC. (0.05)
LONE STAR EROSION CONTROL (10.92)
FIBERTEL, LLC (0.37)
Contract #04243021
Totals2106851.0014759.0014759.000.7

CountyMEDINA ETC
HighwayUS 90 ETC
FromCASTRO ST
ToVETERANS BLVD
CSJ0024-05-102
Proj IDSTP 2025(004)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
61.0842230735.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0024-05-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243026
Totals2230735.000.000.000.0

CountyBEXAR
HighwayUS 90
FromAT SH 211
To.
CSJ0024-07-069
Proj IDSTP 2024(782)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.4946869481.903933134.2857.2
Work Order04-18-24
Work Began06-03-24
Work Completed
Time Computed05-18-24
Contract Working Days307
Addl Days Granted0
Working Days Charged92
Percent Time Used29
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0024-07-069
BEAIRD DRILLING SERVICES, INC. (4.30)
EGGEMEYER LAND CLEARING, LLC (0.25)
FLASHER EQUIPMENT COMPANY (0.53)
FRANK JR REINFORCEMENT LLC (2.62)
LONE STAR EROSION CONTROL (2.31)
LONE STAR PAVING COMPANY (10.14)
STRATA FOUNDATION DRILLING, LLC (1.02)
Contract #03243017
Totals6869481.90781784.163933134.2857.2

CountyBEXAR
HighwayUS 90
FromHORAL ST.
ToSL 353
CSJ0024-08-141
Proj IDF 2023(121)
Work TypeOVERLAY
 
8.70628447459.1226312536.9892.4
Work Order10-13-22
Work Began01-03-23
Work Completed
Time Computed11-12-22
Contract Working Days461
Addl Days Granted0
Working Days Charged411
Percent Time Used89
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-141
TRP CONSTRUCTION GROUP, LLC (3.30)
FLASHER EQUIPMENT COMPANY (0.79)
LONE STAR EROSION CONTROL (5.44)
PRIMATE CONSTRUCTION, LP (1.11)
SERNA"S TRUCKING (0.13)
THE LEVY COMPANY, INC. (1.00)
PERFORMANCE EQUIPMENT SERVICE (1.26)
CALAME CONTRACTING, LLC (0.05)
SK QUALITY CONCRETE LP (1.87)
DUSTROL, INC. (2.30)
TRP CONSTRUCTION GROUP, LLC (0.00)
SWEEPING CORPORATION OF AMERICA, LLC (0.01)
Contract #09223242
Totals28447459.121006220.4026312536.9892.4

CountyBEXAR
HighwayUS 90
FromFRIO CITY RD
ToSL 353 (NOGALITOS ST)
CSJ0024-08-145
Proj IDSTP 2025(005)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.841408069.000.000.0
CountyBEXAR
HighwayIH 410
FromUS 90
ToMEDINA BASE RD
CSJ0521-05-160
Proj IDSTP 2025(005)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.950616885.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days32
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LCR TOTAL TRANSPORT LLC
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-145
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243036
Totals1024954.000.000.000.0

CountyBEXAR
HighwayUS 90
From0.8 MILES WEST OF SH 151
To1.1 MILES EAST OF SH 151
CSJ0024-08-148
Proj IDC 24-8-148
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
1.930484934.120.000.0
Work Order06-12-24
Work Began00-00-00
Work Completed
Time Computed07-12-24
Contract Working Days146
Addl Days Granted0
Working Days Charged19
Percent Time Used13
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-148
BARRICADES UNLIMITED (2.35)
JYV COMMUNICATIONS INC. (4.53)
Contract #05243241
Totals484934.120.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7