Monthly State Let Construction Report For San Antonio District As Of Nov 10, 2024 Page 5 Of 7

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayCS
FromALONG FM 2790, COTTAGE ST., AND PRAIRIE
ToIN LYTLE: MEDINA, ATASCOSA, BEXAR COUNTY
CSJ0915-00-252
Proj IDSTP 2023(490)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1244334.00748603.1460.1
Work Order11-16-23
Work Began02-08-24
Work Completed
Time Computed12-16-23
Contract Working Days280
Addl Days Granted0
Working Days Charged162
Percent Time Used57
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-252
BARRICADES UNLIMITED (2.30)
A K FUQUAY CONSTRUCTION (8.26)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.81)
Contract #10233218
Totals1244334.002700.00748603.1460.1

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CONTROL FY 2023
ToPROJECT 1
CSJ0915-00-253
Proj IDC 915-00-253
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011505725.721637228.2699.9
Work Order03-16-23
Work Began08-07-23
Work Completed
Time Computed06-14-23
Contract Working Days260
Addl Days Granted0
Working Days Charged124
Percent Time Used47
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-253
ALAMO CRANE SERVICE, INC. (0.87)
FIBERTEL, LLC (4.20)
FLASHER EQUIPMENT COMPANY (3.77)
LOZANO TRUCKING COMPANY, INC. (1.03)
M & M STRIPING & POWER WASHING, LLC (1.30)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.09)
CATO ELECTRIC COMPANY (0.14)
Contract #02233231
Totals1505725.720.001637228.2699.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CONTROL FY 2023
ToPROJECT 2
CSJ0915-00-254
Proj IDC 915-00-254
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011347419.721423418.5099.9
Work Order06-28-23
Work Began10-24-23
Work Completed
Time Computed09-26-23
Contract Working Days260
Addl Days Granted0
Working Days Charged126
Percent Time Used48
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-254
LOZANO TRUCKING COMPANY, INC. (1.15)
FIBERTEL, LLC (4.69)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.11)
Contract #05233234
Totals1347419.722833.751423418.5099.9

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-257
Proj IDC 915-00-257
Work TypeTRAFFIC CONTROL DEVICES
 
0.0015176271.915454353.2999.9
Work Order07-19-23
Work Began00-00-00
Work Completed
Time Computed10-17-23
Contract Working Days191
Addl Days Granted0
Working Days Charged191
Percent Time Used100
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-257
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06233217
Totals5176271.911817.005454353.2999.9

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-258
Proj IDC 915-00-258
Work TypeBRIDGE WIDENING OR REHABILITATION
 
1984026.001591920.4780.2
Work Order08-03-23
Work Began10-31-23
Work Completed
Time Computed09-02-23
Contract Working Days173
Addl Days Granted10
Working Days Charged179
Percent Time Used97
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-258
D&G ENERGY CORPORATION (0.67)
TEXAS CUTTING & CORING, LP (0.81)
Contract #06233421
Totals1984026.00188139.311591920.4780.2

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CONTROL FY 2024
ToPROJECT 1
CSJ0915-00-259
Proj IDC 915-00-259
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011607455.00900152.5155.9
Work Order03-06-24
Work Began06-17-24
Work Completed
Time Computed06-04-24
Contract Working Days260
Addl Days Granted0
Working Days Charged43
Percent Time Used16
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-259
LOZANO CONSTRUCTION COMPANY, INC. (0.02)
FIBERTEL, LLC (1.37)
ALAMO CRANE SERVICE, INC. (0.22)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.11)
PAVEMENT MARKINGS INC. (1.37)
Contract #02243031
Totals1607455.0070974.16900152.5155.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CONTROL FY 2024
ToPROJECT 2
CSJ0915-00-260
Proj IDC 915-00-260
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011600870.00105881.006.6
Work Order06-26-24
Work Began00-00-00
Work Completed
Time Computed09-24-24
Contract Working Days260
Addl Days Granted0
Working Days Charged22
Percent Time Used8
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-260
ALAMO CRANE SERVICE, INC. (1.29)
FIBERTEL, LLC (2.07)
LOZANO CONSTRUCTION COMPANY, INC. (0.12)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (1.78)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.62)
Contract #05243032
Totals1600870.00105881.00105881.006.6

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDE SIGNS FY 2024
To.
CSJ0915-00-261
Proj IDC 915-00-261
Work TypeTRAFFIC CONTROL DEVICES
 
0.001914908.41490551.9953.6
Work Order05-16-24
Work Began08-14-24
Work Completed
Time Computed08-14-24
Contract Working Days215
Addl Days Granted0
Working Days Charged47
Percent Time Used21
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-261
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (1.54)
Contract #04243216
Totals914908.41137632.11490551.9953.6

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-263
Proj IDF 2B24(171)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0013699237.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-10-24
Work Began00-00-00
Work Completed
Time Computed01-08-25
Contract Working Days154
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-263
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243221
Totals3699237.020.000.000.0

CountyBEXAR
HighwayVA
FromON POST OAK TR., IN FAIR OAKS RANCH
ToFROM SILVER SPUR TR. TO ROLLING ACRES TR
CSJ0915-00-264
Proj IDSTP 2023(949)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2147579.652028083.8394.4
Work Order08-03-23
Work Began00-00-00
Work Completed
Time Computed09-01-23
Contract Working Days150
Addl Days Granted0
Working Days Charged132
Percent Time Used88
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-264
A K FUQUAY CONSTRUCTION (3.96)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.94)
BARRICADES UNLIMITED (0.44)
LONE STAR EROSION CONTROL (2.54)
TRP CONSTRUCTION GROUP, LLC (2.24)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.35)
LONE STAR PAVING COMPANY (16.05)
Contract #06233623
Totals2147579.6514815.932028083.8394.4

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
ToON THE IH 10 CORRIDOR
CSJ0915-00-268
Proj IDF 2B24(172)
Work TypeTRAFFIC CONTROL DEVICES
 
1282250.5730142.002.3
Work Order07-17-24
Work Began00-00-00
Work Completed
Time Computed09-15-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-268
DIIBS SPECIALISTS, LLC (2.79)
FIBERTEL, LLC (5.71)
LIGHT IT UP ELECTRIC (28.15)
LOZANO CONSTRUCTION COMPANY, INC. (0.02)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (1.11)
Contract #06243043
Totals1282250.570.0030142.002.3

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-269
Proj IDC 915-00-269
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012236322.001704610.7576.2
Work Order11-08-23
Work Began00-00-00
Work Completed
Time Computed12-08-23
Contract Working Days257
Addl Days Granted0
Working Days Charged165
Percent Time Used64
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-269
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233017
Totals2236322.00100553.101704610.7576.2

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-270
Proj IDF 2B24(173)
Work TypeBRIDGE REPLACEMENT
 
9168264.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-24
Work Began00-00-00
Work Completed
Time Computed10-30-24
Contract Working Days269
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-270
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243214
Totals9168264.140.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-297
Proj IDF 2024(973)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012542203.001381001.2854.3
Work Order06-06-24
Work Began08-08-24
Work Completed
Time Computed09-04-24
Contract Working Days255
Addl Days Granted0
Working Days Charged60
Percent Time Used23
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-297
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05243027
Totals2542203.00864672.221381001.2854.3

CountyBEXAR
HighwayCS
FromN WALTERS ST @ UPRR & LARRY STREET
To.
CSJ0915-12-532
Proj IDBR 1402(214)
Work TypeBRIDGE REPLACEMENT
 
0.0621567047.861471926.2996.5
Work Order04-06-22
Work Began09-13-22
Work Completed
Time Computed05-06-22
Contract Working Days108
Addl Days Granted0
Working Days Charged160
Percent Time Used148
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-532
DIIBS SPECIALISTS, LLC (3.22)
HYDRO TECHNOLOGIES, INC. (6.50)
Contract #02223219
Totals1567047.860.001471926.2996.5

CountyBEXAR
HighwayCS
FromON CASTROVILLE RD AT CUPPLES RD
To.
CSJ0915-12-624
Proj IDSTP 2022(690)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.8002074271.501628587.1780.2
Work Order08-04-22
Work Began01-10-23
Work Completed
Time Computed09-03-22
Contract Working Days297
Addl Days Granted0
Working Days Charged344
Percent Time Used115
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-624
FIBERTEL, LLC (5.02)
CATO ELECTRIC COMPANY (0.14)
BEXAR COUNTY TRAFFIC CONTROLLERS, LLC (1.26)
Contract #06223422
Totals2074271.500.001628587.1780.2

CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON PLEASANTON/MOURSUND
ToFROM FITCH AVE TO IH 410
CSJ0915-12-695
Proj IDSTP 2B24(169)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.4192683102.370.000.0
Work Order08-01-24
Work Began00-00-00
Work Completed
Time Computed10-30-24
Contract Working Days240
Addl Days Granted0
Working Days Charged2
Percent Time Used0
Contractor(s)
ELECNOR BELCO ELECTRIC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-695
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243023
Totals2683102.370.000.000.0

CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON PLEASANTON RD
ToAT HARDING BLVD
CSJ0915-12-696
Proj IDSTP 2024(389)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200420898.53514560.6699.9
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON GOLIAD RD
ToAT CLARK AVE
CSJ0915-12-709
Proj IDSTP 2024(389)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
455820.7048952.5010.7
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON GOLIAD RD
ToAT PECAN VALLEY
CSJ0915-12-710
Proj IDSTP 2024(389)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
349938.17282074.0080.6
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON HUEBNER RD
ToAT HUEBNER ES
CSJ0915-12-711
Proj IDSTP 2024(389)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200293322.19253672.1986.4
Work Order12-05-23
Work Began00-00-00
Work Completed
Time Computed03-04-24
Contract Working Days129
Addl Days Granted0
Working Days Charged62
Percent Time Used48
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-696
ALAMO CRANE SERVICE, INC. (0.53)
FIBERTEL, LLC (6.76)
FLASHER EQUIPMENT COMPANY (5.43)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (2.95)
CENTERLINE TECHNOLOGIES, LLC (5.43)
Contract #11233019
Totals1519979.59195881.201099259.3572.3

CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON SAN PEDRO AVE
ToAT SAHARA DR
CSJ0915-12-698
Proj IDSTP 2023(535)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200408559.23445736.6899.9
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON E. SOUTHCROSS BLVD
ToAT PECAN VALLEY
CSJ0915-12-708
Proj IDSTP 2023(535)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200397172.61409194.7199.9
CountyBEXAR
Highway0000000
FromIN SAN ANTONIO ON S FLORES ST
ToAT SAYERS AVE
CSJ0915-12-714
Proj IDSTP 2023(535)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
280986.50292604.0099.9
Work Order04-26-23
Work Began08-21-23
Work Completed
Time Computed05-26-23
Contract Working Days129
Addl Days Granted0
Working Days Charged92
Percent Time Used71
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-698
ALAMO CRANE SERVICE, INC. (0.37)
FIBERTEL, LLC (5.62)
FLASHER EQUIPMENT COMPANY (3.80)
LOZANO TRUCKING COMPANY, INC. (0.39)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (2.62)
Contract #03233026
Totals1086718.340.001147535.3999.9

CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON S. ZARZAMORA
ToAT MERIDA ST
CSJ0915-12-716
Proj IDSTP 2024(786)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
334261.360.000.0
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON NACOGDOCHES RD
ToAT STARCREST DR
CSJ0915-12-719
Proj IDSTP 2024(786)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200233118.870.000.0
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON PROBANDT ST
ToAT THEO AVE
CSJ0915-12-766
Proj IDSTP 2024(786)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
313499.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-24
Work Began00-00-00
Work Completed
Time Computed12-17-24
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ELECNOR BELCO ELECTRIC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-716
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243248
Totals880880.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7