Monthly State Let Construction Report For San Antonio District As Of Nov 10, 2024 Page 7 Of 7

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMEDINA
HighwayFM 2200
FromAT FRANCISCO PEREZ CREEK
To.
CSJ2520-01-015
Proj IDBR 2023(527)
Work TypeBRIDGE REPLACEMENT
 
0.2111196252.751224291.6499.9
CountyMEDINA
HighwayFM 2200
FromVIRGINIA DR
ToCR 764 (HUNTZER LN.)
CSJ2520-01-016
Proj IDSTP 2023(528)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.2005010276.105058104.8599.9
Work Order04-19-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days309
Addl Days Granted5
Working Days Charged307
Percent Time Used97
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2520-01-015
D&G ENERGY CORPORATION (0.78)
LONE STAR EROSION CONTROL (5.25)
TEXAS SHAFTS, INC. (1.64)
FLASHER EQUIPMENT COMPANY (2.22)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.32)
TORO BRAVO CONSTRUCTION, LLC (0.16)
SOUTHEAST GRINDING AND GROOVING LLC (0.11)
Contract #03233218
Totals6206528.85361348.596282396.4999.9

CountyMEDINA
HighwayFM 2676
From1.52 MI E. OF SH 173
ToAT HONDO CREEK
CSJ2649-01-035
Proj IDBR 2023(384)
Work TypeBRIDGE REPLACEMENT
 
0.1754254249.683155666.4174.1
Work Order01-06-23
Work Began06-05-23
Work Completed
Time Computed03-07-23
Contract Working Days284
Addl Days Granted0
Working Days Charged285
Percent Time Used100
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2649-01-035
DIIBS SPECIALISTS, LLC (1.51)
TORO BRAVO CONSTRUCTION, LLC (1.26)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.14)
GREGORY PILE DRIVING, INC. (7.26)
FLASHER EQUIPMENT COMPANY (0.51)
TEXAS MATERIALS GROUP, INC. (4.57)
FARR FOUNDATION, INC. (7.32)
AAA DRILLING FOUNDATION COMPANY, INC. (5.42)
Contract #12223232
Totals4254249.68321650.033155666.4174.1

CountyBEXAR
HighwayFM 2696
From0.1 MI NORTH OF CALICO LANDING
ToWILDERNESS OAK
CSJ2708-01-033
Proj IDSTP 2024(534)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.367778577.00866475.8499.9
Work Order02-02-24
Work Began05-20-24
Work Completed
Time Computed03-03-24
Contract Working Days89
Addl Days Granted0
Working Days Charged78
Percent Time Used87
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2708-01-033
ALAMO CRANE SERVICE, INC. (0.01)
FIBERTEL, LLC (3.14)
LOZANO CONSTRUCTION COMPANY, INC. (0.06)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.76)
LLANO AUGER SERVICE (0.41)
Contract #01243035
Totals778577.001400.00866475.8499.9

CountyKENDALL
HighwayFM 3351
FromSH 46
ToKENDALL/COMAL COUNTY LINE
CSJ3212-04-009
Proj IDF 2023(677)
Work TypeOVERLAY
 
3.680992293.831380196.4999.9
CountyKENDALL
HighwayFM 3351
FromKENDALL WOODS DR
To0.2 MI SOUTH OF SH 46
CSJ3212-04-010
Proj IDSTP 2023(678)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8701803552.631503065.9583.3
CountyKENDALL
HighwayFM 3351
From0.2 MI NORTH OF GUTHRIE RD
ToKENDALL/COMAL COUNTY LINE
CSJ3212-04-012
Proj IDSTP 2023(678)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5651221952.591171925.9295.9
CountyCOMAL
HighwayFM 3351
FromKENDALL/COMAL COUNTY LINE
ToBEXAR/COMAL COUNTY LINE
CSJ3212-05-015
Proj IDF 2023(677)
Work TypeOVERLAY
 
3.1462242729.502202542.6498.2
Work Order06-14-23
Work Began09-12-23
Work Completed
Time Computed09-12-23
Contract Working Days213
Addl Days Granted0
Working Days Charged187
Percent Time Used87
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3212-04-009
TERRA CONSTRUCTION LLC (7.83)
FLASHER EQUIPMENT COMPANY (0.91)
GEOSOURCE, INC. (0.53)
TRP CONSTRUCTION GROUP, LLC (5.66)
EGGEMEYER LAND CLEARING, LLC (0.87)
RPV CONSTRUCTION, LLC (1.20)
A K FUQUAY CONSTRUCTION (1.27)
GREYCO CONSTRUCTION, LLC (2.39)
THE LEVY COMPANY, INC. (0.25)
Contract #05233211
Totals6260528.5519945.666257731.0099.9

CountyCOMAL
HighwayFM 3351
FromAT CIBOLO CREEK
To.
CSJ3212-05-013
Proj IDSTP 2024(729)MM
Work TypeBRIDGE REPLACEMENT
 
12162006.553612941.5629.7
CountyCOMAL
HighwayFM 3351
FromAT CIBOLO CREEK
To.
CSJ3212-05-017
Proj IDF 2022(741)
Work TypeUTILITY ADJUSTMENTS
 
396071.00396872.5099.9
Work Order03-06-24
Work Began00-00-00
Work Completed
Time Computed06-04-24
Contract Working Days527
Addl Days Granted0
Working Days Charged94
Percent Time Used17
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3212-05-013
ENVIRONMENTAL SAFETY SERVICES, INC. (3.22)
HOUSTON SAWING & DRILLING (0.13)
LONE STAR EROSION CONTROL (0.49)
LONE STAR PAVING COMPANY (10.11)
SCOTT DERR PAINTING CO, LLC (0.30)
TORO BRAVO CONSTRUCTION, LLC (2.85)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.51)
HARDY HOLE DRILLING (3.32)
Contract #02243205
Totals12558077.551334751.684009814.0631.9

CountyBEXAR
HighwaySH 151
FromLP 1604
ToIH 410
CSJ3508-01-029
Proj IDF 2023(162)
Work TypeWIDEN FREEWAY
 
5.59194798463.6956816177.8559.9
CountyBEXAR
HighwaySH 151
FromLP 1604
ToIH 410
CSJ3508-01-030
Proj IDROW 3508-1-30
Work TypeRIGHT OF WAY
 
5.5913004452.984547035.2099.9
Work Order02-16-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days1,079
Addl Days Granted36
Working Days Charged443
Percent Time Used39
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 3508-01-029
A. H. BECK FOUNDATION CO., INC. (1.59)
C-3 LAND CLEARING, LLC (0.03)
AARON CONCRETE CONTRACTORS, LLC (1.74)
FLASHER EQUIPMENT COMPANY (1.64)
FARR FOUNDATION, INC. (0.41)
MEX UTILITIES LLC (1.37)
S&S BRIDGE PAINTING (0.00)
SK CONCRETE SERVICES LLC (0.02)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (13.65)
LONE STAR EROSION CONTROL (2.00)
Z & L CONCRETE CONTRACTORS, INC. (3.40)
WAMPOLE MILLER, INC. (0.19)
SERNA"S TRUCKING (0.82)
ROYAL REBAR (1.87)
PIPE WHOLESALERS OF TEXAS, INC. (1.20)
MOBILE ENTERPRISES, INC. (0.04)
BOEN LANDSCAPING & IRRIGATION, LLC (0.00)
HH&W TRANSPORT INC (0.00)
BUYERS BARRICADES, INC. (0.00)
RICHEY TRANSPORT LLC (0.00)
JC DIRECTIONAL DRILLING (0.31)
GIBSON & ASSOCIATES, INC. (0.03)
HYDROMAX, LLC (0.01)
Contract #01233237
Totals97802916.673159300.4661363213.0562.7

CountyBEXAR
HighwayPA 1502
FromFM 1535
ToO'CONNOR/CROSSWINDS WAY
CSJ7774-01-004
Proj IDF 2021(678)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.71219520129.8320922809.1499.9
Work Order08-18-21
Work Began02-01-22
Work Completed
Time Computed11-16-21
Contract Working Days424
Addl Days Granted193
Working Days Charged606
Percent Time Used98
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 7774-01-004
THE LEVY COMPANY, INC. (12.86)
JB PINNACLE GROUP, LLC (7.97)
RUCOBA & MAYA CONSTRUCTION, LLC (1.36)
LONE STAR EROSION CONTROL (4.21)
SCOTT DERR PAINTING CO, LLC (0.35)
TEXAS CUTTING & CORING GP, INC. (0.03)
TEXAS MATERIALS GROUP, INC. (27.98)
TRP CONSTRUCTION GROUP, LLC (3.75)
STRUCTURAL INTEGRITY GROUP LLC (0.41)
ROADWAY SPECIALTIES, INC. (1.08)
JT UNDERGROUND AND UTILITY CONSTRUCTION INC (0.00)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.17)
Contract #07213203
Totals19520129.83152424.0420922809.1499.9