Last Update: Friday, December 13, 2024
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings.
Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and
intended for informational purposes only.
|
|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 |
|
Text version of this page |
County: | FAYETTE | Let Date: | 11/07/24 |
Type: | SEAL COAT | Seq No: | 3204 |
Time: | 75 WORKING DAYS | Project ID: | C 26-3-49 |
Highway: | US 90 | Contract #: | 11243204 |
Length: | 385.586 | CCSJ: | 0026-03-049 |
Limits: | |
From: | 0.130 MI E OF SCHULTZ | Check: | $100,000 |
To: | COLORADO C/L | Misc Cost: | |
Text version of this page |
County: | NOLAN | Let Date: | 11/07/24 |
Type: | CONSTRUCT REST AREA | Seq No: | 3205 |
Time: | 324 WORKING DAYS | Project ID: | STP 2000(401)TP |
Highway: | IH 20 | Contract #: | 11243205 |
Length: | 1.340 | CCSJ: | 0006-03-121 |
Limits: | |
From: | FROM 0.7 MILES EAST OF CR 226 | Check: | $100,000 |
To: | 1.9 MILES EAST OF CR 226 | Misc Cost: | $550,000.00 |
Estimate | $44,172,100.10 | % Over/Under | Company |
Bidder 1 | $34,593,730.02 | -21.68% | FNF CONSTRUCTION, INC. |
Bidder 2 | $34,682,181.09 | -21.48% | A. L. HELMCAMP, INC. |
Bidder 3 | $36,990,900.00 | -16.26% | WEBBER, LLC |
Text version of this page |
County: | ROBERTSON | Let Date: | 11/07/24 |
Type: | BRIDGE REPLACEMENT | Seq No: | 3206 |
Time: | 360 WORKING DAYS | Project ID: | BR 2B24(086) |
Highway: | US 79 | Contract #: | 11243206 |
Length: | 0.762 | CCSJ: | 0204-09-045 |
Limits: | |
From: | AT LITTLE BRAZOS RIVER | Check: | $100,000 |
To: | . | Misc Cost: | |
Estimate | $19,385,140.90 | % Over/Under | Company |
Bidder 1 | $18,997,916.10 | -2.00% | LARRY YOUNG PAVING, INC. |
Bidder 2 | $19,105,990.35 | -1.44% | BIG CREEK CONSTRUCTION, LTD. |
Bidder 3 | $19,361,490.17 | -0.12% | TEXAS MATERIALS GROUP, INC. |
Bidder 4 | $22,839,973.97 | +17.82% | JAMES CONSTRUCTION GROUP, LLC |
Bidder 5 | $29,275,137.76 | +51.02% | MORTMARA CONSTRUCTION, INC. |
Text version of this page |
County: | MOORE | Let Date: | 11/07/24 |
Type: | SEAL COAT | Seq No: | 3207 |
Time: | 109 WORKING DAYS | Project ID: | C 66-5-81 |
Highway: | US 87 | Contract #: | 11243207 |
Length: | 0.000 | CCSJ: | 0066-05-081 |
Limits: | |
From: | FM 277 | Check: | $100,000 |
To: | WHEELER COUNTY LINE | Misc Cost: | |
Text version of this page |
County: | NACOGDOCHES | Let Date: | 11/07/24 |
Type: | SEAL COAT | Seq No: | 3208 |
Time: | 148 WORKING DAYS | Project ID: | F 2025(207) |
Highway: | SH 7 | Contract #: | 11243208 |
Length: | 0.000 | CCSJ: | 0059-01-062 |
Limits: | |
From: | SHELBY COUNTY LINE | Check: | $100,000 |
To: | SH 21 | Misc Cost: | |
Text version of this page |
County: | CONCHO | Let Date: | 11/07/24 |
Type: | GRADING, BASE, PAVING, STORM SEWER, TRAFFIC SIGNA | Seq No: | 3209 |
Time: | 289 WORKING DAYS | Project ID: | F 2B24(364) |
Highway: | US 83 | Contract #: | 11243209 |
Length: | 0.715 | CCSJ: | 0035-03-047 |
Limits: | |
From: | ON US 83 AND US 87 IN EDEN | Check: | $100,000 |
To: | US 87 | Misc Cost: | $115,000.00 |
Estimate | $9,625,756.34 | % Over/Under | Company |
Bidder 1 | $14,120,524.72 | +46.70% | 3LW CIVIL LLC |
Bidder 2 | $14,822,635.30 | +53.99% | CK NEWBERRY, LLC |
Bidder 3 | $16,913,435.61 | +75.71% | REECE ALBERT, INC. |
Text version of this page |
County: | TARRANT | Let Date: | 11/07/24 |
Type: | REHABILITATE BRIDGE | Seq No: | 3210 |
Time: | 299 WORKING DAYS | Project ID: | C 902-00-362 |
Highway: | VA | Contract #: | 11243210 |
Length: | 0.000 | CCSJ: | 0902-00-362 |
Limits: | |
From: | VARIOUS LOCATIONS | Check: | $100,000 |
To: | VARIOUS LOCATIONS | Misc Cost: | |
Estimate | $5,761,253.87 | % Over/Under | Company |
Bidder 1 | $5,157,489.52 | -10.48% | SCOTT TUCKER CONSTRUCTION COMPANY, LLC |
Bidder 2 | $5,749,766.36 | -0.20% | RAGLE CONSTRUCTION, INC. |
Bidder 3 | $5,952,823.06 | +3.33% | GIBSON & ASSOCIATES, INC. |
Bidder 4 | $6,291,258.00 | +9.20% | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC |
Bidder 5 | $7,983,353.00 | +38.57% | FNH CONSTRUCTION, LLC |
Text version of this page |
County: | HAYS | Let Date: | 11/07/24 |
Type: | HAZARD ELIMINATION & SAFETY | Seq No: | 3211 |
Time: | 213 WORKING DAYS | Project ID: | F 2025(198) |
Highway: | RM 3237 | Contract #: | 11243211 |
Length: | 0.000 | CCSJ: | 0805-04-039 |
Limits: | |
From: | RM 150 | Check: | $100,000 |
To: | RM 12 | Misc Cost: | |
Estimate | $6,105,602.64 | % Over/Under | Company |
Bidder 1 | $4,963,084.38 | -18.71% | DEAN WORD COMPANY, LTD. |
Bidder 2 | $5,542,963.13 | -9.22% | TEXAS MATERIALS GROUP, INC. |
Bidder 3 | $5,922,809.61 | -2.99% | HUNTER INDUSTRIES, LTD. |
Bidder 4 | $6,019,461.05 | -1.41% | AARON CONCRETE CONTRACTORS, LLC |
Bidder 5 | $6,137,126.56 | +0.52% | LONE STAR SITEWORK, LLC |
Bidder 6 | $6,492,643.20 | +6.34% | ALTUS CONSTRUCTION LLC |
Bidder 7 | $7,348,922.04 | +20.36% | DAN WILLIAMS COMPANY |
Text version of this page |
County: | ELLIS | Let Date: | 11/07/24 |
Type: | REHABILITATE EXISTING ROADWAY | Seq No: | 3212 |
Time: | 167 WORKING DAYS | Project ID: | C 1599-5-11 |
Highway: | FM 2258 | Contract #: | 11243212 |
Length: | 2.596 | CCSJ: | 1599-05-011 |
Limits: | |
From: | JOHNSON COUNTY LINE | Check: | $100,000 |
To: | FM 157 | Misc Cost: | |
Estimate | $5,268,123.10 | % Over/Under | Company |
Bidder 1 | $5,747,468.58 | +9.10% | KNIFE RIVER CORPORATION - SOUTH |
Bidder 2 | $5,860,136.02 | +11.24% | A. L. HELMCAMP, INC. |
Bidder 3 | $5,969,963.62 | +13.32% | ED BELL CONSTRUCTION COMPANY |
Bidder 4 | $6,291,596.95 | +19.43% | BIG CREEK CONSTRUCTION, LTD. |
Bidder 5 | $7,061,427.00 | +34.04% | FNH CONSTRUCTION, LLC |
Bidder 6 | $7,926,661.50 | +50.46% | CK NEWBERRY, LLC |
Text version of this page |
County: | HARRIS | Let Date: | 11/07/24 |
Type: | REHABILITATE BRIDGE | Seq No: | 3213 |
Time: | 298 WORKING DAYS | Project ID: | C 912-72-801 |
Highway: | VA | Contract #: | 11243213 |
Length: | 0.000 | CCSJ: | 0912-72-801 |
Limits: | |
From: | VARIOUS LOCATIONS IN NORTH HARRIS | Check: | $94,000 |
To: | . | Misc Cost: | |
Estimate | $4,715,636.00 | % Over/Under | Company |
Bidder 1 | $3,348,460.00 | -28.99% | GARRET SHIELDS INFRASTRUCTURE |
Bidder 2 | $3,489,769.20 | -26.00% | ISI CONTRACTING, INC. |
Bidder 3 | $3,673,829.60 | -22.09% | SCR CIVIL CONSTRUCTION, LLC |
Bidder 4 | $3,935,128.40 | -16.55% | SELECT MAINTENANCE, L.L.C. |
Bidder 5 | $4,192,785.60 | -11.09% | MC2 CIVIL, LLC |
Bidder 6 | $4,414,336.00 | -6.39% | B & MS CONSTRUCTION, INC. |
Bidder 7 | $4,886,576.00 | +3.62% | ROY JORGENSEN ASSOCIATES, INC. |
Bidder 8 | $4,900,936.80 | +3.93% | STRUCTURAL INTEGRITY GROUP LLC |
Bidder 9 | $4,959,408.00 | +5.17% | MB WESTERN INDUSTRIAL CONTRACTING CO. |
Bidder 10 | $6,437,626.80 | +36.52% | SOUTHERN ROAD & BRIDGE, LLC |
Text version of this page |
County: | TRAVIS | Let Date: | 11/07/24 |
Type: | RESURFACE ROADWAY | Seq No: | 3214 |
Time: | 70 WORKING DAYS | Project ID: | C 3136-1-190 |
Highway: | SL 1 | Contract #: | 11243214 |
Length: | 0.000 | CCSJ: | 3136-01-190 |
Limits: | |
From: | BARTON SPRINGS ROAD | Check: | $80,000 |
To: | SL 360 | Misc Cost: | |
Estimate | $4,018,784.61 | % Over/Under | Company |
Bidder 1 | $3,314,600.08 | -17.52% | HUNTER INDUSTRIES, LTD. |
Bidder 2 | $3,633,071.62 | -9.60% | LONE STAR PAVING COMPANY |
Bidder 3 | $4,409,183.45 | +9.71% | TEXAS MATERIALS GROUP, INC. |
Bidder 4 | $4,471,310.94 | +11.26% | CLARK CONSTRUCTION OF TEXAS, INC. |
Text version of this page |
County: | FAYETTE | Let Date: | 11/07/24 |
Type: | BRIDGE REPLACEMENT | Seq No: | 3215 |
Time: | 134 WORKING DAYS | Project ID: | BR 2025(220) |
Highway: | FM 153 | Contract #: | 11243215 |
Length: | 0.335 | CCSJ: | 0807-03-038 |
Limits: | |
From: | BIG PIN OAK CREEK | Check: | $61,000 |
To: | STR# 0807-03-008 | Misc Cost: | |
Estimate | $3,030,320.50 | % Over/Under | Company |
Bidder 1 | $2,524,149.82 | -16.70% | ACME BRIDGE COMPANY, INC. |
Bidder 2 | $2,917,986.60 | -3.71% | C. E. BARKER, LTD. |
Bidder 3 | $3,110,615.52 | +2.65% | DEAN WORD COMPANY, LTD. |
Bidder 4 | $3,118,300.18 | +2.90% | E-Z BEL CONSTRUCTION, LLC |
Bidder 5 | $3,379,406.00 | +11.52% | SKYLINE BRIDGE LLC |
Bidder 6 | $3,517,843.09 | +16.09% | TREVWAY, INC. |
Bidder 7 | $3,884,348.17 | +28.18% | YOKO EXCAVATING, LLC |
Bidder 8 | $3,919,297.05 | +29.34% | STX CIVIL |
Text version of this page |
County: | WILLIAMSON | Let Date: | 11/07/24 |
Type: | PREVENTIVE MAINTENANCE | Seq No: | 3217 |
Time: | 42 WORKING DAYS | Project ID: | C 1378-2-59 |
Highway: | RM 1431 | Contract #: | 11243217 |
Length: | 0.000 | CCSJ: | 1378-02-059 |
Limits: | |
From: | TRAVIS COUNTY LINE | Check: | $48,000 |
To: | US 183A | Misc Cost: | |
Text version of this page |
County: | MCCULLOCH | Let Date: | 11/07/24 |
Type: | PREVENTIVE MAINTENANCE | Seq No: | 3218 |
Time: | 53 WORKING DAYS | Project ID: | C 71-1-60 |
Highway: | US 87 | Contract #: | 11243218 |
Length: | 31.328 | CCSJ: | 0071-01-060 |
Limits: | |
From: | .5 MI S OF SH 71 | Check: | $65,000 |
To: | 1 MI. N OF SAN SABA RIVER | Misc Cost: | |
Estimate | $3,270,391.50 | % Over/Under | Company |
Bidder 1 | $3,936,577.18 | +20.37% | RONALD R. WAGNER & CO., LP |
Bidder 2 | $4,516,277.48 | +38.10% | ALLEN KELLER COMPANY |
Bidder 3 | $4,595,982.03 | +40.53% | CLARK CONSTRUCTION OF TEXAS, INC. |
Text version of this page |
County: | BOWIE | Let Date: | 11/07/24 |
Type: | BICYCLE AND PEDESTRIAN IMPROVEMENTS | Seq No: | 3219 |
Time: | 137 WORKING DAYS | Project ID: | STP 2022(680)TAPS |
Highway: | VA | Contract #: | 11243219 |
Length: | 0.000 | CCSJ: | 0919-19-088 |
Limits: | |
From: | SH 93 | Check: | $37,000 |
To: | ROBISON ROAD | Misc Cost: | |
Estimate | $1,848,087.75 | % Over/Under | Company |
Bidder 1 | $1,777,958.06 | -3.79% | THK CONSTRUCTION LLC |
Bidder 2 | $1,879,754.72 | +1.71% | TI-ZACK CONCRETE, LLC |
Bidder 3 | $1,883,359.00 | +1.91% | TATUM EXCAVATING COMPANY, INC. |
Bidder 4 | $1,983,451.50 | +7.32% | GARRET SHIELDS INFRASTRUCTURE |
Bidder 5 | $2,073,095.00 | +12.18% | FNH CONSTRUCTION, LLC |
Bidder 6 | $2,177,738.50 | +17.84% | LONGVIEW BRIDGE AND ROAD, LTD. |
Bidder 7 | $2,647,837.56 | +43.27% | C. E. BARKER, LTD. |
Bidder 8 | $2,950,254.00 | +59.64% | SKYLINE BRIDGE LLC |
Text version of this page |
County: | SMITH | Let Date: | 11/07/24 |
Type: | BRIDGE MAINTENANCE | Seq No: | 3220 |
Time: | 259 WORKING DAYS | Project ID: | C 910-00-142 |
Highway: | VA | Contract #: | 11243220 |
Length: | 0.000 | CCSJ: | 0910-00-142 |
Limits: | |
From: | VARIOUS LOCATIONS | Check: | $91,000 |
To: | IN THE TYLER DISTRICT | Misc Cost: | $25,000.00 |
Estimate | $4,536,200.00 | % Over/Under | Company |
Bidder 1 | $3,108,496.40 | -31.47% | OLYMPUS PAINTING CONTRACTORS, INC. |
Bidder 2 | $3,878,528.40 | -14.50% | M&J OF PINELLAS COUNTY, INC. |
Bidder 3 | $4,080,855.00 | -10.04% | SOUTHERN ROAD & BRIDGE, LLC |
Bidder 4 | $4,374,945.00 | -3.55% | RAGLE CONSTRUCTION, INC. |
Bidder 5 | $4,437,450.00 | -2.18% | GIBSON & ASSOCIATES, INC. |
Bidder 6 | $4,448,550.00 | -1.93% | MB WESTERN INDUSTRIAL CONTRACTING CO. |
Bidder 7 | $4,451,840.00 | -1.86% | SCOTT TUCKER CONSTRUCTION COMPANY, LLC |
Bidder 8 | $4,508,674.64 | -0.61% | THK CONSTRUCTION LLC |
Bidder 9 | $5,174,700.00 | +14.08% | FNH CONSTRUCTION, LLC |
Bidder 10 | $5,329,150.00 | +17.48% | RED BARON BUILDING COMPANY, LLC |