Detail Letting Schedule for Lamar County (FY 2001)
![]() |
![]() |
![]() |
![]() |
![]() |
Detail Letting Schedule for Lamar County (FY 2001) | ||||
Last Update: Friday, August 31, 2001 | ||||
Updated from Design & Construction Information System (DCIS) on: August 31, 2001 |
Lamar County (FY 2001) |
CCSJ: 0435-01-054 | |||
District: | Paris | Let Date: | NOV 2000 |
Highway: | FM 137 | Let Status: | Actual |
Project ID: | AR 435-1-54 | CSJ: | 0435-01-054 |
Description: | GRADING, STRUCTURES, BASE AND SURFACING | Handling Code: |
|
Limits From: | FM 38 | Fund Cat: | 8A |
Limits To: | US 82 | Estimate: | $2,774,169 |
Length: | 9.1 Miles | Actual: | $2,173,414 |
District: | Paris | Let Date: | NOV 2000 |
Highway: | FM 137 | Let Status: | Actual |
Project ID: | AR 749-1-45 | CSJ: | 0749-01-045 |
Description: | STRUCTURES, BASE AND SURFACING | Handling Code: |
|
Limits From: | FM 1184 | Fund Cat: | 8A |
Limits To: | FM 38 | Estimate: | $1,410,025 |
Length: | 5.4 Miles | Actual: | $1,207,636 |
District: | Paris | Let Date: | NOV 2000 |
Highway: | FM 824 | Let Status: | Actual |
Project ID: | AR 1154-1-16 | CSJ: | 1154-01-016 |
Description: | REHAB EXISTING ROADWAY | Handling Code: |
|
Limits From: | LAMAR COUNTY LINE | Fund Cat: | 8A |
Limits To: | FM 1550 INTERSECTION | Estimate: | $151,742 |
Length: | 0.6 Miles | Actual: | $151,741 |
District: | Paris | Let Date: | NOV 2000 |
Highway: | FM 824 | Let Status: | Actual |
Project ID: | AR 1154-2-13 | CSJ: | 1154-02-013 |
Description: | GRADING, STRUCTURES, BASE AND SURFACING | Handling Code: |
|
Limits From: | FM 137 | Fund Cat: | 8A |
Limits To: | FANNIN COUNTY LINE | Estimate: | $1,396,903 |
Length: | 6.5 Miles | Actual: | $1,184,171 |
Back... |
Totals for 0435-01-054 | ||
---|---|---|---|
Length: | 21.6 Miles | ||
Estimate: | $5,732,839 | ||
Actual: | $4,716,962 | ||
CCSJ: 0901-00-042 | |||
District: | Paris | Let Date: | JAN 2001 |
Highway: | VA | Let Status: | Actual |
Project ID: | C 901-00-42 | CSJ: | 0901-00-042 |
Description: | INSTALL PAVEMENT MARKERS /MARKINGS | Handling Code: |
|
Limits From: | VARIOUS LOCATIONS | Fund Cat: | 10A |
Limits To: | . | Estimate: | $888,601 |
Length: | 0.1 Miles | Actual: | $559,439 |
Back... |
Totals for 0901-00-042 | ||
Length: | 0.1 Miles | ||
Estimate: | $888,601 | ||
Actual: | $559,439 | ||
CCSJ: 0901-00-043 | |||
District: | Paris | Let Date: | AUG 2001 |
Highway: | VA | Let Status: | Actual |
Project ID: | C 901-00-43 | CSJ: | 0901-00-043 |
Description: | INSTALL PAVEMENT MARKERS /MARKINGS | Handling Code: |
|
Limits From: | VARIOUS LOCATIONS | Fund Cat: | 10A |
Limits To: | . | Estimate: | $425,491 |
Length: | 0.1 Miles | Actual: | $370,753 |
Award Status Bid Tabulations Back... |
Totals for 0901-00-043 | ||
Length: | 0.1 Miles | ||
Estimate: | $425,491 | ||
Actual: | $370,753 | ||
CCSJ: 0901-29-012 | |||
District: | Paris | Let Date: | AUG 2001 |
Highway: | VA | Let Status: | Approved |
Project ID: | STP 97(267)TE | CSJ: | 0901-29-012 |
Description: | RESTORE PARIS' SANTAFE RAILROAD DEPOT FOR OPERATION AS | Handling Code: |
LC |
Limits From: | BONHAM STREET (BUS 82) & 11TH SW | Fund Cat: | 4B |
Limits To: | 0.1 MI SOUTH | Estimate: | $1,268,603 |
Length: | 0.0 Miles | Actual: | |
Back... |
Totals for 0901-29-012 | ||
Length: | 0.0 Miles | ||
Estimate: | $1,268,603 | ||
Actual: | |||
CCSJ: 1690-01-097 | |||
District: | Paris | Let Date: | FEB 2001 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | STP 2001(181)HES | CSJ: | 1690-01-097 |
Description: | SAFETY LIGHTING | Handling Code: |
|
Limits From: | US 82/271 FROM PINE MILL | Fund Cat: | 4A |
Limits To: | 0.2 MI SOUTH OF BU 82H | Estimate: | $211,460 |
Length: | 0.6 Miles | Actual: | $230,337 |
Back... |
Totals for 1690-01-097 | ||
Length: | 0.6 Miles | ||
Estimate: | $211,460 | ||
Actual: | $230,337 |
Top... Back... Letting Schedule Doing Business with TxDOT |