| District: | Atlanta | Let Date: | MAY 2001 |
| Highway: | US 271 | Let Status: | Actual |
| Project ID: | CPM 248-5-43 | CSJ: | 0248-05-043 |
| Description: | RESURFACE EXISTING 4-LANE RURAL HIGHWAY | Handling Code: |
|
| Limits From: | 0.3 MI N OF FM 726 | Fund Cat: | 7 |
| Limits To: | GREGG COUNTY LINE | Estimate: | $868,651 |
| Length: | 4.5 Miles | Actual: | $902,005 |
|
Back... |
Totals for 0248-05-043 | ||
|---|---|---|---|
| Length: | 4.5 Miles | ||
| Estimate: | $868,651 | ||
| Actual: | $902,005 | ||
CCSJ: 0402-01-018 | |||
| District: | Atlanta | Let Date: | MAR 2001 |
| Highway: | SH 154 | Let Status: | Actual |
| Project ID: | CSR 402-1-18 | CSJ: | 0402-01-018 |
| Description: | REHABILITATE AND WIDEN EXISTING 2-LANE RURAL HIGHWAY | Handling Code: |
|
| Limits From: | FM 1650 | Fund Cat: | 14 |
| Limits To: | FM 726(W) | Estimate: | $1,742,492 |
| Length: | 3.5 Miles | Actual: | $1,501,622 |
| District: | Atlanta | Let Date: | MAR 2001 |
| Highway: | SH 154 | Let Status: | Actual |
| Project ID: | CSR 402-2-22 | CSJ: | 0402-02-022 |
| Description: | REHABILITATE AND WIDEN EXISTING 2-LANE RURAL HIGHWAY | Handling Code: |
|
| Limits From: | FM 726(W) | Fund Cat: | 14 |
| Limits To: | 0.1 MI. W. OF US 259 | Estimate: | $1,445,037 |
| Length: | 3.9 Miles | Actual: | $1,421,732 |
|
Back... |
Totals for 0402-01-018 | ||
| Length: | 7.4 Miles | ||
| Estimate: | $3,187,529 | ||
| Actual: | $2,923,354 | ||
CCSJ: 0520-05-035 | |||
| District: | Atlanta | Let Date: | FEB 2001 |
| Highway: | SH 155 | Let Status: | Actual |
| Project ID: | CPM 520-5-35 | CSJ: | 0520-05-035 |
| Description: | RESURFACE EXISTING 2-LANE RURAL HIGHWAY | Handling Code: |
|
| Limits From: | US 271 IN GILMER | Fund Cat: | 7 |
| Limits To: | US 259 NORTH OF ORE CITY | Estimate: | $4,923,623 |
| Length: | 14.6 Miles | Actual: | $4,348,840 |
|
Back... |
Totals for 0520-05-035 | ||
| Length: | 14.6 Miles | ||
| Estimate: | $4,923,623 | ||
| Actual: | $4,348,840 | ||