Detail Letting Schedule for Bell County (FY 2002)
![]() |
![]() |
![]() |
![]() |
![]() |
Detail Letting Schedule for Bell County (FY 2002) | ||||
Last Update: Thursday, September 5, 2002 | ||||
Updated from Design & Construction Information System (DCIS) on: August 30, 2002 |
Bell County (FY 2002) |
CCSJ: 0015-04-070 | |||
District: | Waco | Let Date: | MAR 2002 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | IM 35-4(208) | CSJ: | 0015-04-070 |
Description: | UPGRADE ILLUMINATION SYSTEM | Handling Code: |
|
Limits From: | SP 290 | Fund Cat: | 1 |
Limits To: | N OF LP 363 IN TEMPLE | Estimate: | $115,379 |
Length: | 0.8 Miles | Actual: | $55,736 |
District: | Waco | Let Date: | MAR 2002 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | IM 35-4(208) | CSJ: | 0015-06-076 |
Description: | UPGRADE ILLUMINATION SYSTEM | Handling Code: |
|
Limits From: | LP 121 | Fund Cat: | 1 |
Limits To: | FM 436 IN BELTON | Estimate: | $57,283 |
Length: | 1.4 Miles | Actual: | $47,933 |
District: | Waco | Let Date: | MAR 2002 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | IM 35-4(208) | CSJ: | 0015-14-111 |
Description: | UPGRADE ILLUMINATION SYSTEM | Handling Code: |
|
Limits From: | FM 436 IN BELTON | Fund Cat: | 1 |
Limits To: | SP 290 IN TEMPLE | Estimate: | $337,110 |
Length: | 10.6 Miles | Actual: | $284,589 |
District: | Waco | Let Date: | MAR 2002 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | MG 2002(321) | CSJ: | 0231-03-110 |
Description: | UPGRADE ILLUMINATION SYSTEM | Handling Code: |
|
Limits From: | WILLOW SPRINGS RD IN KILLEEN | Fund Cat: | 1 |
Limits To: | PADDY HAMILTON RD | Estimate: | $390,714 |
Length: | 11.9 Miles | Actual: | $321,723 |
District: | Waco | Let Date: | MAR 2002 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | MG 2002(321) | CSJ: | 0231-04-049 |
Description: | UPGRADE ILLUMINATION SYSTEM | Handling Code: |
|
Limits From: | PADDY HAMILTON RD | Fund Cat: | 1 |
Limits To: | W C/L OF BELTON | Estimate: | $200,690 |
Length: | 7.4 Miles | Actual: | $168,441 |
Back... |
Totals for 0015-04-070 | ||
---|---|---|---|
Length: | 32.1 Miles | ||
Estimate: | $1,101,176 | ||
Actual: | $878,422 | ||
CCSJ: 0184-02-042 | |||
District: | Waco | Let Date: | APR 2002 |
Highway: | SH 36 | Let Status: | Actual |
Project ID: | BR 2001(746) | CSJ: | 0184-02-042 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | 2.4 MI W OF FM 2409 | Fund Cat: | 10 |
Limits To: | 0.6 MI E OF OWL CREEK RD | Estimate: | $19,166,116 |
Length: | 2.0 Miles | Actual: | $19,984,243 |
Back... |
Totals for 0184-02-042 | ||
Length: | 2.0 Miles | ||
Estimate: | $19,166,116 | ||
Actual: | $19,984,243 | ||
CCSJ: 0231-03-109 | |||
District: | Waco | Let Date: | OCT 2001 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | CPM 231-3-109 | CSJ: | 0231-03-109 |
Description: | ASPHALTIC CONCRETE PAVEMENT OVERLAY AND TURN LANES | Handling Code: |
|
Limits From: | CLEAR CR RD | Fund Cat: | 1 |
Limits To: | INDIAN TRAIL IN HARKER HEIGHTS | Estimate: | $848,039 |
Length: | 1.1 Miles | Actual: | $963,955 |
District: | Waco | Let Date: | OCT 2001 |
Highway: | FM 2410 | Let Status: | Actual |
Project ID: | CPM 2304-2-29 | CSJ: | 2304-02-029 |
Description: | ASPHALTIC CONCRETE PAVEMENT OVERLAY | Handling Code: |
|
Limits From: | BS 190 | Fund Cat: | 1 |
Limits To: | US 190 | Estimate: | $452,495 |
Length: | 2.9 Miles | Actual: | $455,568 |
Back... |
Totals for 0231-03-109 | ||
Length: | 4.0 Miles | ||
Estimate: | $1,300,534 | ||
Actual: | $1,419,523 | ||
CCSJ: 0836-02-051 | |||
District: | Waco | Let Date: | JUL 2002 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | NH 2002(733) | CSJ: | 0231-03-111 |
Description: | CONSTRUCT RIGHT TURN LANES ON FRONTAGE ROADS | Handling Code: |
|
Limits From: | 0.1 MI W OF TRIMMIER RD | Fund Cat: | 1 |
Limits To: | 0.1 MI E OF TRIMMIER RD | Estimate: | $85,374 |
Length: | 0.2 Miles | Actual: | $123,225 |
District: | Waco | Let Date: | JUL 2002 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | NH 2002(733) | CSJ: | 0231-03-112 |
Description: | UPGRADE TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | 0.1 MI W OF TRIMMIER | Fund Cat: | 1 |
Limits To: | 0.1 MI E OF TRIMMIER | Estimate: | $118,729 |
Length: | 0.2 Miles | Actual: | $119,838 |
District: | Waco | Let Date: | JUL 2002 |
Highway: | FM 439 | Let Status: | Actual |
Project ID: | NH 2002(733) | CSJ: | 0836-02-051 |
Description: | REHABILITATION OF EXISTING SURFACE, ADD TURN LANES AND | Handling Code: |
|
Limits From: | 0.1 MI S OF FT HOOD E MAIN GATE | Fund Cat: | 1 |
Limits To: | 0.12 MI S OF US 190 | Estimate: | $993,902 |
Length: | 1.5 Miles | Actual: | $1,241,137 |
Back... |
Totals for 0836-02-051 | ||
Length: | 1.9 Miles | ||
Estimate: | $1,198,005 | ||
Actual: | $1,484,200 | ||
CCSJ: 0836-03-048 | |||
District: | Waco | Let Date: | JUL 2002 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | STP 2002(730)UM | CSJ: | 0055-08-095 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ INTER W/TEXAS CENTRAL | Fund Cat: | 1 |
Limits To: | PKWY IN WOODWAY | Estimate: | $144,661 |
Length: | 0.0 Miles | Actual: | $128,620 |
District: | Waco | Let Date: | JUL 2002 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | STP 2002(730)UM | CSJ: | 0162-01-082 |
Description: | UPGRADE OF TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | INTERS W/SP 299 | Fund Cat: | 1 |
Limits To: | INTERS W/ASHLEMAN IN WACO | Estimate: | $325,000 |
Length: | 0.4 Miles | Actual: | $297,927 |
District: | Waco | Let Date: | JUL 2002 |
Highway: | SH 317 | Let Status: | Actual |
Project ID: | STP 2002(730)UM | CSJ: | 0398-03-050 |
Description: | UPGRADE TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ INTERS W/FM 107 | Fund Cat: | 1 |
Limits To: | IN MOODY | Estimate: | $68,900 |
Length: | 0.0 Miles | Actual: | $62,780 |
District: | Waco | Let Date: | JUL 2002 |
Highway: | SH 317 | Let Status: | Actual |
Project ID: | STP 2002(730)UM | CSJ: | 0398-03-051 |
Description: | UPGRADE OF TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ INTERS W/3RD ST | Fund Cat: | 1 |
Limits To: | IN MCGREGOR | Estimate: | $83,460 |
Length: | 0.0 Miles | Actual: | $80,504 |
District: | Waco | Let Date: | JUL 2002 |
Highway: | FM 439 | Let Status: | Actual |
Project ID: | STP 2002(398)HES | CSJ: | 0836-03-048 |
Description: | MODERNIZE INTERSECTION FLASHING BEACON | Handling Code: |
|
Limits From: | @ ROY REYNOLDS RD | Fund Cat: | 8 |
Limits To: | . | Estimate: | $25,596 |
Length: | 0.1 Miles | Actual: | $22,728 |
District: | Waco | Let Date: | JUL 2002 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2002(730)UM | CSJ: | 0909-00-038 |
Description: | REFURBISH OVERHEAD FLASHING BEACONS | Handling Code: |
|
Limits From: | @ VARIOUS LOCATIONS | Fund Cat: | 1 |
Limits To: | DISTRICTWIDE | Estimate: | $325,228 |
Length: | 0.0 Miles | Actual: | $320,622 |
District: | Waco | Let Date: | JUL 2002 |
Highway: | FM 2410 | Let Status: | Actual |
Project ID: | STP 2002(398)HES | CSJ: | 2304-02-030 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ INTERS W/SCOTT & | Fund Cat: | 8 |
Limits To: | WHITE BLVD | Estimate: | $55,874 |
Length: | 0.1 Miles | Actual: | $50,742 |
Back... |
Totals for 0836-03-048 | ||
Length: | 0.6 Miles | ||
Estimate: | $1,028,719 | ||
Actual: | $963,923 | ||
CCSJ: 0909-36-090 | |||
District: | Waco | Let Date: | MAY 2002 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 99(623)OX | CSJ: | 0909-36-090 |
Description: | REPLACE BRIDGE AND APPROAHCES | Handling Code: |
|
Limits From: | ON CR 382 @ LITTLE RIVER | Fund Cat: | 6 |
Limits To: | . | Estimate: | $485,540 |
Length: | 0.2 Miles | Actual: | $411,793 |
Back... |
Totals for 0909-36-090 | ||
Length: | 0.2 Miles | ||
Estimate: | $485,540 | ||
Actual: | $411,793 | ||
CCSJ: 0909-36-091 | |||
District: | Waco | Let Date: | DEC 2001 |
Highway: | CS | Let Status: | Actual |
Project ID: | CUS 909-36-91 | CSJ: | 0909-36-091 |
Description: | WIDENING TO ADD LEFT TURN LANE, RESURFACE PAVEMENT & | Handling Code: |
LC |
Limits From: | ON 2ND ST FROM SH 317 | Fund Cat: | 13D |
Limits To: | 140' E OF EAST ST IN BELTON | Estimate: | $638,464 |
Length: | 0.1 Miles | Actual: | $704,719 |
District: | Waco | Let Date: | DEC 2001 |
Highway: | FM 93 | Let Status: | Actual |
Project ID: | CD 1835-1-17 | CSJ: | 1835-01-017 |
Description: | WIDENING TO ADD LEFT TURN LANE AND RESURFACING PAVEMENT | Handling Code: |
LC |
Limits From: | SH 317 | Fund Cat: | 11 |
Limits To: | PEARL STREET IN BELTON | Estimate: | $115,180 |
Length: | 0.0 Miles | Actual: | $188,759 |
Back... |
Totals for 0909-36-091 | ||
Length: | 0.1 Miles | ||
Estimate: | $753,644 | ||
Actual: | $893,478 | ||
CCSJ: 0909-36-098 | |||
District: | Waco | Let Date: | APR 2002 |
Highway: | CR | Let Status: | Actual |
Project ID: | MG 2002(297) | CSJ: | 0909-36-098 |
Description: | RECONSTRUCT COUNTY ROAD TO FIVE LANE URBAN ALONG CLEAR CR RD | Handling Code: |
|
Limits From: | ON SH 201 FR FM 3470 | Fund Cat: | 12 |
Limits To: | SH 195 | Estimate: | $14,295,635 |
Length: | 5.5 Miles | Actual: | $12,264,263 |
Back... |
Totals for 0909-36-098 | ||
Length: | 5.5 Miles | ||
Estimate: | $14,295,635 | ||
Actual: | $12,264,263 | ||
CCSJ: 0909-36-103 | |||
District: | Waco | Let Date: | JAN 2002 |
Highway: | CS | Let Status: | Actual |
Project ID: | STP 2001(938)RXH | CSJ: | 0909-36-103 |
Description: | UPGRADE RAILROAD CROSSING WARNING DEVICES | Handling Code: |
XX |
Limits From: | ON LELY RD @ INTERS OF BNSF RR | Fund Cat: | 8 |
Limits To: | IN TROY (DOT# 416173S) | Estimate: | $160,000 |
Length: | 0.0 Miles | Actual: | $160,000 |
Back... |
Totals for 0909-36-103 | ||
Length: | 0.0 Miles | ||
Estimate: | $160,000 | ||
Actual: | $160,000 |