SEP 2001 | OCT 2001 | NOV 2001 | DEC 2001 | JAN 2002 | FEB 2002 | MAR 2002 | APR 2002 | MAY 2002 | JUN 2002 | JUL 2002 | AUG 2002
CCSJ County/
District
Highway Let Status Contract
Cost
Fund
Cat
Description
0058-01-016 Anderson/
Tyler
SH 294 Actual $7,785,087 1 SEAL COAT & PAVEMENT MARKINGS
0199-07-010 Angelina/
Lufkin
LP 36 Actual $151,712 8 SAFETY TREAT FIXED OBJECTS
0913-20-044 Austin/
Yoakum
CR Actual $362,924 6 REPLACE BRIDGE AND APPROACHES
0100-08-080 Bee/
Corpus Christi
US 181 Actual $4,399,024 10 OVERLAY ROADWAY
0909-36-091 Bell/
Waco
CS Actual $893,478 11 WIDENING TO ADD LEFT TURN LANE, RESURFACE PAVEMENT &
0915-12-228 Bexar/
San Antonio
CS Actual $2,811,524 7 REHABILITATE & WIDEN NARROW PAVEMENT W / CLTL (SIDEWALKS)
0111-09-035 Brazoria/
Houston
BS 288B Actual $823,333 1 ACP OVERLAY WITH PAVEMENT MARKINGS
0598-03-019 Brazoria/
Houston
SH 288 Actual $3,774,598 12 GRADE SEPARATION
0049-12-062 Brazos/
Bryan
SH 6 Actual $1,546,523 1 OVERLAY CONSISTING OF PLACING A ONE COURSE SURFACE TREATMENT
0917-30-023 Burleson/
Bryan
CR Actual $210,994 6 REPLACEMENT OF EXISTING BRIDGE
0384-01-018 Caldwell/
Austin
SH 142 Actual $571,074 6 REPLACE BRIDGE & APPROACHES
0123-02-040 Cherokee/
Tyler
US 84 Actual $624,355 1 CLEAN AND SEAL BRIDGE JOINTS
0035-02-034 Concho/
San Angelo
US 83 Actual $4,838,120 1 SEAL COAT AND PAVEMENT MARKINGS
0183-04-041 Coryell/
Waco
SH 36 Actual $5,260,060 1 SEAL COAT
0261-02-055 Dallas/
Dallas
US 67 Actual $1,041,783 1 SOUTHBOUND RAMP REVERSAL
0918-00-057 Dallas/
Dallas
VA Actual $2,578,529 1 SEAL COAT AND STRIPING
0918-00-058 Dallas/
Dallas
VA Actual $3,552,518 1 SEAL COAT AND STRIPING
0918-45-608 Dallas/
Dallas
VA Actual $947,959 7 PRELIMINARY ENGINEERING FOR NEW LOCATION FACILITY
0136-04-038 Delta/
Paris
SH 24 Actual $1,545,234 1 SEAL COAT
0086-10-036 Duval/
Laredo
SH 359 Actual $204,372 11 CONSTRUCT RIGHT TURN LANE
2296-01-042 Ector/
Odessa
SH 191 Actual $2,888,481 1 REMOVE ACP AND PLACE SURFACE TREATMENT AND ACP, INCLUDES
0048-03-049 Ellis/
Dallas
US 77 Actual $12,928,674 11 WIDEN TO 4 - LANE SECTION WITH TWO - WAY LEFT TURN LANE
0902-49-024 Erath/
Fort Worth
CR Actual $756,546 6 REPLACE BRIDGE AND APPROACHES
0902-49-027 Erath/
Fort Worth
CR Actual $543,047 6 REPLACE BRIDGE
0174-03-034 Fannin/
Paris
SH 34 Actual $2,284,117 6 REPL BR & APPRS
0188-02-033 Fort Bend/
Houston
SH 36 Actual $7,325,697 1 SPOT BASE REPAIR, SURFACE REPAIR, PLANING, ACP OVERLAY &
0456-01-037 Freestone/
Bryan
FM 27 Actual $2,139,766 1 SEAL COAT CONSISTING OF A ONE COURSE SURFACE TREATMENT,
0153-02-033 Gonzales/
Yoakum
US 183 Actual $2,465,206 1 SEAL COAT
0045-19-035 Grayson/
Paris
US 82 Actual $1,786,975 1 SEAL COAT
0271-16-116 Harris/
Houston
IH 610 Actual $4,860,447 1 GRIND EXIST PAVEMENT ADD BONDED CONC OVERLAY F.R.'S
0500-03-482 Harris/
Houston
IH 45 Actual $2,709,173 6 WIDEN BRIDGE
0632-03-026 Harrison/
Atlanta
FM 134 Actual $376,035 6 REPLACE BRIDGE AND APPROACHES ON 2 LANE HIGHWAY
0471-02-037 Hays/
Austin
SH 21 Actual $3,465,112 1 WIDEN TO 4 LANES AND ADD SHOULDERS
0005-05-093 Howard/
Abilene
IH 20 Actual $8,507,298 1 SEAL COAT
0668-01-014 Howard/
Abilene
FM 700 Actual $1,660,581 1 RECONSTRUCT EXIT AND ENTRANCE RAMPS FOR ONE WAY FRONTAGE
0174-01-040 Hunt/
Paris
SH 34 Actual $1,894,113 1 SEAL COAT
0089-03-083 Jackson/
Yoakum
US 59 Actual $2,006,925 1 SEAL COAT
2367-01-040 Jefferson/
Beaumont
SH 82 Actual $452,700 10 REPAIR EROSION
0205-04-040 Leon/
Bryan
US 79 Actual $2,347,341 1 OVERLAY CONSISTING OF PAVEMENT REPAIRS, A ONE COURSE SURFACE
0382-05-012 Leon/
Bryan
SH 7 Actual $2,584,637 1 OVERLAY CONSISTING OF A ONE COURSE SURFACE TREATMENT, AN HMA
0813-01-089 Liberty/
Beaumont
FM 787 Actual $415,739 10 EXTEND BRIDGE, REPAIR EROSION AND ROAD
1229-04-009 Maverick/
Laredo
FM 375 Actual $4,030,815 1 RECONSTRUCT ROADWAY_AND ADD TURN LANE
0204-07-044 Milam/
Bryan
US 79 Actual $967,003 1 OVERLAY CONSISTING OF PAVEMENT REPAIRS, A ONE COURSE SURFACE
0917-12-044 Milam/
Bryan
CR Actual $593,661 6 REPLACE BRIDGE AND APPROACHES
0005-08-088 Mitchell/
Abilene
IH 20 Actual $146,000 1 CLEAN & PAINT STRUCTURE
0617-02-046 Nueces/
Corpus Christi
PR 22 Actual $37,749,621 7 TWO 12 FT LANES WITH 10 FT SHLDRS IN EACH DIRECTION
0904-04-006 Ochiltree/
Amarillo
CR Actual $5,784,448 6 REPLACE BRIDGE AND APPROACHES
0028-11-187 Orange/
Beaumont
IH 10 Actual $4,773,712 1 SEAL COAT
0902-38-025 Parker/
Fort Worth
CR Actual $696,811 6 REPLACE BRIDGE AND APPROACHES
0045-10-017 Red River/
Paris
FM 2573 Actual $2,430,537 1 SEAL COAT
0064-02-016 Shelby/
Lufkin
SH 147 Actual $8,259,985 1 SEAL COAT
0038-06-036 Starr/
Pharr
US 83 Actual $4,335,499 1 ACP OVERLAY
0011-09-060 Stephens/
Fort Worth
US 180 Actual $7,327,296 1 SEAL COAT
0022-01-028 Terrell/
Odessa
US 90 Actual $8,441,181 1 SEAL COAT
0734-01-025 Titus/
Atlanta
FM 127 Actual $904,182 6 REPLACE BRIDGE AND APPROACHES
0070-01-050 Tom Green/
San Angelo
FM 1223 Actual $3,805,240 1 SEAL COAT AND PAVEMENT MARKINGS
0114-01-045 Travis/
Austin
SP 69 Actual $6,259,105 7 RECONSTRUCT TO 4 - LN DIVIDED
1809-03-006 Walker/
Bryan
FM 1696 Actual $476,097 1 REHABILITATION OF EXISTING ROAD CONSISTING OF GRADING,
2850-01-014 Walker/
Bryan
FM 2821 Actual $1,133,331 1 MISCELLANEOUS CONSTRUCTION CONSISTING OF GRADING, STRUCTURES
0134-07-063 Wise/
Fort Worth
US 380 Actual $851,762 1 MILL EXISTING PAVEMENT AND OVERLAY 4 INCHES
0038-05-030 Zapata/
Pharr
US 83 Actual $1,682,294 1 SEAL COAT


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract



Top...
Back...
 
Letting Schedule
Doing Business with TxDOT