Letting Schedule for Laredo District (FY 2002)
![]() |
![]() |
![]() |
![]() |
![]() |
Letting Schedule for Laredo District (FY 2002) | ||||
Last Update: Thursday, September 5, 2002 | ||||
Updated from Design & Construction Information System (DCIS) on: August 30, 2002 |
Laredo District (FY 2002) |
Dimmit | Duval | La Salle | Maverick | Val Verde | Webb | Zavala | ||||||
Dimmit County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0300-03-050 | US 277 | Actual | FEB 2002 | $3,569,178 | 1 | FOR THE REHABILITATION OF AN EXISTING ROAD CONSISTING OF |
1813-01-006 | FM 1407 | Actual | SEP 2001 | $1,571,096 | 1 | FOR THE REHABILITATION OF AN EXISTING ROAD CONSISTING OF |
Duval County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0086-10-036 | SH 359 | Actual | DEC 2001 | $204,372 | 11 | CONSTRUCT RIGHT TURN LANE |
La Salle County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0017-08-067 | IH 35 | Actual | APR 2002 | $5,103,252 | 1 | RECONSTRUCT NORTHBOUND AND MILL AND OVERLAY SOUTHBOUND |
0018-10-007 | BI 35-B | Actual | APR 2002 | $6,827,374 | 1 | PREVENTIVE MAINTENANCE - OVERLAY (FY 2002) |
0852-01-024 | FM 469 | Actual | SEP 2001 | $1,615,497 | 1 | FOR THE REHABILITATION OF AN EXISTING ROAD CONSISTING OF |
0922-20-010 | CS | Actual | JAN 2002 | $210,000 | 8 | INSTALLATION OF RAILROAD SIGNALS |
Maverick County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
1229-04-009 | FM 375 | Actual | DEC 2001 | $4,030,815 | 1 | RECONSTRUCT ROADWAY_AND ADD TURN LANE |
Val Verde County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0022-06-043 | US 90 | Actual | APR 2002 | $3,529,949 | 1 | FOR THE CONSTRUCTION OF SEAL COAT TYPE WORK |
Webb County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0922-33-063 | VA | Actual | SEP 2001 | $1,208,113 | 1 | SIGN REFURBISHING |
0922-33-064 | VA | Actual | SEP 2001 | $739,527 | 1 | THERMOPLASTIC RE - STRIPING (FY 2001) - CAT 10A, CAT 2 |
0922-33-067 | CS | Actual | JAN 2002 | $240,000 | 8 | INSTALLATION OF RAILROAD SIGNALS |
0922-33-068 | CS | Actual | JAN 2002 | $160,000 | 8 | INSTALLATION OF RAILROAD SIGNALS |
0922-33-069 | CS | Actual | JAN 2002 | $240,000 | 8 | INSTALLATION OF RAILROAD SIGNALS |
2150-03-017 | FM 1472 | Actual | SEP 2001 | $1,981,245 | 1 | FOR THE CONSTRUCTION AND REHABILITATION OF AN EXISTING |
Zavala County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0037-02-043 | US 83 | Actual | FEB 2002 | $2,525,097 | 8 | MOD. BRIDGERAIL AND APPROACH, INSTALL PROTECTION AND |
1279-01-029 | FM 1025 | Actual | JAN 2002 | $672,447 | 1 | REPLACE BRIDGE AND APPROACHES |