Letting Schedule for San Angelo District (FY 2006)
Letting Schedule for San Angelo District (FY 2006) | ||||
Last Update: Monday, August 28, 2006 |
San Angelo District (FY 2006) |
Concho | Kimble | Reagan | Real | Runnels | Sutton | Tom Green | ||||||
Concho County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0035-03-042 | US 83 | Actual | NOV 2005 | $713,900 | 1 | RETRACE PAVEMENT MARKINGS |
Kimble County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0148-03-023 | US 377 | Actual | MAR 2006 | $7,934,581 | 1 | RESTORATION OF EXISTING ROAD |
2007-01-007 | FM 2169 | Actual | JUL 2006 | $3,154,644 | 1 | REPLACE STRUCTURES AT JOHNSON FORK CROSSINGS & REHAB ROADWAY |
Reagan County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0907-23-002 | VA | Actual | JUN 2006 | $1,832,429 | 10 | LANDSCAPE ESTABLISHMENT |
Real County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0036-03-024 | US 83 | Actual | JUL 2006 | $13,973,308 | 1 | GRADING, STRUCTURES, BASE AND SURFACING |
Runnels County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0034-03-016 | US 83 | Actual | JAN 2006 | $6,116,650 | 1 | SEAL COAT |
0034-06-010 | FM 2887 | Actual | AUG 2006 | $2,189,938 | 1 | RESTORE AND RESURFACE ROAD |
Sutton County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0141-04-033 | IH 10 | Actual | OCT 2005 | $1,038,531 | 1 | MILLING AND MICROSURFACING |
Tom Green County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0077-06-079 | US 67 | Actual | AUG 2006 | $17,407,114 | 11 | REHABILITATE & WIDEN EXISTING ROADWAY |
0077-06-084 | US 67 | Actual | JUN 2006 | $5,686,165 | 1 | ACP OVERLAY |
0907-00-068 | VA | Actual | DEC 2005 | $205,155 | 1 | CONSTRUCT PEDESTRIAN RAMPS |
|
|