Amarillo District (FY 2009) |
Armstrong | Deaf Smith | Hartley | Hemphill | Hutchinson | Moore | Ochiltree | Potter | Randall | Sherman | ||||||
Armstrong County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0042-03-038 | US 287 | Actual | APR 2009 | $8,895,225 | 1 | REHAB EXISTING ROADWAY |
Deaf Smith County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0168-05-033 | US 60 | Actual | MAR 2009 | $4,633,594 | 6 | REPLACE BRIDGE AND APPROACHES |
0168-07-039 | US 60 | Actual | JAN 2009 | $455,589 | 1 | OVERLAY AND ADD ACCEL / DECEL LANES |
Hartley County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0041-01-038 | US 87 | Actual | MAY 2009 | $3,824,417 | 1 | REHAB EXISTING ROADWAY (NBL) |
Hemphill County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0030-06-050 | US 83 | Actual | NOV 2008 | $8,965,395 | 1 | SEAL COAT |
Hutchinson County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0904-07-008 | CR | Actual | AUG 2009 | $289,229 | 6 | REPLACE BRIDGE & APPROACHES |
0904-07-010 | CR | Actual | MAY 2009 | $452,651 | 6 | REPLACE BRIDGE AND APPROACHES |
1623-02-016 | FM 1551 | Actual | AUG 2009 | $200,000 | 8 | 2009 FEDERAL RR SIGNAL PROGRAM |
Moore County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0425-02-029 | US 87 | Actual | AUG 2009 | $9,581,339 | 6 | RR GRADE SEPARATION |
Ochiltree County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0030-02-041 | US 83 | Actual | APR 2009 | $1,366,894 | 1 | REHAB EXISTING RDWY |
0030-03-022 | US 83 | Actual | MAR 2009 | $3,566,992 | 6 | REPLACE BRIDGE & APPROACHES |
Potter County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0275-01-154 | IH 40 | Actual | JAN 2009 | $3,427,716 | 1 | REHAB EXIST RDWY & UPG CONC BARRIER |
Randall County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0168-09-107 | IH 27 | Actual | NOV 2008 | $2,587,093 | 1 | REPLACE BRIDGE AND APPROACHES |
0168-09-154 | IH 27 | Actual | MAY 2009 | $1,563,365 | 1 | OVERLAY |
2635-03-013 | LP 335 | Actual | MAR 2009 | $363,322 | 11 | ADD TURN LANES, INSTALL TRAFFIC SIGNAL |
Sherman County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0066-02-023 | US 287 | Actual | JUL 2009 | $5,833,551 | 9 | REHAB EXIST RDWY, & ADD 2 ADDITIONAL LANES |
|
|