Letting Schedule for November, 2008 (FY 2009)
Letting Schedule for November, 2008 (FY 2009) | ||||
Last Update: Monday, November 9, 2009 |
November, 2008 (FY 2009) | (see Links) |
SEP 2008 | OCT 2008 | NOV 2008 | DEC 2008 | JAN 2009 | FEB 2009 | MAR 2009 | APR 2009 | MAY 2009 | JUN 2009 | JUL 2009 | AUG 2009 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0017-04-039 | Atascosa/ San Antonio |
IH 35 | Actual | $6,799,542 | 1 | SEAL COAT & PAVEMENT MARKINGS_ (FRONTAGE RDS) |
0088-01-053 | Bee/ Corpus Christi |
US 59 | Actual | $2,478,000 | 6 | REPLACE BRIDGE AND APPROACHES |
0915-12-447 | Bexar/ San Antonio |
CS | Actual | $582,231 | 10 | REPLACE BRIDGE AND APPROACHES |
0046-03-034 | Bowie/ Atlanta |
US 82 | Actual | $1,772,383 | 6 | REHABILITATE BRIDGE AND APPROACHES |
0046-05-045 | Bowie/ Atlanta |
US 82 | Actual | $5,499,012 | 1 | SEAL COAT |
0912-31-116 | Brazoria/ Houston |
CR | Actual | $1,474,840 | 6 | REPLACE BRIDGE |
0912-31-129 | Brazoria/ Houston |
CS | Actual | $2,326,203 | 6 | REPLACE BRIDGE AND APPROACHES |
0912-31-132 | Brazoria/ Houston |
CR | Actual | $2,739,208 | 6 | REPLACE BRIDGE AND APPROACHES |
0381-01-015 | Childress/ Childress |
US 62 | Actual | $4,832,008 | 1 | 2009 DISTRICTWIDE SEALCOAT |
0054-02-030 | Coleman/ Brownwood |
US 84 | Actual | $5,186,708 | 1 | SEAL COAT |
0035-03-044 | Concho/ San Angelo |
US 83 | Actual | $6,398,724 | 1 | SEAL COAT |
0918-00-153 | Dallas/ Dallas |
VA | Actual | $1,833,000 | 1 | FUNDS TRANSFER FOR VARIOUS ROUTINE ITS MAINTENANCE CONTRACTS |
0134-09-062 | Denton/ Dallas |
US 380 | Actual | $7,063,537 | 1 | SEALCOAT - DISTRICT NORTHERN SECTION |
0007-14-005 | Eastland/ Brownwood |
FM 2945 | Actual | $5,547,547 | 1 | SEAL COAT |
0005-01-100 | Ector/ Odessa |
BI 20-E | Actual | $14,475,763 | 1 | SEAL COAT |
2550-01-008 | Erath/ Fort Worth |
FM 2303 | Actual | $1,158,395 | 8 | SAFETY TREAT FIXED OBJECTS; WIDEN LANE & CONSTRUCT PAVED SHO |
3510-04-029 | Fort Bend/ Houston |
SH 99 | Actual | $698,662 | 5 | ADD 5 TURN LANES |
0071-06-056 | Gillespie/ Austin |
US 87 | Actual | $289,485 | 11 | SIDEWALK RAMPS |
0987-01-030 | Guadalupe/ San Antonio |
FM 621 | Actual | $1,243,644 | 1 | RECONSTRUCT EXISTING ROADWAY |
0030-06-050 | Hemphill/ Amarillo |
US 83 | Actual | $8,965,395 | 1 | SEAL COAT |
0028-07-051 | Jefferson/ Beaumont |
US 90 | Actual | $1,408,453 | 10 | LANDSCAPING AND OTHER SCENIC BEAUTIFICATION |
0642-05-020 | Kaufman/ Dallas |
FM 986 | Actual | $941,874 | 1 | REPLACE BRIDGE AND APPROACHES |
0072-05-084 | Kendall/ San Antonio |
IH 10 | Actual | $8,267,707 | 1 | SEAL COAT & PAVEMENT MARKINGS_ (FRONTAGE RDS) |
0005-02-102 | Midland/ Odessa |
BI 20-E | Actual | $206,397 | 1 | TRAFFIC SIGNALS |
3050-02-019 | Montgomery/ Houston |
FM 2978 | Actual | $277,188 | 5 | ADD LEFT TURN LANE |
0121-04-024 | Navarro/ Dallas |
SH 22 | Actual | $13,978,394 | 1 | SEALCOAT - DISTRICT SOUTHERN SECTION |
0006-15-032 | Nolan/ Abilene |
BI 20-M | Actual | $3,888,169 | 1 | SEAL COAT |
2239-01-021 | Panola/ Atlanta |
FM 2517 | Actual | $5,816,981 | 6 | REPLACE / WIDEN BRIDGES AND APPROACHES |
0168-09-107 | Randall/ Amarillo |
IH 27 | Actual | $2,587,093 | 1 | REPLACE BRIDGE AND APPROACHES |
0063-06-089 | Shelby/ Lufkin |
SH 87 | Actual | $7,260,383 | 1 | SEAL COAT |
0095-08-018 | Smith/ Tyler |
US 80 | Actual | $11,733,195 | 1 | SEAL COAT & PAVEMENT MARKINGS |
0013-10-072 | Tarrant/ Fort Worth |
BU 287P | Actual | $86,500 | 1 | INSTALLATION OF A FULL TRAFFIC - ACTUATED TRAFFIC SIGNAL |
0094-01-038 | Tarrant/ Fort Worth |
SH 183 | Actual | $1,800,035 | 1 | REPLACE HYDRAULICALLY INADEQUATE CULVERT |
0006-04-066 | Taylor/ Abilene |
IH 20 | Actual | $3,617,497 | 1 | SEAL COAT |
0271-04-083 | Waller/ Houston |
IH 10 | Actual | $2,623,136 | 11 | TEMPORARY RAMPS |
0921-27-027 | Willacy/ Pharr |
CR | Actual | $1,884,145 | 6 | REPLACE BRIDGE AND APPROACHES |
|
|