Letting Schedule for Wichita Falls District (FY 2009)
Letting Schedule for Wichita Falls District (FY 2009) | ||||
Last Update: Monday, November 9, 2009 |
Wichita Falls District (FY 2009) |
Archer | Baylor | Clay | Cooke | Montague | Wichita | Wilbarger | Young | ||||||
Archer County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0137-05-028 | SH 25 | Actual | APR 2009 | $3,147,193 | 1 | EXTEND CULVERTS AND ADD SHOULDERS |
Baylor County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0903-31-003 | CR | Actual | JUL 2009 | $288,509 | 6 | REPLACE BRIDGE AND APPROACHES |
Clay County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0224-02-042 | US 287 | Actual | MAR 2009 | $1,417,618 | 1 | HOT MIX OVERLAY |
0282-01-014 | SH 79 | Actual | JUN 2009 | $3,585,898 | 6 | REPLACE BRIDGE AND APPROACHES |
Cooke County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0194-02-088 | IH 35 | Actual | APR 2009 | $2,396,646 | 1 | HEAVY HOT MIX OVERLAY |
0312-01-060 | FM 51 | Actual | JUL 2009 | $1,009,655 | 6 | REPLACE BRIDGE AND APPROACHES |
0312-01-066 | FM 51 | Actual | JUN 2009 | $1,811,829 | 6 | REPLACE BRIDGE AND APPROACHES |
0845-03-048 | FM 922 | Actual | MAR 2009 | $870,379 | 6 | REPLACE BRIDGE AND APPROACHES |
1357-03-004 | FM 3496 | Actual | FEB 2009 | $1,033,965 | 1 | ADD SHOULDERS |
1855-01-021 | FM 2071 | Actual | MAY 2009 | $2,108,364 | 1 | ADD SHOULDERS |
Montague County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
1352-02-018 | FM 455 | Actual | JUL 2009 | $1,888,451 | 8 | ADD SHOULDERS |
Wichita County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0043-09-115 | US 287 | Actual | DEC 2008 | $6,514,295 | 1 | SEAL COAT |
0043-09-117 | US 287 | Actual | MAR 2009 | $1,730,097 | 1 | NOVACHIP |
0044-01-090 | US 287 | Actual | FEB 2009 | $1,141,767 | 1 | CONCRETE PATCH REPAIR |
0156-14-027 | BU 277A | Actual | JUN 2009 | $788,365 | 1 | "ULTRA THIN BONDED HOT MIX WEARING COURSE (UTBHMWC) " |
0903-00-059 | VA | Actual | MAR 2009 | $195,323 | 1 | BRIDGE MAINTENANCE AND REPAIR |
Wilbarger County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0043-07-104 | US 287 | Actual | APR 2009 | $2,590,421 | 1 | SEAL COAT AND HMAC OVERLAY |
0903-30-042 | CS | Actual | AUG 2009 | $6,400,000 | 8 | 2009 FEDERAL SIGNAL PROGRAM |
Young County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0903-27-019 | CR | Actual | JUN 2009 | $533,875 | 6 | REPLACE BRIDGE AND APPROACHES |
|
|