Detail Letting Schedule for Jim Wells County (FY 2010)

 
 
Last Update: Tuesday, November 2, 2010
Jim Wells County (FY 2010)

CCSJ: 0086-11-041

District: Corpus Christi Let Date: SEP 2009
Highway: SH 44 Let Status: Actual
Project ID: STP 2010(032)ES CSJ: 0086-11-041
Description: REHAB. EXISTING ROADWAY Handling
Code:
 
Limits From: VENTURA ST., IN SAN DIEGO, EAST Fund Cat: 1
Limits To: APPROX. 0.15 MI E OF FM 1554 CN Estimate: $4,861,139
Length: 8.7 Miles Actual: $3,776,702
 
Back...

Totals for 0086-11-041
Length: 8.7 Miles
Estimate: $4,861,139
Actual: $3,776,702

CCSJ: 0086-11-042

District: Corpus Christi Let Date: OCT 2009
Highway: SH 44 Let Status: Actual
Project ID: STP 2010(133)HES CSJ: 0086-11-042
Description: INSTALL TRAFFIC SIGNALS Handling
Code:
 
Limits From: ON SH44@INTERS. OF SH44 & US281 Fund Cat: 8
Limits To: . Estimate: $251,028
Length: 0.2 Miles Actual: $185,187
 
District: Corpus Christi Let Date: OCT 2009
Highway: SH 361 Let Status: Actual
Project ID: STP 2010(133)HES CSJ: 0180-10-072
Description: INSTALL TRAFFIC SIGNALS Handling
Code:
 
Limits From: ON SH361 @ INTER. WITH AVENUE J Fund Cat: 8
Limits To: . Estimate: $74,553
Length: 0.1 Miles Actual: $73,578
 
Back...

Totals for 0086-11-042
Length: 0.3 Miles
Estimate: $325,581
Actual: $258,765

CCSJ: 0916-37-025

District: Corpus Christi Let Date: MAY 2010
Highway: CR Let Status: Actual
Project ID: BR 2007(272) CSJ: 0916-37-025
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: STR (B00750001) KING ST @ SAN DIEGO Fund Cat: 6
Limits To: APPROX 1.2 MI N OF SH 44 Estimate: $767,272
Length: 0.1 Miles Actual: $687,033
 
Back...

Totals for 0916-37-025
Length: 0.1 Miles
Estimate: $767,272
Actual: $687,033


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract