Detail Letting Schedule for San Jacinto County (FY 2010)
Detail Letting Schedule for San Jacinto County (FY 2010) | ||||
Last Update: Tuesday, November 2, 2010 |
San Jacinto County (FY 2010) |
CCSJ: 0177-02-053 | |||
District: | Lufkin | Let Date: | FEB 2010 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2009(574)SB | CSJ: | 0177-02-053 |
Description: | UPGRADE TO FREEWAY FACILITY WITH 4 - LANE DIVIDED OVERPASS @ | Handling Code: |
|
Limits From: | SH 150 | Fund Cat: | 8 |
Limits To: | S OF UP RR | Estimate: | $41,965,660 |
Length: | 3.4 Miles | Actual: | $33,439,438 |
District: | Lufkin | Let Date: | FEB 2010 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | RW 177-2-72 | CSJ: | 0177-02-072 |
Description: | ACQUISITION, UTILITIES AND RELOCATION | Handling Code: |
NC |
Limits From: | AT UPRR IN SHEPHERD | Fund Cat: | 8 |
Limits To: | . | Estimate: | |
Length: | 0.0 Miles | Actual: | $683,821 |
Back... |
Totals for 0177-02-053 | ||
---|---|---|---|
Length: | 3.4 Miles | ||
Estimate: | $41,965,660 | ||
Actual: | $34,123,259 | ||
CCSJ: 0177-02-085 | |||
District: | Lufkin | Let Date: | SEP 2009 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2010(075)ES | CSJ: | 0177-02-085 |
Description: | MICROSURFACING | Handling Code: |
|
Limits From: | 0.61 MI S OF RR OVERPASS | Fund Cat: | 1 |
Limits To: | LIBERTY COUNTY LINE | Estimate: | $271,434 |
Length: | 5.3 Miles | Actual: | $243,279 |
District: | Lufkin | Let Date: | SEP 2009 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2010(075)ES | CSJ: | 0177-02-086 |
Description: | MICROSURFACING | Handling Code: |
|
Limits From: | TRINITY RIVER BRIDGE | Fund Cat: | 1 |
Limits To: | 0.13 MI N OF FM 1127 | Estimate: | $128,401 |
Length: | 2.5 Miles | Actual: | $115,017 |
District: | Lufkin | Let Date: | SEP 2009 |
Highway: | SH 103 | Let Status: | Actual |
Project ID: | STP 2010(075)ES | CSJ: | 0336-07-060 |
Description: | MICROSURFACING | Handling Code: |
|
Limits From: | FM 1751 | Fund Cat: | 1 |
Limits To: | SABINE COUNTY LINE | Estimate: | $205,640 |
Length: | 3.1 Miles | Actual: | $185,281 |
District: | Lufkin | Let Date: | SEP 2009 |
Highway: | SH 103 | Let Status: | Actual |
Project ID: | STP 2010(075)ES | CSJ: | 0336-08-024 |
Description: | MICROSURFACING | Handling Code: |
|
Limits From: | SAN AUGUSTINE COUNTY LINE | Fund Cat: | 1 |
Limits To: | 0.284 MI W OF SH 21 | Estimate: | $654,552 |
Length: | 9.3 Miles | Actual: | $592,967 |
District: | Lufkin | Let Date: | SEP 2009 |
Highway: | US 96 | Let Status: | Actual |
Project ID: | STP 2010(075)ES | CSJ: | 0809-03-034 |
Description: | MICROSURFACING | Handling Code: |
|
Limits From: | SHELBY COUNTY LINE | Fund Cat: | 1 |
Limits To: | 2.95 MI S OF SHELBY COUNTY LINE | Estimate: | $153,022 |
Length: | 2.9 Miles | Actual: | $139,092 |
Back... |
Totals for 0177-02-085 | ||
Length: | 23.1 Miles | ||
Estimate: | $1,413,049 | ||
Actual: | $1,275,636 | ||
CCSJ: 2594-02-011 | |||
District: | Lufkin | Let Date: | OCT 2009 |
Highway: | FM 3081 | Let Status: | Actual |
Project ID: | STP 2009(822)SB | CSJ: | 2594-02-011 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | 2.1 MI S OF FM 1725 | Fund Cat: | 8 |
Limits To: | BROWN STREET | Estimate: | $1,655,764 |
Length: | 5.0 Miles | Actual: | $1,120,845 |
Back... |
Totals for 2594-02-011 | ||
Length: | 5.0 Miles | ||
Estimate: | $1,655,764 | ||
Actual: | $1,120,845 |
|
|