Letting Schedule for February, 2010 (FY 2010)
| Letting Schedule for February, 2010 (FY 2010) | ||||
| Last Update: Tuesday, November 2, 2010 | 
| February, 2010 (FY 2010) | (see Links) | 
| SEP 2009 | OCT 2009 | NOV 2009 | DEC 2009 | JAN 2010 | FEB 2010 | MAR 2010 | APR 2010 | MAY 2010 | JUN 2010 | JUL 2010 | AUG 2010 | ||||||
| CCSJ | County/ District  | 
Highway | Let Status | Contract Cost  | 
Fund Cat  | 
Description | 
|---|---|---|---|---|---|---|
| 0109-01-055 | Anderson/ Tyler  | 
US 287 | Actual | $1,687,637 | 1 | REPAIR PAVEMENT & RESURFACE ROADWAY | 
| 0187-02-055 | Austin/ Yoakum  | 
SH 36 | Actual | $31,436,567 | 11 | ADD 2 - LANE FOR 4 - LANE DIVIDED FACILITY | 
| 0408-05-024 | Austin/ Yoakum  | 
FM 529 | Actual | $296,354 | 8 | SAFETY TREAT FIXED OBJECTS | 
| 0115-04-041 | Bastrop/ Austin  | 
FM 20 | Actual | $4,792,710 | 1 | WIDEN, REHAB, ADD TURN LANE & OVERLAY | 
| 0017-02-073 | Bexar/ San Antonio  | 
IH 35 | Actual | $924,077 | 1 | MILL, SEAL COAT, OVERLAY & PAVEMENT MARKINGS | 
| 0253-04-140 | Bexar/ San Antonio  | 
US 281 | Actual | $5,156,792 | 7 | OPERATIONAL IMPROVEMENTS AND RECONFIGURE INTERSECTIONS AT | 
| 0113-05-045 | Blanco/ Austin  | 
US 290 | Actual | $70,365 | 8 | INSTALL ADVANCE WARNING SIGNALS | 
| 0046-06-074 | Bowie/ Atlanta  | 
US 82 | Actual | $625,745 | 11 | RESURFACE EXISTING HIGHWAY | 
| 0912-31-225 | Brazoria/ Houston  | 
VA | Actual | $62,234 | 10 | LANDSCAPE DEVELOPMENT | 
| 0020-11-045 | Brewster/ El Paso  | 
US 67 | Actual | $6,089,377 | 1 | OVERLAY UPGRADE SIDEWALKS TO ADA STANDARDS | 
| 0054-06-092 | Brown/ Brownwood  | 
US 67 | Actual | $175,517 | 8 | RECONFIGURE INTERSECTION | 
| 3195-01-010 | Cass/ Atlanta  | 
FM 3129 | Actual | $3,898,849 | 6 | RAILROAD GRADE SEPARATION | 
| 0508-03-092 | Chambers/ Beaumont  | 
IH 10 | Actual | $2,184,620 | 1 | CONSTRUCT RAMPS FOR NEW TOURIST AND VISITOR CENTER AND MAKE | 
| 0915-17-056 | Comal/ San Antonio  | 
CS | Actual | $60,733 | 8 | CONSTRUCT SIDEWALKS, CROSSWALKS, AND MARKINGS | 
| 0070-05-023 | Concho/ San Angelo  | 
US 87 | Actual | $267,328 | 6 | REHABILITATE BRIDGE | 
| 0194-02-089 | Cooke/ Wichita Falls  | 
IH 35 | Actual | $1,103,629 | 1 | OVERLAY - PFC | 
| 0003-01-051 | Culberson/ El Paso  | 
IH 10 | Actual | $409,447 | 1 | MILL AND INLAY | 
| 0918-45-587 | Dallas/ Dallas  | 
VA | Actual | $809,298 | 5 | CONSTRUCT TRAIL EXTENSION TO EXISTING KATY TRAIL WITH | 
| 0918-45-640 | Dallas/ Dallas  | 
VA | Actual | $1,549,413 | 9 | CONSTRUCT PEDESTRIAN BRIDGE OVER IH635 (LBJ) TO DART STATION | 
| 0918-45-763 | Dallas/ Dallas  | 
VA | Actual | $268,100 | 7 | INTERSECTION IMPROVEMENTS | 
| 0918-45-772 | Dallas/ Dallas  | 
VA | Actual | $85,000 | 5 | ITS ARCHITECTURE DEVELOPMENT | 
| 0918-45-849 | Dallas/ Dallas  | 
CS | Actual | $145,000 | 7 | INSTALL ITS / TRAIN DETECTION | 
| 1068-04-151 | Dallas/ Dallas  | 
IH 30 | Actual | $592,144 | 1 | ACP OVERLAY OF EXISTING HIGHWAY AND LANDSCAPING | 
| 0042-06-064 | Donley/ Childress  | 
US 287 | Actual | $1,416,688 | 1 | OVERLAY | 
| 0237-06-037 | Duval/ Laredo  | 
SH 44 | Actual | $535,026 | 1 | RESTORATION OF MAINLANES | 
| 0007-04-109 | Eastland/ Brownwood  | 
IH 20 | Actual | $515,542 | 8 | INSTALL MEDIAN BARRIER | 
| 0924-00-069 | El Paso/ El Paso  | 
VA | Actual | $418,966 | 11 | RURAL STRIPING AND REFLECTORIZED PAVEMENT MARKINGS | 
| 7224-01-001 | El Paso/ El Paso  | 
RL BNSF | Actual | $1,200,000 | 1 | REHABILITATE EXISTING TRACK AND CONSTUCT 550 FEET OF | 
| 0543-02-047 | Fort Bend/ Houston  | 
FM 359 | Actual | $11,784,812 | 7 | RECONSTRUCT 2 LANES TO 4 LANES | 
| 1415-02-040 | Fort Bend/ Houston  | 
FM 1464 | Actual | $13,611,377 | 7 | WIDEN 2 LANES TO 4 LANES DIVIDED | 
| 0912-73-133 | Galveston/ Houston  | 
VA | Actual | $918,004 | 1 | COUNTYWIDE ASPHALT PAVEMENT REPAIR | 
| 0045-19-041 | Grayson/ Paris  | 
US 82 | Actual | $7,974,883 | 10 | WIDEN FROM 2 - LANE TO 4 - LANE, DIVIDED MEDIAN | 
| 2455-01-029 | Grayson/ Paris  | 
FM 1417 | Actual | $138,167 | 8 | ADD CONTINUOUS TWO WAY LEFT TURN LANE | 
| 0029-02-046 | Guadalupe/ San Antonio  | 
US 90 | Actual | $468,388 | 1 | MILL, SEAL COAT, OVERLAY & PAVEMENT MARKINGS | 
| 0215-09-026 | Guadalupe/ San Antonio  | 
FM 725 | Actual | $680,998 | 1 | BASE REPAIR, SEAL COAT, OVERLAY & PAVEMENT MARKINGS | 
| 0216-02-055 | Guadalupe/ San Antonio  | 
SH 46 | Actual | $76,621 | 8 | INSTALL INTERSECTION FLASHING BEACON | 
| 1659-02-008 | Hamilton/ Waco  | 
FM 1744 | Actual | $1,892,852 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | 
| 0389-13-052 | Harris/ Houston  | 
SH 146 | Actual | $4,118,845 | 1 | CONSTRUCT DIRECT CONNECTOR (RAMP E DC SB TO WB) | 
| 0912-00-389 | Harris/ Houston  | 
VA | Actual | $3,198,720 | 7 | REGIONAL VANPOOL PROGRAM (FY 2010) | 
| 0912-00-396 | Harris/ Houston  | 
VA | Actual | $2,000,000 | 7 | GCFRD - COMMUTER RAIL PE | 
| 0912-72-207 | Harris/ Houston  | 
CS | Actual | $22,739,821 | 7 | PHASE 1 - 5 PEDESTRIAN / TRANSIT IMPROVEMENTS | 
| 0912-72-237 | Harris/ Houston  | 
CS | Actual | $9,492,165 | 10 | PEDESTRIAN TRANSIT CONNECTION IMPROVEMENTS | 
| 0912-72-239 | Harris/ Houston  | 
CS | Actual | $15,877,126 | 7 | PEDESTRIAN TRANSIT CONNECTION IMPROVEMENTS (GREATER EAST END | 
| 0980-02-017 | Harris/ Houston  | 
FM 526 | Actual | $1,291,158 | 1 | FOR THE CONSTRUCTION OF ASPHALT CONCRETE PAVEMENT OVERLAY, | 
| 0495-08-093 | Harrison/ Atlanta  | 
IH 20 | Actual | $4,469,235 | 1 | RESURFACE EXISTING INTERSTATE FACILITY | 
| 0843-09-020 | Harrison/ Atlanta  | 
FM 2199 | Actual | $1,570,140 | 1 | REHABILITATE PAVEMENT ON EXISTING 2 LANE RURAL HIGHWAY | 
| 2642-02-022 | Harrison/ Atlanta  | 
LP 281 | Actual | $4,656,180 | 1 | REHABILITATE PAVEMENT ON EXISTING 4 LANE HIGHWAY | 
| 0285-03-048 | Hays/ Austin  | 
RM 12 | Actual | $998,761 | 7 | ADD CENTER TURN LANE | 
| 0471-02-061 | Hays/ Austin  | 
SH 21 | Actual | $694,868 | 10 | ADD LEFT TURN LANE & SHOULDERS | 
| 0656-01-037 | Hill/ Waco  | 
FM 67 | Actual | $1,063,330 | 8 | SAFETY TREAT FIXED OBJECTS | 
| 1282-01-015 | Hudspeth/ El Paso  | 
FM 1437 | Actual | $561,341 | 1 | SEAL COAT | 
| 0083-01-044 | Hunt/ Paris  | 
SH 11 | Actual | $4,231,611 | 8 | WIDEN FROM 2 - LANE WITHOUT SHOULDERS TO 5 - LANE WITH SHOULDERS | 
| 0355-06-034 | Hutchinson/ Amarillo  | 
SH 136 | Actual | $2,360,346 | 1 | SEAL COAT | 
| 0920-38-232 | Jefferson/ Beaumont  | 
VA | Actual | $119,510 | 10 | ILLUMINATION REPAIR & REPALCEMENT DUE TO DAMAGES CAUSED BY | 
| 0902-50-077 | Johnson/ Fort Worth  | 
VA | Actual | $1,324,712 | 9 | BURLESON PEDESTRIAN AND BICYCLE TRAIL CONNECTING SCHOOLS, | 
| 0018-02-053 | La Salle/ Laredo  | 
IH 35 | Actual | $989,979 | 1 | RESURFACE OF EXISTING ROADWAY | 
| 0338-12-002 | Liberty/ Beaumont  | 
SH 105 | Actual | $28,386,133 | 11 | CONSTRUCT 2 LANES OF A NEW 4 LANE ROADWAY | 
| 0053-01-115 | Lubbock/ Lubbock  | 
FM 835 | Actual | $3,387,881 | 1 | SEAL COAT | 
| 0933-01-033 | Lubbock/ Lubbock  | 
FM 835 | Actual | $417,993 | 8 | HAZARD ELIMINATION SAFETY | 
| 0300-01-075 | Maverick/ Laredo  | 
US 57 | Actual | $1,472,375 | 1 | RESURFACE OF EXISTING HIGHWAY | 
| 3624-01-001 | Midland/ Odessa  | 
SH 58 | Actual | $2,351,020 | 3 | NEW LOCATION NON - FREEWAY | 
| 0675-08-061 | Montgomery/ Houston  | 
IH 45 | Actual | $52,361,240 | 1 | WIDEN TO 8 MAIN LANES AND RECONSTRUCT 2 - LANE FRONTAGE ROADS | 
| 0028-11-195 | Orange/ Beaumont  | 
IH 10 | Actual | $38,315,248 | 3 | RECONSTRUCT EXISTING 4 - LANE FREEWAY FACILITY | 
| 0904-00-141 | Potter/ Amarillo  | 
VA | Actual | $717,973 | 1 | THERMOPLASTIC STRIPING | 
| 0003-05-048 | Reeves/ Odessa  | 
IH 20 | Actual | $3,460,027 | 1 | PAVEMENT OVERLAY | 
| 0177-02-053 | San Jacinto/ Lufkin  | 
US 59 | Actual | $34,123,259 | 8 | UPGRADE TO FREEWAY FACILITY WITH 4 - LANE DIVIDED OVERPASS @ | 
| 0916-28-053 | San Patricio/ Corpus Christi  | 
CS | Actual | $304,704 | 8 | CONSTRUCT APPROX 6, 417 FT, 6FT SIDEWALKS / SRTS | 
| 1549-04-027 | San Patricio/ Corpus Christi  | 
FM 1069 | Actual | $75,691 | 11 | SIGNAL IMPROVEMENTS | 
| 0190-05-059 | Smith/ Tyler  | 
US 69 | Actual | $85,858 | 11 | CONSTRUCT ENTRY GATE FEATURE | 
| 0191-03-078 | Smith/ Tyler  | 
FM 2493 | Actual | $737,750 | 1 | RESURFACE ROADWAY W / NOVA CHIP & IMPRV LP 323 INTERSECTION | 
| 0345-02-049 | Smith/ Tyler  | 
SH 110 | Actual | $382,262 | 8 | CONSTRUCT TWO - WAY CONTINUOUS OR LEFT TURN LANE | 
| 0902-48-728 | Tarrant/ Fort Worth  | 
VA | Actual | $1,662,500 | 5 | MOBILITY ASSISTANCE THROUGHOUT TARRANT COUNTY | 
| 0033-08-036 | Taylor/ Abilene  | 
BU 83-D | Actual | $1,147,451 | 1 | REPAIR BASE, UNDERSEAL, SURFACE | 
| 0555-05-021 | Tom Green/ San Angelo  | 
RM 853 | Actual | $371,489 | 1 | ASPHALT CONCRETE PAVEMENT OVERLAY | 
| 0113-09-067 | Travis/ Austin  | 
US 290 | Actual | $169,971 | 11 | INSTALL SIDEWALKS & PED SIGNALS | 
| 0113-13-106 | Travis/ Austin  | 
US 290 | Actual | $25,630,378 | 11 | CONST 4 REMAINING DIRECT CONNECTORS | 
| 0700-03-014 | Travis/ Austin  | 
SH 71 | Actual | $8,080,390 | 10 | INSTALL 14' CONTINUOUS LEFT TURN LANE AND 10' SHOULDERS | 
| 0914-00-013 | Travis/ Austin  | 
VA | Actual | $200,100 | 10 | COMMUNICATION DEVICES | 
| 0914-00-014 | Travis/ Austin  | 
VA | Actual | $300,100 | 10 | COMMUNICATION DEVICES | 
| 0914-04-261 | Travis/ Austin  | 
CR | Actual | $117,650 | 6 | REHAB BRIDGE | 
| 3136-01-167 | Travis/ Austin  | 
LP 1 | Actual | $3,569,639 | 1 | MILL, SEAL & THIN OVERLAY | 
| 0022-09-050 | Val Verde/ Laredo  | 
US 90 | Actual | $447,582 | 1 | RESURFACE OF EXISTING HIGHWAY | 
| 0108-01-027 | Van Zandt/ Tyler  | 
SH 19 | Actual | $2,263,994 | 1 | SEAL COAT & PAVEMENT MARKINGS | 
| 0495-02-060 | Van Zandt/ Tyler  | 
IH 20 | Actual | $2,243,290 | 1 | REPAIR & RESURFACE ROADWAY (EBL & WBL) | 
| 0038-01-066 | Webb/ Laredo  | 
US 83 | Actual | $1,570,274 | 1 | RESURFACE OF EXISTING HIGHWAY | 
| 0089-15-017 | Wharton/ Yoakum  | 
BU 59-S | Actual | $1,459,242 | 1 | PAVEMENT REPAIR AND ACP SURFACING | 
| 0240-02-029 | Wharton/ Yoakum  | 
SH 60 | Actual | $681,628 | 8 | SAFETY TREAT FIXED OBJECTS | 
| 1303-01-016 | Wharton/ Yoakum  | 
FM 1161 | Actual | $319,903 | 8 | SAFETY TREAT FIXED OBJECTS | 
| 0914-05-168 | Williamson/ Austin  | 
VA | Actual | $2,000,000 | 7 | TRANSIT TERMINAL SITE IMPROVEMENT | 
| 0134-02-053 | Young/ Wichita Falls  | 
SH 16 | Actual | $2,124,483 | 1 | MILL SURFACE AND FILL WITH HMAC | 
  | 
|   |