Detail Letting Schedule for Young County (FY 2018)
| Young County (FY 2018) |
CCSJ: 0133-08-035 |
|||
| District: | WICHITA FALLS | Let Date: | Nov 2017 |
| Highway: | SH 114 | Let Status: | Actual |
| Project ID: | NH 2018(249) | CSJ: | 0133-08-035 |
| Description: | SPOT MILL, BASE REPAIR & OVERLAY | Handling Code: | |
| Limits From: | FM 2178 NORTH | Fund Cat: | 1 |
| Limits To: | SL 132/S AVE M | ESTIMATE: | $447,751 |
| Length: | 1.0 | Actual | $409,068 |
| District: | WICHITA FALLS | Let Date: | Nov 2017 |
| Highway: | SH 79 | Let Status: | Actual |
| Project ID: | STP 2018(250) | CSJ: | 0283-05-013 |
| Description: | OVERLAY | Handling Code: | |
| Limits From: | ARCHER COUNTY LINE | Fund Cat: | 1 |
| Limits To: | NORTH END OF SPLIT | ESTIMATE: | $201,749 |
| Length: | 0.6 | Actual | $194,690 |
| District: | WICHITA FALLS | Let Date: | Nov 2017 |
| Highway: | SH 79 | Let Status: | Actual |
| Project ID: | STP 2018(250) | CSJ: | 0284-01-051 |
| Description: | OVERLAY | Handling Code: | |
| Limits From: | NORTH END OF SPLIT | Fund Cat: | 1 |
| Limits To: | SH 114 | ESTIMATE: | $527,491 |
| Length: | 1.2 | Actual | $465,778 |
| Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0133-08-035 | ||
|---|---|---|---|
| Length: | 2.8 | ||
| Estimate: | $1,176,990 | ||
| Actual: | $1,069,537 | ||
CCSJ: 1711-01-029 |
|||
| District: | WICHITA FALLS | Let Date: | Dec 2017 |
| Highway: | FM 1769 | Let Status: | Actual |
| Project ID: | STP 2017(404) | CSJ: | 1711-01-029 |
| Description: | REHAB, WIDEN & OVERLAY | Handling Code: | |
| Limits From: | SH 114 | Fund Cat: | 1 |
| Limits To: | US 380 | ESTIMATE: | $3,919,381 |
| Length: | 8.0 | Actual | $3,310,004 |
| Proposal Request Bid List List Showing Order Addenda Bid Tabulations Award Status Back... | Totals for 1711-01-029 | ||
| Length: | 8 | ||
| Estimate: | $3,919,381 | ||
| Actual: | $3,310,004 | ||
| Handling Code | Definition |
|---|---|
| XX | Project not processed through statewide letting |
| TR | Transfer of funds |
| LC | Project let through local entity |
| LC | Project not charged against district apportionment |
| Let Status | Definition |
|---|---|
| Tentative | Estimated letting date for this project |
| Approved | Project has administrative approval to be let |
| Actual | Project was let to contract |