Detail Letting Schedule for Cass County (FY 2022)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Cass County (FY 2022) |
CCSJ: 0062-04-051 |
|||
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0062-04-051 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT SH 155 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $67,426 |
Length: | 0.5 | Actual | $96,116 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0062-06-060 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT FM 2208 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $10,430 |
Length: | 1.0 | Actual | $9,424 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0062-06-061 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT SH 49 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $12,700 |
Length: | 0.5 | Actual | $10,732 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0062-07-099 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT SL 390 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $17,060 |
Length: | 1.0 | Actual | $13,802 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0062-07-100 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT POPLAR ST. | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $12,190 |
Length: | 1.0 | Actual | $10,389 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0062-07-101 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT SH 43 N. | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $8,475 |
Length: | 1.0 | Actual | $7,301 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0062-07-102 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT US 80 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $15,315 |
Length: | 0.5 | Actual | $14,334 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0063-01-097 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT HOUSTON ST. | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $18,091 |
Length: | 1.0 | Actual | $15,808 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0063-01-098 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT FM 31 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $37,840 |
Length: | 1.0 | Actual | $33,091 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0063-01-099 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT ELYSIAN FIELDS AVE. | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $13,910 |
Length: | 1.0 | Actual | $12,011 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0063-01-100 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT JOHNSON ST. | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $10,195 |
Length: | 1.0 | Actual | $8,924 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0063-01-101 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT SH 43 S. | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $14,165 |
Length: | 1.0 | Actual | $12,183 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0063-01-102 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT BELL ST. | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $12,470 |
Length: | 1.0 | Actual | $10,457 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0063-03-070 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT US 79 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $17,040 |
Length: | 1.0 | Actual | $14,459 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0063-04-066 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT FM 699 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $14,790 |
Length: | 1.0 | Actual | $12,494 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0063-04-067 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT SH 149 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $16,510 |
Length: | 0.5 | Actual | $14,116 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0218-01-101 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT FM 989 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $12,700 |
Length: | 1.0 | Actual | $10,732 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0218-01-102 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: | |
Limits From: | AT FM 2148 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $14,890 |
Length: | 1.0 | Actual | $12,592 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0218-01-103 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: | |
Limits From: | AT SL 151 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $50,941 |
Length: | 1.0 | Actual | $45,645 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | IH 369 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0218-02-053 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT US 82 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $18,475 |
Length: | 1.0 | Actual | $16,298 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | IH 369 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0218-02-054 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT US 67 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $18,340 |
Length: | 1.0 | Actual | $15,428 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0218-04-123 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT EMMA LENA WAY | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $11,870 |
Length: | 1.0 | Actual | $10,043 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0218-04-124 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: | |
Limits From: | AT SH 77 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $54,142 |
Length: | 1.0 | Actual | $49,194 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0218-04-125 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT FM 125 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $11,590 |
Length: | 1.0 | Actual | $9,975 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | US 271 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0248-02-068 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT SL 179 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $8,475 |
Length: | 1.0 | Actual | $7,301 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | SH 77 | Let Status: | Actual |
Project ID: | F 2022(516) | CSJ: | 0278-01-063 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT FM 251 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $12,190 |
Length: | 1.0 | Actual | $10,389 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | SH 154 | Let Status: | Actual |
Project ID: | F 2022(516) | CSJ: | 0401-04-039 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT FM 49 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $10,220 |
Length: | 1.0 | Actual | $8,820 |
District: | ATLANTA | Let Date: | Apr 2022 |
Highway: | SH 93 | Let Status: | Actual |
Project ID: | F 2022(515) | CSJ: | 0945-01-044 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT US 82 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $15,300 |
Length: | 0.0 | Actual | $12,837 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0062-04-051 | ||
---|---|---|---|
Length: | 25 | ||
Estimate: | $537,740 | ||
Actual: | $504,893 | ||
CCSJ: 0919-00-081 |
|||
District: | ATLANTA | Let Date: | Jan 2022 |
Highway: | VA | Let Status: | Actual |
Project ID: | F 2022(293) | CSJ: | 0919-00-081 |
Description: | HIGHWAY IMPROVEMENT | Handling Code: | |
Limits From: | VARIOUS LOCATIONS | Fund Cat: | 1 |
Limits To: | VARIOUS LOCATIONS | ESTIMATE: | $1,146,416 |
Length: | 0.3 | Actual | $934,909 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0919-00-081 | ||
Length: | 0.3 | ||
Estimate: | $1,146,416 | ||
Actual: | $934,909 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |