Detail Letting Schedule for Gregg County (FY 2022)

Last Update: Wednesday, June 09, 2021

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Gregg County (FY 2022)

CCSJ: 0910-07-072

District:TYLERLet Date:Mar 2022
Highway:CSLet Status:Tentative
Project ID:BR 2018(505)CSJ:0910-07-072
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:AT UPRR AND SABINE STFund Cat:6
Limits To:STR #001, IN LONGVIEWESTIMATE:$5,693,140
Length:0.0Actual$0
 
Back...
Totals for 0910-07-072
Length:0
Estimate:$5,693,140
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract