Detail Letting Schedule for Kerr County (FY 2022)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Kerr County (FY 2022) |
CCSJ: 0142-03-031 |
|||
District: | SAN ANTONIO | Let Date: | Feb 2022 |
Highway: | SH 27 | Let Status: | Actual |
Project ID: | BR 2022(335) | CSJ: | 0142-03-031 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | AT FESSENDEN BRANCH | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $1,477,040 |
Length: | 0.1 | Actual | $1,836,910 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0142-03-031 | ||
---|---|---|---|
Length: | 0.1 | ||
Estimate: | $1,477,040 | ||
Actual: | $1,836,910 | ||
CCSJ: 0291-03-076 |
|||
District: | SAN ANTONIO | Let Date: | May 2022 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 2022(403)HES | CSJ: | 0291-03-076 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.1 MI NORTH OF THOMPSON DR | Fund Cat: | 8 |
Limits To: | 0.1 MI SOUTH OF THOMPSON DR | ESTIMATE: | $282,428 |
Length: | 0.2 | Actual | $283,894 |
District: | SAN ANTONIO | Let Date: | May 2022 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 2022(403)HES | CSJ: | 0291-04-027 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.25 MI NORTH OF FM 2107 | Fund Cat: | 8 |
Limits To: | 0.45 MI SOUTH OF MESA VERDE RD | ESTIMATE: | $277,628 |
Length: | 2.8 | Actual | $234,855 |
District: | SAN ANTONIO | Let Date: | May 2022 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 2022(403)HES | CSJ: | 0291-06-059 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | ROBINDALE W | Fund Cat: | 8 |
Limits To: | FM 1283 | ESTIMATE: | $183,185 |
Length: | 7.6 | Actual | $192,439 |
District: | SAN ANTONIO | Let Date: | May 2022 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 2022(403)HES | CSJ: | 0291-08-026 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.2 MI SOUTH OF SILVER SPGS | Fund Cat: | 8 |
Limits To: | 0.5 MI NORTH OF CR188 | ESTIMATE: | $69,295 |
Length: | 1.9 | Actual | $86,546 |
District: | SAN ANTONIO | Let Date: | May 2022 |
Highway: | RM 187 | Let Status: | Actual |
Project ID: | STP 2022(403)HES | CSJ: | 0678-02-041 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 2.0 MI NORTH OF KELLY RANCH RD | Fund Cat: | 8 |
Limits To: | SABINAL ROAD | ESTIMATE: | $576,511 |
Length: | 22.0 | Actual | $496,300 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0291-03-076 | ||
Length: | 34.5 | ||
Estimate: | $1,389,047 | ||
Actual: | $1,294,034 | ||
CCSJ: 0915-15-097 |
|||
District: | SAN ANTONIO | Let Date: | Oct 2021 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2021(064) | CSJ: | 0915-15-097 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | WITT ROAD | Fund Cat: | 6 |
Limits To: | AT VERDE CREEK | ESTIMATE: | $675,946 |
Length: | 0.1 | Actual | $596,018 |
Proposal Request Bid List List Showing Order Addenda Bid Tabulations Award Status Back... | Totals for 0915-15-097 | ||
Length: | 0.1 | ||
Estimate: | $675,946 | ||
Actual: | $596,018 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |