Letting Schedule for Abilene District (FY 2022)

Last Update: Tuesday, May 11, 2021

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Abilene District (FY 2022)
Borden | Callahan | Haskell | Howard | Jones | Kent | Nolan | Scurry | Stonewall | Taylor |

Borden County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1155-04-013FM 1785TentativeAug 2022$2,462,0448WIDEN ROAD - ADD SHOULDERS0.0

Callahan County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0974-02-017FM 604TentativeDec 2021$9,731,9671SEAL COAT0.0

Haskell County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0157-04-057US 277TentativeJan 2022$6,000,0001PREVENTIVE MAINTENANCE0.0

Howard County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1872-02-019FM 846TentativeFeb 2022$759,2498INSTALL/REPLACE SIGNS0.0
0668-02-022FM 700TentativeJan 2022$400,0001INSTALL TRAFFIC SIGNAL0.0

Jones County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0484-01-025FM 707TentativeJan 2022$2,108,1676BRIDGE REPLACEMENT0.0

Kent County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
2011-02-015SH 208TentativeAug 2022$7,000,0006BRIDGE REPLACEMENT0.0

Nolan County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0264-01-045SH 70TentativeDec 2021$10,000,0001REHABILITATE EXISTING ROADWAY0.0
0006-02-114IH 20TentativeAug 2022$70,000,0001INTERCHANGE IMPROVEMENT (NEW OR UPDATE)0.0

Scurry County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0296-01-038US 180TentativeJan 2022$7,400,0001REHABILITATE EXISTING ROADWAY0.0

Stonewall County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0106-04-036US 380TentativeAug 2022$15,189,0406BRIDGE REPLACEMENT0.0

Taylor County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0908-00-109VATentativeDec 2021$2,500,0001PREVENTIVE MAINTENANCE0.0
0908-00-108VATentativeNov 2021$2,000,00011FURNISH & INSTALL DYNAMIC MESSAGE SIGNS0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract