The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Stonewall County (FY 2022)

CCSJ: 0032-07-029

District:ABILENELet Date:Jan 2022
Highway:US 83Let Status:Approved
Project ID:STP 1302(057)CSJ:0032-07-029
Description:WIDEN ROAD - ADD LANESHandling
Code:
 
Limits From:KING COUNTY LINEFund Cat:1
Limits To:US 380ESTIMATE:$18,291,358
Length:15.5Actual$0
 
District:ABILENELet Date:Jan 2022
Highway:US 83Let Status:Approved
Project ID:STP 1302(057)CSJ:0106-05-030
Description:WIDEN ROAD - ADD LANESHandling
Code:
 
Limits From:US 380Fund Cat:1
Limits To:NORTH OF ASPERMONTESTIMATE:$1,086,741
Length:2.0Actual$0
 
Back...
Totals for 0032-07-029
Length:17.5
Estimate:$19,378,099
Actual:

CCSJ: 0033-01-038

District:ABILENELet Date:Jan 2022
Highway:US 83Let Status:Approved
Project ID:STP 1302(058)CSJ:0033-01-038
Description:WIDEN ROAD - ADD LANESHandling
Code:
 
Limits From:US 380Fund Cat:1
Limits To:FISHER COUNTY LINEESTIMATE:$11,602,029
Length:13.1Actual$0
 
District:ABILENELet Date:Jan 2022
Highway:US 83Let Status:Approved
Project ID:STP 1302(058)CSJ:0033-02-017
Description:WIDEN ROAD - ADD LANESHandling
Code:
 
Limits From:STONEWALL COUNTY LINEFund Cat:1
Limits To:JONES COUNTY LINEESTIMATE:$1,653,059
Length:1.6Actual$0
 
District:ABILENELet Date:Jan 2022
Highway:US 83Let Status:Approved
Project ID:STP 1302(058)CSJ:0033-03-026
Description:WIDEN ROAD - ADD LANESHandling
Code:
 
Limits From:FISHER COUNTY LINEFund Cat:1
Limits To:HAMLIN CITY LIMITESTIMATE:$958,261
Length:3.6Actual$0
 
Back...
Totals for 0033-01-038
Length:18.3
Estimate:$14,213,349
Actual:

CCSJ: 0106-04-036

District:ABILENELet Date:Aug 2022
Highway:US 380Let Status:Tentative
Project ID:BR ( )CSJ:0106-04-036
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:SALT FORK BRAZOS RIVERFund Cat:6
Limits To:.ESTIMATE:$15,189,040
Length:0.0Actual$0
 
District:ABILENELet Date:Aug 2022
Highway:SH 208Let Status:Tentative
Project ID:BR ( )CSJ:2011-02-015
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:SALT FORK BRAZOS RIVERFund Cat:6
Limits To:.ESTIMATE:$7,000,000
Length:0.0Actual$0
 
Back...
Totals for 0106-04-036
Length:0
Estimate:$22,189,040
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract