Letting Schedule for Lufkin District (FY 2022)

Last Update: Monday, October 18, 2021

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Lufkin District (FY 2022)
Angelina | Houston | Nacogdoches | Polk | Sabine | San Augustine | San Jacinto | Shelby | Trinity |

Angelina County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0176-02-118US 59TentativeJun 2022$48,504,0001HIGHWAY IMPROVEMENT0.0
0911-00-079VAActualSep 2021$1,971,2781HIGHWAY IMPROVEMENT0.0
0911-00-117VAApprovedNov 2021$499,79811BRIDGE MAINTENANCE0.0
0911-00-122VATentativeApr 2022$1,000,0001BRIDGE MAINTENANCE0.0
0336-03-072SH 103TentativeApr 2022$5,280,7598HAZARD ELIMINATION & SAFETY0.0
3264-01-010FM 326TentativeApr 2022$1,600,0001ROADWAY REHABILITATION/RECONSTRUCTION WITH NO ADDED CAPACITY0.0
0911-00-119VATentativeMar 2022$586,5206BRIDGE MAINTENANCE0.0

Houston County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0340-01-046US 287ActualSep 2021$7,83610EMERGENCY RELIEF0.0
0911-28-048CRTentativeJul 2022$1,131,1006BRIDGE REPLACEMENT0.0
0118-02-040SH 21ActualSep 2021$812,20810EMERGENCY RELIEF0.0
0117-06-047SH 21TentativeApr 2022$14,648,7006BRIDGE REPLACEMENT0.0
0335-02-035SH 7TentativeJun 2022$14,000,0006BRIDGE REPLACEMENT0.0
0937-03-022FM 227ActualSep 2021$22,12210EMERGENCY RELIEF0.0

Nacogdoches County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
3248-01-007FM 1878TentativeMay 2022$4,875,6541ROADWAY REHABILITATION/RECONSTRUCTION WITH NO ADDED CAPACITY0.0
0118-08-075SH 21ApprovedJan 2022$2,165,7026BRIDGE REPLACEMENT0.0
0706-05-014FM 95ActualSep 2021$6,00910EMERGENCY RELIEF0.0

Polk County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0176-04-056US 59TentativeMay 2022$163,100,00111HIGHWAY IMPROVEMENT0.0
0911-04-089CRTentativeJun 2022$675,0006BRIDGE REPLACEMENT0.0

Sabine County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0304-03-028SH 87TentativeMar 2022$423,1801RESURFACE ROADWAY0.0

San Augustine County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0809-04-057US 96ApprovedDec 2021$4,257,3691REHABILITATE EXISTING ROADWAY0.0
0064-04-043SH 21ApprovedNov 2021$9,698,2541RESURFACE ROADWAY0.0

San Jacinto County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0177-02-095US 59ApprovedJan 2022$1,500,0001HIGHWAY IMPROVEMENT0.0

Shelby County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0304-01-032SH 87ActualOct 2021$476,7718HIGHWAY IMPROVEMENT0.0
0059-04-049SH 7ActualOct 2021$371,9891REPAIR ROADWAY4.0
0911-39-063CRTentativeJun 2022$675,0006BRIDGE REPLACEMENT0.0
2893-01-018FM 947TentativeAug 2022$1,911,1828HAZARD ELIMINATION & SAFETY0.0
0742-01-058FM 139ActualSep 2021$8,78010EMERGENCY RELIEF0.0
2700-01-021FM 2694ActualSep 2021$64,02710EMERGENCY RELIEF0.0
2700-01-022FM 2694ActualSep 2021$6,36510EMERGENCY RELIEF0.0

Trinity County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
2117-02-015FM 357ApprovedNov 2021$1,301,8241BRIDGE REPLACEMENT4.0
0931-04-034FS 357TentativeAug 2022$1,327,1398HAZARD ELIMINATION & SAFETY0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract